Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UK/UEAP-T(KMVN)/NTL/02(R) BAGESHWAR Agreement signed
Project: UEAP-T Package No.: 2227 Package Name: UK/UEAP-T(KMVN)/NTL/02(R) BAGESHWAR Sanction Cost: 874.45  lakhs
District: Bageshwar Block: Kapkot Constituency: Kapkote Circle: KMVN
DEA: KMVN Bageshwar DSC: DSC Scope: Design and Supervision No.of Sub project : 9
Subproject in this package
1  7267   FRP Huts at Supi (0.000 KM.) (in prorgress)
2  7268   FRP Huts at Jhooni (0.000 KM.) (in prorgress)
3  7269   FRP Huts at Jaikuni (0.000 KM.) (in prorgress)
4  7270   FRP Huts at Badyakot (0.000 KM.) (in prorgress)
5  7271   FRP Huts at Sorag (0.000 KM.) (in prorgress)
6  7272   FRP Huts at Bacham Tok Dhakuri (0.000 KM.) (in prorgress)
7  7273   FRP Huts at Sorag Tok Dhoor (0.000 KM.) (in prorgress)
8  7274   FRP Huts at Phurkia (0.000 KM.) (in prorgress)
9  7275   FRP Huts at Teekh (0.000 KM.) (in prorgress)
Procurement:
Package No.: 2227        Package Name: UK/UEAP-T(KMVN)/NTL/02(R) BAGESHWAR        Tender Date: 30-10-2014        Current Status: Agreement signed        Achieved on Date: 31-01-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UK/UEAP-T(KMVN)/NTL/02(R) BAGESHWAR        Contractor Name: Enertech Engineering Private Limited       
Start Date: 07-02-2015        Intended Completion Date: 06-02-2017       
Total Bond Cost: 73720885.2 (737.21 lakhs)       
LD Analysis for Milestone1: calculated LD is Rs 6450500 for 175 days        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Site Development9.00 Job52.209.00 Job7.22 Job5.8341.83
2.Foundation and Plinth Work9.00 Job67.529.00 Job8.00 Job8.3760.02
3.Structural Frame9.00 Job427.889.00 Job8.00 Job53.03380.34
4.Water Supply and Sanitary work 9.00 Job42.299.00 Job0.00 Job00.00
5.Electrification Works9.00 Job53.139.00 Job0.00 Job00.00
6.Furnishing Work9.00 Job74.259.00 Job0.00 Job00.00
Total Amount: 717.27 67.23   482.19
Remarks: No Remarks       Work Program Made On: 18-05-2016      
Work Program Status:This Package contain more than one subproject,pleae check individua subproject for Program Expired.
Financial Progress
SNo. Date Payment
1.05-December-201540.20  lakhs
2.14-March-201628.53  lakhs
3.02-July-2016495.07  lakhs
4.14-February-201765.13  lakhs
Total 628.93  lakhs
% Payment 85.31 %
Advance Amount:  111.14  lakhs        Recovered Amount:  86.75  lakhs        Balance to be Recovered  24.39  lakhs        * Advances are at package level not sub project level
Analysis:Physical Progress Wrongly Reported.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):No Pending Issue
Environment & Social Compliances(Sub Project level):
FRP Huts at Supi(7267) debris disposal, Query, Borrow pits, DG set
FRP Huts at Jhooni(7268) debris disposal, Query, Borrow pits, DG set
FRP Huts at Jaikuni(7269) debris disposal, Query, Borrow pits, DG set
FRP Huts at Badyakot(7270) debris disposal, Query, Borrow pits, DG set
FRP Huts at Sorag(7271) debris disposal, Query, Borrow pits, DG set
FRP Huts at Bacham Tok Dhakuri(7272) debris disposal, Query, Borrow pits, DG set
FRP Huts at Sorag Tok Dhoor(7273) debris disposal, Query, Borrow pits, DG set
FRP Huts at Phurkia(7274) debris disposal, Query, Borrow pits, DG set
FRP Huts at Teekh(7275) Glove, debris disposal, Query, Borrow pits, DG set
Detailed report of this Package
Quality
Test Information not Available.
