09/BC/PIU/USIDCL/PB/2015-16
Agreement signed
|
Project: |
UDRP-H |
Package No.: |
2259 |
Package Name: |
09/BC/PIU/USIDCL/PB/2015-16 |
Sanction Cost: |
1208.00 lakhs |
District: |
Pauri |
Block: |
Khirsu |
Constituency: |
Pauri |
Circle: |
|
DEA: |
DEA PB |
DSC: |
SOWil Limited |
DSC Scope: |
Design and Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 7319 Ladies Police Station, Srinagar (0.000 KM.) (completed) |
|
Procurement: |
Package No.: 2259
Package Name: 09/BC/PIU/USIDCL/PB/2015-16
Tender Date: 09-11-2015
Current Status: Agreement signed
Achieved on Date: 28-03-2016 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: 09/BC/PIU/USIDCL/PB/2015-16
Contractor Name: Makin Developers Pvt. Ltd.
|
Start Date: 01-04-2016
Intended Completion Date: 31-03-2018
Original End Date: 31-08-2017
|
Total Bond Cost: 108421569 (1084.22 lakhs)
Variation Cost: -12159764.83 (-121.6 lakhs) Hence Total Bond Cost is 96261804.17 (962.62 lakhs)
|
LD Analysis for Milestone1: calculated LD is Rs 8294283 for +153 days
LD Analysis for Milestone2: calculated LD is Rs 26129702 for 482 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Site Development | 15.87 Job | 152.77 | 15.87 Job | 15.87 Job | 15.87 | 152.77 | 2. | Foundation and Plinth Work | 14.53 Job | 139.87 | 14.53 Job | 14.53 Job | 14.53 | 139.87 | 3. | Structural Frame | 29.87 Job | 287.53 | 29.87 Job | 29.87 Job | 29.87 | 287.53 | 4. | Doors & Windows | 11.26 Job | 108.39 | 11.26 Job | 11.26 Job | 11.26 | 108.39 | 5. | Water Supply and Sanitary work | 3.40 Job | 32.73 | 3.40 Job | 3.40 Job | 3.4 | 32.73 | 6. | Electrification Works | 10.34 Job | 99.53 | 10.34 Job | 10.34 Job | 10.34 | 99.53 | 7. | Other Allied Works & Finishing Work | 14.73 Job | 141.79 | 14.73 Job | 14.73 Job | 14.73 | 141.79 |
Total Amount: |
962.61 |
|
100 |
962.61 |
|
Remarks:
No Remarks
Work Program Made On:
04-05-2016
Updation of work program on:
11-07-2019
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 13-July-2016 | 10.61 lakhs |
2. | 20-September-2016 | 49.86 lakhs |
3. | 27-October-2016 | 42.46 lakhs |
4. | 20-December-2016 | 73.54 lakhs |
5. | 24-January-2017 | 34.52 lakhs |
6. | 25-March-2017 | 63.37 lakhs |
7. | 03-May-2017 | 49.10 lakhs |
8. | 25-May-2017 | 54.49 lakhs |
9. | 30-June-2017 | 24.19 lakhs |
10. | 29-September-2017 | 38.84 lakhs |
11. | 25-January-2018 | 131.15 lakhs |
12. | 15-March-2018 | 94.73 lakhs |
13. | 23-May-2018 | 155.49 lakhs |
14. | 21-August-2018 | 23.28 lakhs |
15. | 03-December-2018 | 116.97 lakhs |
Total |
962.6 lakhs |
% Payment |
100 % |
|
Advance Amount: 19.15 lakhs
Recovered Amount: 19.15 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 133 |
Number of Notice(s) issued: 50 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 24-02-2019 | Ladies police station srinagar | Inaguration | Praveen Negi | JE | UDRP-PB Pauri | See Pic |
2. | 24-02-2019 | Ladies police station | Inaguration of Ladies police station srinagar | Praveen Negi | JE | UDRP-PB Pauri | See Pic |
3. | 25-03-2018 | Srinagar | VDF flooring in Fire Station. | Manjeet Deshwal | RE | UDRP-H Pauri | See Pic |
4. | 25-03-2018 | Srinagar | VDF flooring at Ramp. | Manjeet Deshwal | RE | UDRP-H Pauri | See Pic |
5. | 28-02-2018 | Srinagar | Fire Station | Manjeet Deshwal | RE | UDRP-H Pauri | See Pic |
6. | 28-02-2018 | Fire Station, Srinagar | Fire Station | Manjeet Deshwal | RE | UDRP-H Pauri | See Pic |
7. | 26-02-2018 | Mahila thana srinagar | Earth resistance test of Residential building LT panel Earthing | Praveen Negi | JE | UDRP-PB Pauri | See Pic |
8. | 26-02-2018 | Mahila thana srinagar | Earthing test of Copper earthing | Praveen Negi | JE | UDRP-PB Pauri | See Pic |
9. | 26-02-2018 | Mahila thana srinagar | Residential building - Mahila thana srinagar | Praveen Negi | JE | UDRP-PB Pauri | See Pic |
10. | 15-02-2018 | Srinagar | Electrical Fixtures fixing are in progress. | Manjeet Deshwal | RE | UDRP-H Pauri | See Pic |
11. | 10-02-2018 | Srinagar mahila thana | Cable laying work sand filling | Praveen Negi | JE | UDRP-PB Pauri | See Pic |
12. | 10-02-2018 | Mahila thana srinagar | Site visit by IG and Staffs | Praveen Negi | JE | UDRP-PB Pauri | See Pic |
13. | 05-02-2018 | Srinagar | Cable laying for DG set work at fire station srinagar | Praveen Negi | JE | UDRP-PB Pauri | See Pic |
14. | 04-02-2018 | Srinagar | Light and fixtures fittings at CO Residence srinagar | Praveen Negi | JE | UDRP-PB Pauri | See Pic |
15. | 04-02-2018 | Fire and CO office | CO and fire external finishing | Praveen Negi | JE | UDRP-PB Pauri | See Pic |
16. | 04-02-2018 | CO office | CO office External | Praveen Negi | JE | UDRP-PB Pauri | See Pic |
17. | 21-01-2018 | Srinagar | Painting work is in progress of C.O office. | Manjeet Deshwal | RE | UDRP-H Pauri | See Pic |
18. | 20-01-2018 | Srinagar | Site visit by FSO, Pauri. | Manjeet Deshwal | RE | UDRP-H Pauri | See Pic |
19. | 20-01-2018 | Srinagar | Fire station front view. | Manjeet Deshwal | RE | UDRP-H Pauri | See Pic |
20. | 20-01-2018 | Srinagar | Fire station back side view. | Manjeet Deshwal | RE | UDRP-H Pauri | See Pic |
|
|