Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UK/UEAP-T(GMVN)/DDN/05 Agreement signed
Project: UEAP-T Package No.: 2203 Package Name: UK/UEAP-T(GMVN)/DDN/05 Sanction Cost: 566.49  lakhs
District: Chamoli Block: Joshimath Constituency: Badrinath Circle: GMVN
DEA: GMVN Chamoli DSC: DSC Scope: Design & Supervision No.of Sub project : 5
Subproject in this package
1  7208   Hybrid Huts at Pandukeshwar ( KM.) (in prorgress)
2  7209   Hybrid Huts at Joshimath ( KM.) (in prorgress)
3  7210   Hybrid Huts at Auli ( KM.) (in prorgress)
4  7211   Hybrid Huts at Deval ( KM.) (in prorgress)
5  7212   Hybrid Huts at Lohjung ( KM.) (in prorgress)
Procurement:
Package No.: 2203        Package Name: UK/UEAP-T(GMVN)/DDN/05        Tender Date: 12-06-2014        Current Status: Agreement signed        Achieved on Date: 01-10-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UK/UEAP-T(GMVN)/DDN/05        Contractor Name: ACME Clean Tech Solutions Ltd       
Start Date: 10-10-2014        Intended Completion Date: 30-06-2017        Original End Date:  09-04-2016
Total Bond Cost: 44096194.28 (440.96 lakhs)        Variation Cost: 6605615.89 (66.06 lakhs)     Hence Total Bond Cost is   50701810.17 (507.02 lakhs) 
LD Analysis for Milestone1: calculated LD is Rs 4034784 for +183 days        LD Analysis for Milestone2: calculated LD is Rs 13868192 for 629 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Site Development5.00 Job8.885.00 Job3.80 Job1.66.75
2.Foundation and Plinth Work5.00 Job69.025.00 Job4.95 Job16.0168.44
3.Structural Frame5.00 Job255.895.00 Job4.20 Job49.02208.97
4.Doors & Windows 5.00 Job18.535.00 Job1.50 Job1.054.63
5.Water Supply and Sanitary work 5.00 Job17.615.00 Job0.30 Job0.20.88
6.Electrification Works5.00 Job6.285.00 Job0.00 Job00.00
7.Other Allied Works & Finishing Work 5.00 Job18.685.00 Job1.10 Job0.833.55
8.Furnishing Work5.00 Job32.565.00 Job0.00 Job00.00
Total Amount: 427.45 68.71   293.22
Remarks: No Remarks       Work Program Made On: 06-01-2015      
Work Program Status:This Package contain more than one subproject,pleae check individua subproject for Program Expired.
Financial Progress
SNo. Date Payment
1.28-September-201520.42  lakhs
2.29-September-20150.42  lakhs
3.31-October-20156.92  lakhs
4.31-May-201686.41  lakhs
Total 114.17  lakhs
% Payment 22.52 %
Advance Amount:  210.99  lakhs        Recovered Amount:  0.00  lakhs        Balance to be Recovered  210.99  lakhs        * Advances are at package level not sub project level
Analysis:Bill should be issued
Pending Environmental & Social issues
Environment & Social Compliances(Package level): PUC vehicles
Environment & Social Compliances(Sub Project level):
Hybrid Huts at Pandukeshwar(7208)No Pending Issue
Hybrid Huts at Joshimath(7209)No Pending Issue
Hybrid Huts at Auli(7210)No Pending Issue
Hybrid Huts at Deval(7211) project information board
Hybrid Huts at Lohjung(7212) project information board
Detailed report of this Package
Quality
Test Information not Available.
Number of Pics Available on Web Repository: 347
Number of Notice(s) issued: 69

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.04-09-2017AuliWater line connected with hutsRajat RajputAEUEAP-T GMVN Chamoli See Pic
2.04-09-2017AuliBreast wall work is in progressRajat RajputAEUEAP-T GMVN Chamoli See Pic
3.01-04-2017pandukeshwarinteriors work in progressAshish KumarJEUEAP-T GMVN Chamoli See Pic
4.05-03-2017AuliHybrid hut at AuliAshish AswalAEUEAP-T GMVN Rudraprayag See Pic
5.05-03-2017PandukeshwarHybrid hut at PandukeshwarAshish AswalAEUEAP-T GMVN Rudraprayag See Pic
6.05-03-2017AuliHybrid hut washroomAshish AswalAEUEAP-T GMVN Rudraprayag See Pic
7.03-03-2017pandukeshwarfinishing work in progressAshish KumarJEUEAP-T GMVN Chamoli See Pic
8.03-03-2017pandukeshwarfurniture supplyAshish KumarJEUEAP-T GMVN Chamoli See Pic
9.02-03-2017aulifurniture supply and fixing work in progressAshish KumarJEUEAP-T GMVN Chamoli See Pic
10.02-03-2017aulisanitary fixture work in progressAshish KumarJEUEAP-T GMVN Chamoli See Pic
11.02-03-2017aulifinishing work in progressAshish KumarJEUEAP-T GMVN Chamoli See Pic
12.02-03-2017aulisanitary fixture work in progressAshish KumarJEUEAP-T GMVN Chamoli See Pic
13.02-03-2017aulifinishing work in progressAshish KumarJEUEAP-T GMVN Chamoli See Pic
14.02-03-2017auliinformation board at auliAshish KumarJEUEAP-T GMVN Chamoli See Pic
15.02-03-2017AuliSanitary fixtures fixed in toiletsRajat RajputAEUEAP-T GMVN Chamoli See Pic
16.02-03-2017AuliBio digester unloaded at site, yet to install.Rajat RajputAEUEAP-T GMVN Chamoli See Pic
17.02-03-2017AuliHybrid hut at AuliRajat RajputAEUEAP-T GMVN Chamoli See Pic
18.02-03-2017AuliApproch stairs work is in progressRajat RajputAEUEAP-T GMVN Chamoli See Pic
19.02-03-2017AuliProject information board at siteRajat RajputAEUEAP-T GMVN Chamoli See Pic
20.30-01-2017PandukeshwarHybrid hut at PandukeshwarAshish AswalAEUEAP-T GMVN Rudraprayag See Pic