UK/UEAP-T(GMVN)/DDN/05
Agreement signed
|
Project: |
UEAP-T |
Package No.: |
2203 |
Package Name: |
UK/UEAP-T(GMVN)/DDN/05 |
Sanction Cost: |
566.49 lakhs |
District: |
Chamoli |
Block: |
Joshimath |
Constituency: |
Badrinath |
Circle: |
GMVN |
DEA: |
GMVN Chamoli |
DSC: |
|
DSC Scope: |
Design & Supervision |
No.of Sub project : |
5 |
Subproject in this package |
1 7208 Hybrid Huts at Pandukeshwar ( KM.) (in prorgress) | 2 7209 Hybrid Huts at Joshimath ( KM.) (in prorgress) | 3 7210 Hybrid Huts at Auli ( KM.) (in prorgress) | 4 7211 Hybrid Huts at Deval ( KM.) (in prorgress) | 5 7212 Hybrid Huts at Lohjung ( KM.) (in prorgress) |
|
Procurement: |
Package No.: 2203
Package Name: UK/UEAP-T(GMVN)/DDN/05
Tender Date: 12-06-2014
Current Status: Agreement signed
Achieved on Date: 01-10-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UK/UEAP-T(GMVN)/DDN/05
Contractor Name: ACME Clean Tech Solutions Ltd
|
Start Date: 10-10-2014
Intended Completion Date: 30-06-2017
Original End Date: 09-04-2016
|
Total Bond Cost: 44096194.28 (440.96 lakhs)
Variation Cost: 6605615.89 (66.06 lakhs) Hence Total Bond Cost is 50701810.17 (507.02 lakhs)
|
LD Analysis for Milestone1: calculated LD is Rs 4034784 for +183 days
LD Analysis for Milestone2: calculated LD is Rs 13868192 for 629 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Site Development | 5.00 Job | 8.88 | 5.00 Job | 3.80 Job | 1.6 | 6.75 | 2. | Foundation and Plinth Work | 5.00 Job | 69.02 | 5.00 Job | 4.95 Job | 16.01 | 68.44 | 3. | Structural Frame | 5.00 Job | 255.89 | 5.00 Job | 4.20 Job | 49.02 | 208.97 | 4. | Doors & Windows | 5.00 Job | 18.53 | 5.00 Job | 1.50 Job | 1.05 | 4.63 | 5. | Water Supply and Sanitary work | 5.00 Job | 17.61 | 5.00 Job | 0.30 Job | 0.2 | 0.88 | 6. | Electrification Works | 5.00 Job | 6.28 | 5.00 Job | 0.00 Job | 0 | 0.00 | 7. | Other Allied Works & Finishing Work | 5.00 Job | 18.68 | 5.00 Job | 1.10 Job | 0.83 | 3.55 | 8. | Furnishing Work | 5.00 Job | 32.56 | 5.00 Job | 0.00 Job | 0 | 0.00 |
Total Amount: |
427.45 |
|
68.71 |
293.22 |
|
Remarks:
No Remarks
Work Program Made On:
06-01-2015
|
|
Work Program Status:This Package contain more than one subproject,pleae check individua subproject for Program Expired. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 28-September-2015 | 20.42 lakhs |
2. | 29-September-2015 | 0.42 lakhs |
3. | 31-October-2015 | 6.92 lakhs |
4. | 31-May-2016 | 86.41 lakhs |
Total |
114.17 lakhs |
% Payment |
22.52 % |
|
Advance Amount: 210.99 lakhs
Recovered Amount: 0.00 lakhs
Balance to be Recovered 210.99 lakhs
* Advances are at package level not sub project level
|
Analysis:Bill should be issued |
|
Pending Environmental & Social issues
|
Environment & Social Compliances(Package level): | PUC vehicles | Environment & Social Compliances(Sub Project level): | Hybrid Huts at Pandukeshwar(7208) | No Pending Issue | Hybrid Huts at Joshimath(7209) | No Pending Issue | Hybrid Huts at Auli(7210) | No Pending Issue | Hybrid Huts at Deval(7211) | project information board | Hybrid Huts at Lohjung(7212) | project information board |
Detailed report of this Package
|
|
Quality
|
Test Information not Available. |
Number of Pics Available on Web Repository: 347 |
Number of Notice(s) issued: 69 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 04-09-2017 | Auli | Water line connected with huts | Rajat Rajput | AE | UEAP-T GMVN Chamoli | See Pic |
2. | 04-09-2017 | Auli | Breast wall work is in progress | Rajat Rajput | AE | UEAP-T GMVN Chamoli | See Pic |
3. | 01-04-2017 | pandukeshwar | interiors work in progress | Ashish Kumar | JE | UEAP-T GMVN Chamoli | See Pic |
4. | 05-03-2017 | Auli | Hybrid hut at Auli | Ashish Aswal | AE | UEAP-T GMVN Rudraprayag | See Pic |
5. | 05-03-2017 | Pandukeshwar | Hybrid hut at Pandukeshwar | Ashish Aswal | AE | UEAP-T GMVN Rudraprayag | See Pic |
6. | 05-03-2017 | Auli | Hybrid hut washroom | Ashish Aswal | AE | UEAP-T GMVN Rudraprayag | See Pic |
7. | 03-03-2017 | pandukeshwar | finishing work in progress | Ashish Kumar | JE | UEAP-T GMVN Chamoli | See Pic |
8. | 03-03-2017 | pandukeshwar | furniture supply | Ashish Kumar | JE | UEAP-T GMVN Chamoli | See Pic |
9. | 02-03-2017 | auli | furniture supply and fixing work in progress | Ashish Kumar | JE | UEAP-T GMVN Chamoli | See Pic |
10. | 02-03-2017 | auli | sanitary fixture work in progress | Ashish Kumar | JE | UEAP-T GMVN Chamoli | See Pic |
11. | 02-03-2017 | auli | finishing work in progress | Ashish Kumar | JE | UEAP-T GMVN Chamoli | See Pic |
12. | 02-03-2017 | auli | sanitary fixture work in progress | Ashish Kumar | JE | UEAP-T GMVN Chamoli | See Pic |
13. | 02-03-2017 | auli | finishing work in progress | Ashish Kumar | JE | UEAP-T GMVN Chamoli | See Pic |
14. | 02-03-2017 | auli | information board at auli | Ashish Kumar | JE | UEAP-T GMVN Chamoli | See Pic |
15. | 02-03-2017 | Auli | Sanitary fixtures fixed in toilets | Rajat Rajput | AE | UEAP-T GMVN Chamoli | See Pic |
16. | 02-03-2017 | Auli | Bio digester unloaded at site, yet to install. | Rajat Rajput | AE | UEAP-T GMVN Chamoli | See Pic |
17. | 02-03-2017 | Auli | Hybrid hut at Auli | Rajat Rajput | AE | UEAP-T GMVN Chamoli | See Pic |
18. | 02-03-2017 | Auli | Approch stairs work is in progress | Rajat Rajput | AE | UEAP-T GMVN Chamoli | See Pic |
19. | 02-03-2017 | Auli | Project information board at site | Rajat Rajput | AE | UEAP-T GMVN Chamoli | See Pic |
20. | 30-01-2017 | Pandukeshwar | Hybrid hut at Pandukeshwar | Ashish Aswal | AE | UEAP-T GMVN Rudraprayag | See Pic |
|
|