UK/UEAP-T(GMVN)/DDN/06
Agreement signed
|
Project: |
UEAP-T |
Package No.: |
2204 |
Package Name: |
UK/UEAP-T(GMVN)/DDN/06 |
Sanction Cost: |
1858.14 lakhs |
District: |
Rudraprayag |
Block: |
August Muni |
Constituency: |
Rudraprayag |
Circle: |
GMVN |
DEA: |
GMVN Rudraprayag |
DSC: |
|
DSC Scope: |
Design & Supervision |
No.of Sub project : |
6 |
Subproject in this package |
1 7213 LGFS Huts, Multi Purpose Hall & Meditation Center at Tilwara ( KM.) (in prorgress) | 2 7214 LGFS Huts at Triyuginarayan ( KM.) (in prorgress) | 3 7215 LGFS Huts at Jakholi ( KM.) (completed) | 4 7216 LGFS Huts at Guptkashi ( KM.) (in prorgress) | 5 7217 LGFS Night Shelter at Sonprayag ( KM.) (in prorgress) | 6 7218 LGFS Huts at Gaurikund ( KM.) (in prorgress) |
|
Procurement: |
Package No.: 2204
Package Name: UK/UEAP-T(GMVN)/DDN/06
Tender Date: 02-05-2014
Current Status: Agreement signed
Achieved on Date: 01-10-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UK/UEAP-T(GMVN)/DDN/06
Contractor Name: Loom Crafts Shade Systems Pvt. Ltd
|
Start Date: 09-10-2014
Intended Completion Date: 31-08-2017
Original End Date: 08-04-2016
|
Total Bond Cost: 176686392 (1766.86 lakhs)
Variation Cost: 26127450.68 (261.27 lakhs) Hence Total Bond Cost is 202813842.68 (2028.14 lakhs)
|
LD Analysis for Milestone1: calculated LD is Rs 16166769 for +183 days
LD Analysis for Milestone2: calculated LD is Rs 61133356 for 692 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Site Development | 6.00 Job | 77.19 | 6.00 Job | 5.20 Job | 3.4 | 61.49 | 2. | Foundation and Plinth Work | 6.00 Job | 62.22 | 6.00 Job | 5.40 Job | 3.06 | 54.84 | 3. | Structural Frame | 6.00 Job | 911.45 | 6.00 Job | 4.90 Job | 37.96 | 682.39 | 4. | Doors & Windows | 6.00 Job | 83.77 | 6.00 Job | 4.20 Job | 2.41 | 43.60 | 5. | Water Supply and Sanitary work | 6.00 Job | 116.66 | 6.00 Job | 4.20 Job | 3.73 | 67.31 | 6. | Electrification Works | 6.00 Job | 67.75 | 6.00 Job | 3.90 Job | 1.35 | 24.41 | 7. | Other Allied Works & Finishing Work | 6.00 Job | 295.41 | 6.00 Job | 3.30 Job | 8.41 | 150.69 | 8. | Furnishing Work | 6.00 Job | 189.75 | 6.00 Job | 4.00 Job | 5.36 | 96.67 |
Total Amount: |
1804.2 |
|
65.68 |
1181.4 |
|
Remarks:
Work Program Made On:
02-01-2015
Updation of work program on:
11-10-2017
|
|
Work Program Status:This Package contain more than one subproject,pleae check individua subproject for Program Expired. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 07-September-2015 | 22.92 lakhs |
2. | 10-September-2015 | 36.90 lakhs |
3. | 31-October-2015 | 51.45 lakhs |
4. | 30-November-2015 | 59.22 lakhs |
5. | 31-December-2015 | 89.84 lakhs |
6. | 30-January-2016 | 63.70 lakhs |
7. | 29-February-2016 | 44.34 lakhs |
8. | 30-April-2016 | 54.11 lakhs |
9. | 31-May-2016 | 79.88 lakhs |
10. | 16-August-2016 | 70.16 lakhs |
11. | 22-September-2016 | 92.39 lakhs |
12. | 31-August-2017 | 145.13 lakhs |
Total |
810.04 lakhs |
% Payment |
39.94 % |
|
Advance Amount: 175.00 lakhs
Recovered Amount: 19.69 lakhs
Balance to be Recovered 155.31 lakhs
* Advances are at package level not sub project level
|
Analysis:Bill should be issued |
|
Pending Environmental & Social issues
|
