01/BC/PIU/USIDCL/PB/2015-16
Agreement signed
|
Project: |
UDRP-H |
Package No.: |
2251 |
Package Name: |
01/BC/PIU/USIDCL/PB/2015-16 |
Sanction Cost: |
169.72 lakhs |
District: |
Rudraprayag |
Block: |
August Muni |
Constituency: |
Kedarnath |
Circle: |
|
DEA: |
DEA PB |
DSC: |
SOWil Limited |
DSC Scope: |
Design and Supervision |
No.of Sub project : |
2 |
Subproject in this package |
1 7310 Primary School Gandhari (Chopta) (0.000 KM.) (completed) | 2 7311 Primary School Chopta (Chopta) (0.000 KM.) (completed) |
|
Procurement: |
Package No.: 2251
Package Name: 01/BC/PIU/USIDCL/PB/2015-16
Tender Date: 04-09-2015
Current Status: Agreement signed
Achieved on Date: 15-09-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: 01/BC/PIU/USIDCL/PB/2015-16
Contractor Name: Chamoli Associates
|
Start Date: 10-09-2015
Intended Completion Date: 03-09-2017
|
Total Bond Cost: 17714717.24 (177.15 lakhs)
Variation Cost: -1276369.24 (-12.76 lakhs) Hence Total Bond Cost is 16438348 (164.38 lakhs)
|
LD Analysis for Milestone1: calculated LD is Rs 2152251 for +243 days
LD Analysis for Milestone2: calculated LD is Rs 2550816 for 288 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Site Development | 18.09 Job | 16.44 | 15.64 Job | 15.64 Job | 9.03 | 16.44 | 2. | Foundation and Plinth Work | 34.72 Job | 31.50 | 31.03 Job | 31.03 Job | 17.37 | 31.50 | 3. | Structural Frame | 76.40 Job | 69.39 | 76.40 Job | 76.40 Job | 38.18 | 69.39 | 4. | Doors & Windows | 8.83 Job | 8.06 | 8.83 Job | 8.83 Job | 4.39 | 8.06 | 5. | Water Supply and Sanitary work | 4.55 Job | 4.13 | 4.55 Job | 4.55 Job | 2.28 | 4.13 | 6. | Electrification Works | 5.31 Job | 4.85 | 5.31 Job | 5.31 Job | 2.64 | 4.85 | 7. | Other Allied Works & Finishing Work | 52.10 Job | 47.18 | 52.10 Job | 52.10 Job | 26.11 | 47.18 |
Total Amount: |
181.55 |
|
100 |
181.55 |
|
Remarks:
Task finished
Work Program Made On:
01-02-2016
Updation of work program on:
22-08-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 16-May-2016 | 24.91 lakhs |
2. | 30-June-2016 | 14.45 lakhs |
3. | 22-September-2016 | 18.93 lakhs |
4. | 27-October-2016 | 8.77 lakhs |
5. | 29-December-2016 | 9.05 lakhs |
6. | 24-January-2017 | 5.47 lakhs |
7. | 27-February-2017 | 8.31 lakhs |
8. | 25-March-2017 | 4.89 lakhs |
9. | 21-June-2017 | 5.58 lakhs |
10. | 30-August-2017 | 14.35 lakhs |
11. | 24-March-2018 | 49.67 lakhs |
Total |
164.38 lakhs |
% Payment |
100 % |
|
Advance Amount: 8.86 lakhs
Recovered Amount: 8.86 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 144 |
Number of Notice(s) issued: 74 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 12-02-2020 | Birahi | Ch. 204 to 214 3rd lift superstructure M15 grade concrete in progress | Rohit Yadav | QC | DSC WB Irrigation Chamoli | See Pic |
2. | 02-02-2018 | P. S chopta | Checking white washing and other work | Anil Kumar RE | RE | UDRP PB | See Pic |
3. | 02-02-2018 | Primary school Gandhari | checking of completion work | Anil Kumar RE | RE | UDRP PB | See Pic |
4. | 25-10-2017 | Primary School Chopta | Boundary wall work and inter locking Tile work finishing. | Rahul Bhatt | JE | UDRP-H Rudraprayag | See Pic |
5. | 25-10-2017 | Primary School Chopta | Primary school chopta building | Rahul Bhatt | JE | UDRP-H Rudraprayag | See Pic |
6. | 25-10-2017 | Primary school chopta | Water tank work complete | Rahul Bhatt | JE | UDRP-H Rudraprayag | See Pic |
7. | 28-09-2017 | Primary School Gandhari, Rudrapryag | Interlocking paver Tile work in progress. | Rahul Bhatt | JE | UDRP-H Rudraprayag | See Pic |
8. | 28-09-2017 | Primary School Gandhari, Rudrapryag | School Building in finishing level. | Rahul Bhatt | JE | UDRP-H Rudraprayag | See Pic |
9. | 25-09-2017 | Primary School Chopta, Rudrapryag | Main Gate work in progress | Rahul Bhatt | JE | UDRP-H Rudraprayag | See Pic |
10. | 25-09-2017 | Primary School chopta, Rudrapryag | Bala work | Rahul Bhatt | JE | UDRP-H Rudraprayag | See Pic |
11. | 25-09-2017 | Bala work | Bala work | Rahul Bhatt | JE | UDRP-H Rudraprayag | See Pic |
12. | 25-09-2017 | Primary School Chopta, Rudrapryag | Stair case railling with bala work | Rahul Bhatt | JE | UDRP-H Rudraprayag | See Pic |
13. | 25-09-2017 | Primary School Gandhari, Rudrapryag | Bala work | Rahul Bhatt | JE | UDRP-H Rudraprayag | See Pic |
14. | 25-09-2017 | Primary school Gandhari | Bala work | Rahul Bhatt | JE | UDRP-H Rudraprayag | See Pic |
15. | 25-09-2017 | Primary School Gandhari, Rudrapryag | Bala work | Rahul Bhatt | JE | UDRP-H Rudraprayag | See Pic |
16. | 25-09-2017 | Primary School Gandhari, Rudrapryag | Stair Case railling and BaLA work. | Rahul Bhatt | JE | UDRP-H Rudraprayag | See Pic |
17. | 19-08-2017 | Primary school Gandhari | White washing and painting work is in progress | Anil Kumar RE | RE | UDRP PB | See Pic |
18. | 22-07-2017 | Primary school Gandhari | BaLA drawing work in boundary wall. | Rahul Bhatt | JE | UDRP-H Rudraprayag | See Pic |
19. | 21-07-2017 | Primary school chopta | White washing and painting work is in progress | Anil Kumar RE | RE | UDRP PB | See Pic |
20. | 19-07-2017 | Primary school Gandhari | Bala work is in progress | Anil Kumar RE | RE | UDRP PB | See Pic |
|
|