Number of Pics Available on Web Repository: 71
Number of Notice(s) issued: 70

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.13-10-2017Bacham tok dhakuri5 Frp hut has been complete with furniture...Mohd. Shazar KhanJEUEAP T-KMVN Bageshwar See Pic
2.13-10-2017Sorag Tok dhoor5 FRP HUT HAS BEEN COMPLETE..with furnitureMohd. Shazar KhanJEUEAP T-KMVN Bageshwar See Pic
3.15-06-2017Sorag Tok dhoorSITE VISIT AT SORAG TOK DHOOR WITH ADB TEAM..Mohd. Shazar KhanJEUEAP T-KMVN Bageshwar See Pic
4.15-06-2017Bacham tok dhakuriSITE VISIT WITH ADB TEAMMohd. Shazar KhanJEUEAP T-KMVN Bageshwar See Pic
5.03-06-2017Bacham tok dhakuriFurniture installed and electrification also completed..Mohd. Shazar KhanJEUEAP T-KMVN Bageshwar See Pic
6.03-06-2017Teekh5 FRP HUT INSTALLED AND ELECTRIFICATION WORK IN PROGRESSMohd. Shazar KhanJEUEAP T-KMVN Bageshwar See Pic
7.25-04-2017Bacham tok dhakuri5 Frp hut installed and 3nos bathroom has been installed SANITARY fitting work in progressMohd. Shazar KhanJEUEAP T-KMVN Bageshwar See Pic
8.25-04-2017Bacham tok dhakuri5 Frp hut and 3nos bathroom has been installed with fittingsMohd. Shazar KhanJEUEAP T-KMVN Bageshwar See Pic
9.25-04-20175 nos Frp hut and 3nos bathroom has been installedTeekhMohd. Shazar KhanJEUEAP T-KMVN Bageshwar See Pic
10.25-04-2017Teekh5nos frp hut and3nos bathroom has been installed with fittings..Mohd. Shazar KhanJEUEAP T-KMVN Bageshwar See Pic
11.25-04-2017Sorag Tok dhoor3 nos bathroom has been installedMohd. Shazar KhanJEUEAP T-KMVN Bageshwar See Pic
12.25-04-2017Sorag Tok dhoor5 Frp hut 3 nos bathroom has been installed water line and SANITARY fitting also completeMohd. Shazar KhanJEUEAP T-KMVN Bageshwar See Pic
13.20-03-2017Teekh5 FRP AND 3 BATHROOM INSTALLEDMohd. Shazar KhanJEUEAP T-KMVN Bageshwar See Pic
14.20-03-2017Teekh5 Frp hut installed with 3 bathroom..Mohd. Shazar KhanJEUEAP T-KMVN Bageshwar See Pic
15.20-03-2017Bacham tok dhakuri5 FRP HUT INSTALLED WITH 3 BATHROOMMohd. Shazar KhanJEUEAP T-KMVN Bageshwar See Pic
16.20-03-2017Sorag Tok dhoor5 GDP HUT INSTALLED WITH FITTINGSMohd. Shazar KhanJEUEAP T-KMVN Bageshwar See Pic
17.20-03-2017Sorag Tok dhoor5 Frp hut installed with fittingMohd. Shazar KhanJEUEAP T-KMVN Bageshwar See Pic
18.20-03-2017Supi5 Frp hut installed with door windowMohd. Shazar KhanJEUEAP T-KMVN Bageshwar See Pic
19.02-03-2017Supi5 GDP AND 5 BATHROOM HAS ALSO BEEN INSTALLED SANITARY WORK IN PROGRESSMohd. Shazar KhanJEUEAP T-KMVN Bageshwar See Pic
20.02-03-2017Supi5 FRP AND 5 BATHROOM HAS ALSO BEEN INSTALLEDMohd. Shazar KhanJEUEAP T-KMVN Bageshwar See Pic