UK/UEAP-T(KMVN)/NTL/02(R) BAGESHWAR
Agreement signed
|
Project: |
UEAP-T |
Package No.: |
2227 |
Package Name: |
UK/UEAP-T(KMVN)/NTL/02(R) BAGESHWAR |
Sanction Cost: |
874.45 lakhs |
District: |
Bageshwar |
Block: |
Kapkot |
Constituency: |
Kapkote |
Circle: |
KMVN |
DEA: |
KMVN Bageshwar |
DSC: |
|
DSC Scope: |
Design and Supervision |
No.of Sub project : |
9 |
Subproject in this package |
1 7267 FRP Huts at Supi (0.000 KM.) (in prorgress) | 2 7268 FRP Huts at Jhooni (0.000 KM.) (in prorgress) | 3 7269 FRP Huts at Jaikuni (0.000 KM.) (in prorgress) | 4 7270 FRP Huts at Badyakot (0.000 KM.) (in prorgress) | 5 7271 FRP Huts at Sorag (0.000 KM.) (in prorgress) | 6 7272 FRP Huts at Bacham Tok Dhakuri (0.000 KM.) (in prorgress) | 7 7273 FRP Huts at Sorag Tok Dhoor (0.000 KM.) (in prorgress) | 8 7274 FRP Huts at Phurkia (0.000 KM.) (in prorgress) | 9 7275 FRP Huts at Teekh (0.000 KM.) (in prorgress) |
|
Procurement: |
Package No.: 2227
Package Name: UK/UEAP-T(KMVN)/NTL/02(R) BAGESHWAR
Tender Date: 30-10-2014
Current Status: Agreement signed
Achieved on Date: 31-01-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UK/UEAP-T(KMVN)/NTL/02(R) BAGESHWAR
Contractor Name: Enertech Engineering Private Limited
|
Start Date: 07-02-2015
Intended Completion Date: 06-02-2017
|
Total Bond Cost: 73720885.2 (737.21 lakhs)
|
LD Analysis for Milestone1: calculated LD is Rs 6450500 for 175 days
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Site Development | 9.00 Job | 52.20 | 9.00 Job | 7.22 Job | 5.83 | 41.83 | 2. | Foundation and Plinth Work | 9.00 Job | 67.52 | 9.00 Job | 8.00 Job | 8.37 | 60.02 | 3. | Structural Frame | 9.00 Job | 427.88 | 9.00 Job | 8.00 Job | 53.03 | 380.34 | 4. | Water Supply and Sanitary work | 9.00 Job | 42.29 | 9.00 Job | 0.00 Job | 0 | 0.00 | 5. | Electrification Works | 9.00 Job | 53.13 | 9.00 Job | 0.00 Job | 0 | 0.00 | 6. | Furnishing Work | 9.00 Job | 74.25 | 9.00 Job | 0.00 Job | 0 | 0.00 |
Total Amount: |
717.27 |
|
67.23 |
482.19 |
|
Remarks:
No Remarks
Work Program Made On:
18-05-2016
|
|
Work Program Status:This Package contain more than one subproject,pleae check individua subproject for Program Expired. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 05-December-2015 | 40.20 lakhs |
2. | 14-March-2016 | 28.53 lakhs |
3. | 02-July-2016 | 495.07 lakhs |
4. | 14-February-2017 | 65.13 lakhs |
Total |
628.93 lakhs |
% Payment |
85.31 % |
|
Advance Amount: 111.14 lakhs
Recovered Amount: 86.75 lakhs
Balance to be Recovered 24.39 lakhs
* Advances are at package level not sub project level
|
Analysis:Physical Progress Wrongly Reported. |
|
Pending Environmental & Social issues
|
Environment & Social Compliances(Package level): | No Pending Issue | Environment & Social Compliances(Sub Project level): | FRP Huts at Supi(7267) | debris disposal, Query, Borrow pits, DG set | FRP Huts at Jhooni(7268) | debris disposal, Query, Borrow pits, DG set | FRP Huts at Jaikuni(7269) | debris disposal, Query, Borrow pits, DG set | FRP Huts at Badyakot(7270) | debris disposal, Query, Borrow pits, DG set | FRP Huts at Sorag(7271) | debris disposal, Query, Borrow pits, DG set | FRP Huts at Bacham Tok Dhakuri(7272) | debris disposal, Query, Borrow pits, DG set | FRP Huts at Sorag Tok Dhoor(7273) | debris disposal, Query, Borrow pits, DG set | FRP Huts at Phurkia(7274) | debris disposal, Query, Borrow pits, DG set | FRP Huts at Teekh(7275) | Glove, debris disposal, Query, Borrow pits, DG set |
