Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

05/BC/PIU/USIDCL/PB/2015-16 Agreement signed
Project: UDRP-H Package No.: 2255 Package Name: 05/BC/PIU/USIDCL/PB/2015-16 Sanction Cost: 371.46  lakhs
District: Rudraprayag Block: August Muni Constituency: Rudraprayag Circle:
DEA: DEA PB DSC: SOWil Limited DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  7309   Govt Inter College Ghimtoli (0.000 KM.) (completed)
Procurement:
Package No.: 2255        Package Name: 05/BC/PIU/USIDCL/PB/2015-16        Tender Date: 04-09-2015        Current Status: Agreement signed        Achieved on Date: 15-09-2015

Construction Phase

Agreement Details
Bond/Agreement Name: 05/BC/PIU/USIDCL/PB/2015-16        Contractor Name: Chamoli Associates       
Start Date: 10-09-2015        Intended Completion Date: 24-02-2018        Original End Date:  09-12-2016
Total Bond Cost: 39879783 (398.8 lakhs)        Variation Cost: 799404.76 (7.99 lakhs)     Hence Total Bond Cost is   40679187.76 (406.79 lakhs) 
LD Analysis for Milestone1: calculated LD is Rs 3050820 for +153 days        LD Analysis for Milestone2: calculated LD is Rs 8773600 for 440 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Site Development3.18 Job12.933.18 Job3.18 Job3.1812.93
2.Foundation and Plinth Work17.62 Job71.6717.62 Job17.62 Job17.6271.67
3.Structural Frame39.70 Job161.4939.70 Job39.70 Job39.7161.49
4.Doors & Windows 10.12 Job41.1710.12 Job10.12 Job10.1241.17
5.Water Supply and Sanitary work 2.42 Job9.842.42 Job2.42 Job2.429.84
6.Electrification Works6.47 Job26.316.47 Job6.47 Job6.4726.31
7.Other Allied Works & Finishing Work 20.49 Job83.3520.49 Job20.49 Job20.4983.35
Total Amount: 406.76 100   406.76
Remarks: No Remarks       Work Program Made On: 02-02-2016       Updation of work program on: 25-11-2017      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.10-March-201658.05  lakhs
2.16-May-201640.68  lakhs
3.30-June-201619.90  lakhs
4.06-September-201629.26  lakhs
5.29-December-201611.33  lakhs
6.24-January-20178.94  lakhs
7.27-February-20178.00  lakhs
8.25-March-20178.67  lakhs
9.25-May-201728.88  lakhs
10.30-June-201722.80  lakhs
11.30-August-201723.76  lakhs
12.16-February-201862.25  lakhs
13.28-March-201820.06  lakhs
14.29-September-201834.48  lakhs
Total 377.06  lakhs
% Payment 92.69 %
Advance Amount:  19.94  lakhs        Recovered Amount:  19.94  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 141     No. of Test Done : 141      No. of Test Passed : 141      No. of Test Failed : 0   Test report of this package
Number of Pics Available on Web Repository: 77
Number of Notice(s) issued: 71

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.03-06-2018GIC GHIMTOLI RUDRAPRAYAGCollege FurnitureSatyendra SaklaniJEUDRP-H Rudraprayag See Pic
2.16-05-2018GIC GHIMTOLI RUDRAPRAYAGBuilding view from Main RoadSatyendra SaklaniJEUDRP-H Rudraprayag See Pic
3.11-05-2018GIC GHIMTOLI RudraprayagSchool FurnitureSatyendra SaklaniJEUDRP-H Rudraprayag See Pic
4.20-02-2018GIC GHIMTOLI RUDRAPRAYAGBuilding ElevationSatyendra SaklaniJEUDRP-H Rudraprayag See Pic
5.13-12-2017GIC GHIMTOLI RudraprayagBuilding ElevationSatyendra SaklaniJEUDRP-H Rudraprayag See Pic
6.19-08-2017GIC Ghimtol RudraprayagIntercollege Top Terrace HallSatyendra SaklaniJEUDRP-H Rudraprayag See Pic
7.25-07-2017GIC GhimtoliR R wallSatyendra SaklaniJEUDRP-H Rudraprayag See Pic
8.21-07-2017G. I. C Ghimtoli3D view of buildingAnil Kumar REREUDRP PB See Pic
9.08-07-2017GIC Ghimtoli RudraprayagBuilding ElevationSatyendra SaklaniJEUDRP-H Rudraprayag See Pic
10.09-06-2017Inter college Ghimtoli3D viewRakesh RawatJEUDRP-H Rudraprayag See Pic
11.30-05-2017Govt. Inter college GhimtoliRoofing workRakesh RawatJEUDRP-H Rudraprayag See Pic
12.22-05-2017Govt. Inter college ghimtoliSecond floor to aboveRakesh RawatJEUDRP-H Rudraprayag See Pic
13.05-05-2017Govt. Inter college ghimtoliBuilding left sideRakesh RawatJEUDRP-H Rudraprayag See Pic
14.25-04-2017Govt. Inter college ghimtoliTrussRakesh RawatJEUDRP-H Rudraprayag See Pic
15.17-04-2017G.i.c ghimtoliPlaster work is in progressAnil Kumar REREUDRP PB See Pic
16.10-04-2017Govt. Inter college Ghimtoli3DRakesh RawatJEUDRP-H Rudraprayag See Pic
17.30-03-2017Govt. Inter college ghimtoliTruss workRakesh RawatJEUDRP-H Rudraprayag See Pic
18.07-03-2017Govt. Inter college ghimtoliGroove makingRakesh RawatJEUDRP-H Rudraprayag See Pic
19.27-02-2017Govt. Inter college GhimtoliKota stone flooring workRakesh RawatJEUDRP-H Rudraprayag See Pic
20.22-02-2017Govt. Inter college ghimtoliBuilding frontRakesh RawatJEUDRP-H Rudraprayag See Pic