UK/UEAP-T(GMVN)/DDN/09/LOT U1 (TRH PUROLA) Agreement signed
Project: UEAP-T Package No.: 2228 Package Name: UK/UEAP-T(GMVN)/DDN/09/LOT U1 (TRH PUROLA) Sanction Cost: 119.76  lakhs
District: Uttarkashi Block: Puraula Constituency: Purola Circle:
DEA: GMVN Uttarkashi DSC: DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  7246   TRH Purola (0.000 KM.) (in prorgress)
Procurement:
Package No.: 2228        Package Name: UK/UEAP-T(GMVN)/DDN/09/LOT U1 (TRH PUROLA)        Tender Date: 16-05-2016        Current Status: Agreement signed        Achieved on Date: 19-12-2016

Construction Phase

Agreement Details
Bond/Agreement Name: UK/UEAP-T(GMVN)/DDN/09/LOT U1 (TRH PUROLA)        Contractor Name: Shri Balaji Trading Co.       
Start Date: 29-12-2016        Intended Completion Date: 28-06-2017       
Total Bond Cost: 11014841.69 (110.15 lakhs)       
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 1051837 for 191 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Site Development3.00 Job23.323.00 Job2.70 Job19.0620.99
2.Foundation and Plinth Work2.00 Job14.642.00 Job1.90 Job12.6213.91
3.Doors & Windows 1.00 Job9.671.00 Job0.70 Job6.156.77
4.Water Supply and Sanitary work 2.00 Job7.522.00 Job1.65 Job5.636.21
5.Electrification Works2.00 Job26.052.00 Job1.00 Job11.8213.02
6.Other Allied Works & Finishing Work 2.00 Job5.532.00 Job1.40 Job3.523.87
7.Furnishing Work3.00 Job23.413.00 Job0.00 Job00.00
Total Amount: 110.14 58.8   64.77
Remarks: No Remarks       Work Program Made On: 05-05-2017       Updation of work program on: 30-08-2017      
Work Program Status:Program Expired.
Financial Progress
SNo. Date Payment
1.13-September-201713.76  lakhs
Total 13.76  lakhs
% Payment 12.49 %
Advance Amount:  0.00  lakhs        Recovered Amount:  0.00  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Analysis:Bill should be issued
Pending Environmental & Social issues
Environment & Social Compliances(Package level): PUC vehicles, labour licence, workmen Insurance
Environment & Social Compliances(Sub Project level):
TRH Purola(7246) Land Owner Consent, Helmet, Jacket, Boot, Glove, Signs, project information board, debris disposal, Query
Detailed report of this Package
Quality
Test Information not Available.
Number of Pics Available on Web Repository: 7
Number of Notice(s) issued: 8

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.29-07-2017TRH PurolaWork of ceilng in Dining Hall is in progressSanjay GuptaProcurement OfficerUEAP-T GMVN See Pic
2.29-07-2017TRH PurolaWork of internal plumbing has been completedSanjay GuptaProcurement OfficerUEAP-T GMVN See Pic
3.29-07-2017TRH PurolaWork of ceilng and POP at first floor rooms has been completedSanjay GuptaProcurement OfficerUEAP-T GMVN See Pic
4.28-06-2017TRH PurolaWork of making opening for Windows has been completedSanjay GuptaProcurement OfficerUEAP-T GMVN See Pic
5.28-06-2017TRH PurolaWork of internal plumbing in first floor rooms has been completedSanjay GuptaProcurement OfficerUEAP-T GMVN See Pic
6.27-06-2017TRH PurolaWork of changing of planks in roof has been completedSanjay GuptaProcurement OfficerUEAP-T GMVN See Pic
7.27-06-2017TRH PurolaWork of Profile Sheet in roof has been completedSanjay GuptaProcurement OfficerUEAP-T GMVN See Pic