UK/UEAP-T(GMVN)/DDN/06 Agreement signed
Project: UEAP-T Package No.: 2204 Package Name: UK/UEAP-T(GMVN)/DDN/06 Sanction Cost: 1858.14  lakhs
District: Rudraprayag Block: August Muni Constituency: Rudraprayag Circle: GMVN
DEA: GMVN Rudraprayag DSC: DSC Scope: Design & Supervision No.of Sub project : 6
Subproject in this package
1  7213   LGFS Huts, Multi Purpose Hall & Meditation Center at Tilwara ( KM.) (in prorgress)
2  7214   LGFS Huts at Triyuginarayan ( KM.) (in prorgress)
3  7215   LGFS Huts at Jakholi ( KM.) (completed)
4  7216   LGFS Huts at Guptkashi ( KM.) (in prorgress)
5  7217   LGFS Night Shelter at Sonprayag ( KM.) (in prorgress)
6  7218   LGFS Huts at Gaurikund ( KM.) (in prorgress)
Procurement:
Package No.: 2204        Package Name: UK/UEAP-T(GMVN)/DDN/06        Tender Date: 02-05-2014        Current Status: Agreement signed        Achieved on Date: 01-10-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UK/UEAP-T(GMVN)/DDN/06        Contractor Name: Loom Crafts Shade Systems Pvt. Ltd       
Start Date: 09-10-2014        Intended Completion Date: 31-08-2017        Original End Date:  08-04-2016
Total Bond Cost: 176686392 (1766.86 lakhs)        Variation Cost: 26127450.68 (261.27 lakhs)     Hence Total Bond Cost is   202813842.68 (2028.14 lakhs) 
LD Analysis for Milestone1: calculated LD is Rs 16166769 for +183 days        LD Analysis for Milestone2: calculated LD is Rs 61133356 for 692 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Site Development6.00 Job77.196.00 Job5.20 Job3.461.49
2.Foundation and Plinth Work6.00 Job62.226.00 Job5.40 Job3.0654.84
3.Structural Frame6.00 Job911.456.00 Job4.90 Job37.96682.39
4.Doors & Windows 6.00 Job83.776.00 Job4.20 Job2.4143.60
5.Water Supply and Sanitary work 6.00 Job116.666.00 Job4.20 Job3.7367.31
6.Electrification Works6.00 Job67.756.00 Job3.90 Job1.3524.41
7.Other Allied Works & Finishing Work 6.00 Job295.416.00 Job3.30 Job8.41150.69
8.Furnishing Work6.00 Job189.756.00 Job4.00 Job5.3696.67
Total Amount: 1804.2 65.68   1181.4
Remarks:        Work Program Made On: 02-01-2015       Updation of work program on: 11-10-2017      
Work Program Status:This Package contain more than one subproject,pleae check individua subproject for Program Expired.
Financial Progress
SNo. Date Payment
1.07-September-201522.92  lakhs
2.10-September-201536.90  lakhs
3.31-October-201551.45  lakhs
4.30-November-201559.22  lakhs
5.31-December-201589.84  lakhs
6.30-January-201663.70  lakhs
7.29-February-201644.34  lakhs
8.30-April-201654.11  lakhs
9.31-May-201679.88  lakhs
10.16-August-201670.16  lakhs
11.22-September-201692.39  lakhs
12.31-August-2017145.13  lakhs
Total 810.04  lakhs
% Payment 39.94 %
Advance Amount:  175.00  lakhs        Recovered Amount:  19.69  lakhs        Balance to be Recovered  155.31  lakhs        * Advances are at package level not sub project level
Analysis:Bill should be issued
Pending Environmental & Social issues
Environment & Social Compliances(Package level):No Pending Issue
Environment & Social Compliances(Sub Project level):
LGFS Huts at Guptkashi(7216) project information board
LGFS Night Shelter at Sonprayag(7217) Helmet, Jacket, Boot, Glove, Signs, project information board
Detailed report of this Package
Quality
Test Information not Available.
Number of Pics Available on Web Repository: 235
Number of Notice(s) issued: 69

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.10-08-2017Construction of Lgfs hut at tilwaraFixing of CFB & wall cladding work is in progress at lgfs hutHarish ChauhanJEGMVN Rudraprayag See Pic
2.05-08-2017Construction of lgfs huts at tilwaraFixing of membrane of MPH is in progressHarish ChauhanJEGMVN Rudraprayag See Pic
3.05-08-2017Construction of lgfs hutsFixing of lgfs ceiling of MPH is in progressHarish ChauhanJEGMVN Rudraprayag See Pic
4.19-07-2017Multipurpose hallFixing of roof shingle of MPH is in progressHarish ChauhanJEGMVN Rudraprayag See Pic
5.19-07-2017Lgfs hut at tilwaraInternal plumbing work in hut no 13 is in progressHarish ChauhanJEGMVN Rudraprayag See Pic
6.19-07-2017Lgfs huts at tilwaraConstruction of RR Retaining wall behind hut no 9 to 13 is in progressHarish ChauhanJEGMVN Rudraprayag See Pic
7.19-07-2017Lgfs hut at tilwaraFixing of CFB at corners of hut no 11 is in progressHarish ChauhanJEGMVN Rudraprayag See Pic
8.19-07-2017Lgfs hutsTile work in toilets of hut no 12 is in progress.Harish ChauhanJEGMVN Rudraprayag See Pic
9.19-07-2017Lgfs hutWall cladding work is in progressHarish ChauhanJEGMVN Rudraprayag See Pic
10.27-06-2017Construction of lgfs hut at tilwaraLandscaping work is in progressHarish ChauhanJEGMVN Rudraprayag See Pic
11.06-06-2017LGFS HUT AT TILWARAInstallation of concealed cistern jaquar make at hut no 13Harish ChauhanJEGMVN Rudraprayag See Pic
12.05-05-2017Construction of LGFS Huts at TilwaraLgfs huts at Tilwara made available for tourist useHarish ChauhanJEGMVN Rudraprayag See Pic
13.02-05-2017TilwaraFixing of 160 KVA DG setAshish AswalAEUEAP-T GMVN Rudraprayag See Pic
14.02-05-2017TilwaraFixing of main feeder panal at tilwara site.Ashish AswalAEUEAP-T GMVN Rudraprayag See Pic
15.02-05-2017TilwaraHut no 6 7 and 8Ashish AswalAEUEAP-T GMVN Rudraprayag See Pic
16.02-05-2017TilwaraHut no 13Ashish AswalAEUEAP-T GMVN Rudraprayag See Pic
17.15-04-2017TilwaraLGFS huts at TilwaraAshish AswalAEUEAP-T GMVN Rudraprayag See Pic
18.15-04-2017TilwaraWork is in progress at tilwara in Multipurpose Hall.Ashish AswalAEUEAP-T GMVN Rudraprayag See Pic
19.11-04-2017Multipurpose HallInstallation of ISMB BUILT UP SECTION BeamHarish ChauhanJEGMVN Rudraprayag See Pic
20.29-01-2017Lgfs hut at jakholiFinishing work in progressHarish ChauhanJEGMVN Rudraprayag See Pic