Environment & Social Compliances(Package level): | No Pending Issue | Environment & Social Compliances(Sub Project level): | LGFS Huts at Guptkashi(7216) | project information board | LGFS Night Shelter at Sonprayag(7217) | Helmet, Jacket, Boot, Glove, Signs, project information board |
Detailed report of this Package
|
|
Quality
|
Test Information not Available. |
Number of Pics Available on Web Repository: 235 |
Number of Notice(s) issued: 69 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 10-08-2017 | Construction of Lgfs hut at tilwara | Fixing of CFB & wall cladding work is in progress at lgfs hut | Harish Chauhan | JE | GMVN Rudraprayag | See Pic |
2. | 05-08-2017 | Construction of lgfs huts at tilwara | Fixing of membrane of MPH is in progress | Harish Chauhan | JE | GMVN Rudraprayag | See Pic |
3. | 05-08-2017 | Construction of lgfs huts | Fixing of lgfs ceiling of MPH is in progress | Harish Chauhan | JE | GMVN Rudraprayag | See Pic |
4. | 19-07-2017 | Multipurpose hall | Fixing of roof shingle of MPH is in progress | Harish Chauhan | JE | GMVN Rudraprayag | See Pic |
5. | 19-07-2017 | Lgfs hut at tilwara | Internal plumbing work in hut no 13 is in progress | Harish Chauhan | JE | GMVN Rudraprayag | See Pic |
6. | 19-07-2017 | Lgfs huts at tilwara | Construction of RR Retaining wall behind hut no 9 to 13 is in progress | Harish Chauhan | JE | GMVN Rudraprayag | See Pic |
7. | 19-07-2017 | Lgfs hut at tilwara | Fixing of CFB at corners of hut no 11 is in progress | Harish Chauhan | JE | GMVN Rudraprayag | See Pic |
8. | 19-07-2017 | Lgfs huts | Tile work in toilets of hut no 12 is in progress. | Harish Chauhan | JE | GMVN Rudraprayag | See Pic |
9. | 19-07-2017 | Lgfs hut | Wall cladding work is in progress | Harish Chauhan | JE | GMVN Rudraprayag | See Pic |
10. | 27-06-2017 | Construction of lgfs hut at tilwara | Landscaping work is in progress | Harish Chauhan | JE | GMVN Rudraprayag | See Pic |
11. | 06-06-2017 | LGFS HUT AT TILWARA | Installation of concealed cistern jaquar make at hut no 13 | Harish Chauhan | JE | GMVN Rudraprayag | See Pic |
12. | 05-05-2017 | Construction of LGFS Huts at Tilwara | Lgfs huts at Tilwara made available for tourist use | Harish Chauhan | JE | GMVN Rudraprayag | See Pic |
13. | 02-05-2017 | Tilwara | Fixing of 160 KVA DG set | Ashish Aswal | AE | UEAP-T GMVN Rudraprayag | See Pic |
14. | 02-05-2017 | Tilwara | Fixing of main feeder panal at tilwara site. | Ashish Aswal | AE | UEAP-T GMVN Rudraprayag | See Pic |
15. | 02-05-2017 | Tilwara | Hut no 6 7 and 8 | Ashish Aswal | AE | UEAP-T GMVN Rudraprayag | See Pic |
16. | 02-05-2017 | Tilwara | Hut no 13 | Ashish Aswal | AE | UEAP-T GMVN Rudraprayag | See Pic |
17. | 15-04-2017 | Tilwara | LGFS huts at Tilwara | Ashish Aswal | AE | UEAP-T GMVN Rudraprayag | See Pic |
18. | 15-04-2017 | Tilwara | Work is in progress at tilwara in Multipurpose Hall. | Ashish Aswal | AE | UEAP-T GMVN Rudraprayag | See Pic |
19. | 11-04-2017 | Multipurpose Hall | Installation of ISMB BUILT UP SECTION Beam | Harish Chauhan | JE | GMVN Rudraprayag | See Pic |
20. | 29-01-2017 | Lgfs hut at jakholi | Finishing work in progress | Harish Chauhan | JE | GMVN Rudraprayag | See Pic |
|
|