Detailed report of this Package
|
|
Quality
|
Test Information not Available. |
Number of Pics Available on Web Repository: 71 |
Number of Notice(s) issued: 70 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 13-10-2017 | Bacham tok dhakuri | 5 Frp hut has been complete with furniture... | Mohd. Shazar Khan | JE | UEAP T-KMVN Bageshwar | See Pic |
2. | 13-10-2017 | Sorag Tok dhoor | 5 FRP HUT HAS BEEN COMPLETE..with furniture | Mohd. Shazar Khan | JE | UEAP T-KMVN Bageshwar | See Pic |
3. | 15-06-2017 | Sorag Tok dhoor | SITE VISIT AT SORAG TOK DHOOR WITH ADB TEAM.. | Mohd. Shazar Khan | JE | UEAP T-KMVN Bageshwar | See Pic |
4. | 15-06-2017 | Bacham tok dhakuri | SITE VISIT WITH ADB TEAM | Mohd. Shazar Khan | JE | UEAP T-KMVN Bageshwar | See Pic |
5. | 03-06-2017 | Bacham tok dhakuri | Furniture installed and electrification also completed.. | Mohd. Shazar Khan | JE | UEAP T-KMVN Bageshwar | See Pic |
6. | 03-06-2017 | Teekh | 5 FRP HUT INSTALLED AND ELECTRIFICATION WORK IN PROGRESS | Mohd. Shazar Khan | JE | UEAP T-KMVN Bageshwar | See Pic |
7. | 25-04-2017 | Bacham tok dhakuri | 5 Frp hut installed and 3nos bathroom has been installed SANITARY fitting work in progress | Mohd. Shazar Khan | JE | UEAP T-KMVN Bageshwar | See Pic |
8. | 25-04-2017 | Bacham tok dhakuri | 5 Frp hut and 3nos bathroom has been installed with fittings | Mohd. Shazar Khan | JE | UEAP T-KMVN Bageshwar | See Pic |
9. | 25-04-2017 | 5 nos Frp hut and 3nos bathroom has been installed | Teekh | Mohd. Shazar Khan | JE | UEAP T-KMVN Bageshwar | See Pic |
10. | 25-04-2017 | Teekh | 5nos frp hut and3nos bathroom has been installed with fittings.. | Mohd. Shazar Khan | JE | UEAP T-KMVN Bageshwar | See Pic |
11. | 25-04-2017 | Sorag Tok dhoor | 3 nos bathroom has been installed | Mohd. Shazar Khan | JE | UEAP T-KMVN Bageshwar | See Pic |
12. | 25-04-2017 | Sorag Tok dhoor | 5 Frp hut 3 nos bathroom has been installed water line and SANITARY fitting also complete | Mohd. Shazar Khan | JE | UEAP T-KMVN Bageshwar | See Pic |
13. | 20-03-2017 | Teekh | 5 FRP AND 3 BATHROOM INSTALLED | Mohd. Shazar Khan | JE | UEAP T-KMVN Bageshwar | See Pic |
14. | 20-03-2017 | Teekh | 5 Frp hut installed with 3 bathroom.. | Mohd. Shazar Khan | JE | UEAP T-KMVN Bageshwar | See Pic |
15. | 20-03-2017 | Bacham tok dhakuri | 5 FRP HUT INSTALLED WITH 3 BATHROOM | Mohd. Shazar Khan | JE | UEAP T-KMVN Bageshwar | See Pic |
16. | 20-03-2017 | Sorag Tok dhoor | 5 GDP HUT INSTALLED WITH FITTINGS | Mohd. Shazar Khan | JE | UEAP T-KMVN Bageshwar | See Pic |
17. | 20-03-2017 | Sorag Tok dhoor | 5 Frp hut installed with fitting | Mohd. Shazar Khan | JE | UEAP T-KMVN Bageshwar | See Pic |
18. | 20-03-2017 | Supi | 5 Frp hut installed with door window | Mohd. Shazar Khan | JE | UEAP T-KMVN Bageshwar | See Pic |
19. | 02-03-2017 | Supi | 5 GDP AND 5 BATHROOM HAS ALSO BEEN INSTALLED SANITARY WORK IN PROGRESS | Mohd. Shazar Khan | JE | UEAP T-KMVN Bageshwar | See Pic |
20. | 02-03-2017 | Supi | 5 FRP AND 5 BATHROOM HAS ALSO BEEN INSTALLED | Mohd. Shazar Khan | JE | UEAP T-KMVN Bageshwar | See Pic |
|
|