05/BC/PIU/USIDCL/PB/2015-16
Agreement signed
|
Project: |
UDRP-H |
Package No.: |
2255 |
Package Name: |
05/BC/PIU/USIDCL/PB/2015-16 |
Sanction Cost: |
371.46 lakhs |
District: |
Rudraprayag |
Block: |
August Muni |
Constituency: |
Rudraprayag |
Circle: |
|
DEA: |
DEA PB |
DSC: |
SOWil Limited |
DSC Scope: |
Design and Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 7309 Govt Inter College Ghimtoli (0.000 KM.) (completed) |
|
Procurement: |
Package No.: 2255
Package Name: 05/BC/PIU/USIDCL/PB/2015-16
Tender Date: 04-09-2015
Current Status: Agreement signed
Achieved on Date: 15-09-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: 05/BC/PIU/USIDCL/PB/2015-16
Contractor Name: Chamoli Associates
|
Start Date: 10-09-2015
Intended Completion Date: 24-02-2018
Original End Date: 09-12-2016
|
Total Bond Cost: 39879783 (398.8 lakhs)
Variation Cost: 799404.76 (7.99 lakhs) Hence Total Bond Cost is 40679187.76 (406.79 lakhs)
|
LD Analysis for Milestone1: calculated LD is Rs 3050820 for +153 days
LD Analysis for Milestone2: calculated LD is Rs 8773600 for 440 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Site Development | 3.18 Job | 12.93 | 3.18 Job | 3.18 Job | 3.18 | 12.93 | 2. | Foundation and Plinth Work | 17.62 Job | 71.67 | 17.62 Job | 17.62 Job | 17.62 | 71.67 | 3. | Structural Frame | 39.70 Job | 161.49 | 39.70 Job | 39.70 Job | 39.7 | 161.49 | 4. | Doors & Windows | 10.12 Job | 41.17 | 10.12 Job | 10.12 Job | 10.12 | 41.17 | 5. | Water Supply and Sanitary work | 2.42 Job | 9.84 | 2.42 Job | 2.42 Job | 2.42 | 9.84 | 6. | Electrification Works | 6.47 Job | 26.31 | 6.47 Job | 6.47 Job | 6.47 | 26.31 | 7. | Other Allied Works & Finishing Work | 20.49 Job | 83.35 | 20.49 Job | 20.49 Job | 20.49 | 83.35 |
Total Amount: |
406.76 |
|
100 |
406.76 |
|
Remarks:
No Remarks
Work Program Made On:
02-02-2016
Updation of work program on:
25-11-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 10-March-2016 | 58.05 lakhs |
2. | 16-May-2016 | 40.68 lakhs |
3. | 30-June-2016 | 19.90 lakhs |
4. | 06-September-2016 | 29.26 lakhs |
5. | 29-December-2016 | 11.33 lakhs |
6. | 24-January-2017 | 8.94 lakhs |
7. | 27-February-2017 | 8.00 lakhs |
8. | 25-March-2017 | 8.67 lakhs |
9. | 25-May-2017 | 28.88 lakhs |
10. | 30-June-2017 | 22.80 lakhs |
11. | 30-August-2017 | 23.76 lakhs |
12. | 16-February-2018 | 62.25 lakhs |
13. | 28-March-2018 | 20.06 lakhs |
14. | 29-September-2018 | 34.48 lakhs |
Total |
377.06 lakhs |
% Payment |
92.69 % |
|
Advance Amount: 19.94 lakhs
Recovered Amount: 19.94 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 77 |
Number of Notice(s) issued: 71 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 03-06-2018 | GIC GHIMTOLI RUDRAPRAYAG | College Furniture | Satyendra Saklani | JE | UDRP-H Rudraprayag | See Pic |
2. | 16-05-2018 | GIC GHIMTOLI RUDRAPRAYAG | Building view from Main Road | Satyendra Saklani | JE | UDRP-H Rudraprayag | See Pic |
3. | 11-05-2018 | GIC GHIMTOLI Rudraprayag | School Furniture | Satyendra Saklani | JE | UDRP-H Rudraprayag | See Pic |
4. | 20-02-2018 | GIC GHIMTOLI RUDRAPRAYAG | Building Elevation | Satyendra Saklani | JE | UDRP-H Rudraprayag | See Pic |
5. | 13-12-2017 | GIC GHIMTOLI Rudraprayag | Building Elevation | Satyendra Saklani | JE | UDRP-H Rudraprayag | See Pic |
6. | 19-08-2017 | GIC Ghimtol Rudraprayag | Intercollege Top Terrace Hall | Satyendra Saklani | JE | UDRP-H Rudraprayag | See Pic |
7. | 25-07-2017 | GIC Ghimtoli | R R wall | Satyendra Saklani | JE | UDRP-H Rudraprayag | See Pic |
8. | 21-07-2017 | G. I. C Ghimtoli | 3D view of building | Anil Kumar RE | RE | UDRP PB | See Pic |
9. | 08-07-2017 | GIC Ghimtoli Rudraprayag | Building Elevation | Satyendra Saklani | JE | UDRP-H Rudraprayag | See Pic |
10. | 09-06-2017 | Inter college Ghimtoli | 3D view | Rakesh Rawat | JE | UDRP-H Rudraprayag | See Pic |
11. | 30-05-2017 | Govt. Inter college Ghimtoli | Roofing work | Rakesh Rawat | JE | UDRP-H Rudraprayag | See Pic |
12. | 22-05-2017 | Govt. Inter college ghimtoli | Second floor to above | Rakesh Rawat | JE | UDRP-H Rudraprayag | See Pic |
13. | 05-05-2017 | Govt. Inter college ghimtoli | Building left side | Rakesh Rawat | JE | UDRP-H Rudraprayag | See Pic |
14. | 25-04-2017 | Govt. Inter college ghimtoli | Truss | Rakesh Rawat | JE | UDRP-H Rudraprayag | See Pic |
15. | 17-04-2017 | G.i.c ghimtoli | Plaster work is in progress | Anil Kumar RE | RE | UDRP PB | See Pic |
16. | 10-04-2017 | Govt. Inter college Ghimtoli | 3D | Rakesh Rawat | JE | UDRP-H Rudraprayag | See Pic |
17. | 30-03-2017 | Govt. Inter college ghimtoli | Truss work | Rakesh Rawat | JE | UDRP-H Rudraprayag | See Pic |
18. | 07-03-2017 | Govt. Inter college ghimtoli | Groove making | Rakesh Rawat | JE | UDRP-H Rudraprayag | See Pic |
19. | 27-02-2017 | Govt. Inter college Ghimtoli | Kota stone flooring work | Rakesh Rawat | JE | UDRP-H Rudraprayag | See Pic |
20. | 22-02-2017 | Govt. Inter college ghimtoli | Building front | Rakesh Rawat | JE | UDRP-H Rudraprayag | See Pic |
|
|