Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UK/UEAP-T(GMVN)/DDN/03 Agreement signed
Project: UEAP-T Package No.: 2201 Package Name: UK/UEAP-T(GMVN)/DDN/03 Sanction Cost: 376.07  lakhs
District: Uttarkashi Block: Bhatwari Constituency: Gangotri Circle: GMVN
DEA: GMVN Uttarkashi DSC: DSC Scope: Design & Supervision No.of Sub project : 6
Subproject in this package
1  7201   FRP Huts at Raithal ( KM.) (completed)
2  7202   FRP Huts at Barsu ( KM.) (completed)
3  7203   Hybrid Huts at Purola ( KM.) (completed)
4  7204   Hybrid Huts at Barkot ( KM.) (completed)
5  7205   Hybrid Huts at Phoolchatti ( KM.) (completed)
6  7206   Hybrid Huts at Harsil ( KM.) (completed)
Procurement:
Package No.: 2201        Package Name: UK/UEAP-T(GMVN)/DDN/03        Tender Date: 12-06-2014        Current Status: Agreement signed        Achieved on Date: 01-10-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UK/UEAP-T(GMVN)/DDN/03        Contractor Name: ACME Clean Tech Solutions Ltd       
Start Date: 10-10-2014        Intended Completion Date: 30-06-2017        Original End Date:  09-04-2016
Total Bond Cost: 30317675.03 (303.18 lakhs)        Variation Cost: 4498797.22 (44.99 lakhs)     Hence Total Bond Cost is   34816472.25 (348.16 lakhs) 
LD Analysis for Milestone1: calculated LD is Rs 2774097 for 183 days        LD Analysis for Milestone2: calculated LD is Rs 9535011 for 629 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Site Development6.00 Job11.036.00 Job6.00 Job3.6311.03
2.Foundation and Plinth Work6.00 Job41.716.00 Job6.00 Job13.8641.71
3.Structural Frame6.00 Job184.706.00 Job6.00 Job60.74184.70
4.Water Supply and Sanitary work 6.00 Job16.426.00 Job6.00 Job5.4116.42
5.Electrification Works6.00 Job4.856.00 Job6.00 Job1.594.85
6.Other Allied Works & Finishing Work 6.00 Job10.966.00 Job6.00 Job3.6410.96
7.Furnishing Work6.00 Job24.536.00 Job6.00 Job8.1324.53
8.Doors & Windows 4.00 Job8.984.00 Job4.00 Job3.018.98
Total Amount: 303.18 100   303.18
Remarks: No Remarks       Work Program Made On: 16-01-2015       Updation of work program on: 16-01-2015      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.28-September-201535.64  lakhs
2.31-October-20154.39  lakhs
Total 40.03  lakhs
% Payment 11.5 %
Advance Amount:  114.74  lakhs        Recovered Amount:  114.74  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Analysis:Bill should be issued
Pending Environmental & Social issues
Detailed report of this Package
Quality
Test Information not Available.
Number of Pics Available on Web Repository: 256
Number of Notice(s) issued: 69

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.02-09-2017Hybrid Hut at PhoolchattiSite Development work has been completedSanjay GuptaProcurement OfficerUEAP-T GMVN See Pic
2.02-09-2017Hybrid Hut at PhoolchattiHybrid Hut at PhoolchattiSanjay GuptaProcurement OfficerUEAP-T GMVN See Pic
3.02-09-2017Hybrid HutWork of Hybrid Hut has been completedSanjay GuptaProcurement OfficerUEAP-T GMVN See Pic
4.02-09-2017Hybrid Hut at BarsuCeiling and Panelling work have been completedSanjay GuptaProcurement OfficerUEAP-T GMVN See Pic
5.02-09-2017Hybrid Hut at BarsuBeds and linen have been placedSanjay GuptaProcurement OfficerUEAP-T GMVN See Pic
6.02-09-2017Hybrid Hut at BarsuWork of fixing of Aluminium doors shutter has been completedSanjay GuptaProcurement OfficerUEAP-T GMVN See Pic
7.02-09-2017Hybrid Hut at BarsuWork of Hybrid Huts have been completedSanjay GuptaProcurement OfficerUEAP-T GMVN See Pic
8.02-09-2017Hybrid Hut at RaithalWith of fixing of door shutter has been completedSanjay GuptaProcurement OfficerUEAP-T GMVN See Pic
9.02-09-2017Hybrid Hut at RaithalCeiling and Panelling work have been completedSanjay GuptaProcurement OfficerUEAP-T GMVN See Pic
10.02-09-2017Hybrid Hut at HarsilCeiling and Panelling work have been completedSanjay GuptaProcurement OfficerUEAP-T GMVN See Pic
11.02-09-2017Hybrid Hut at RaithalBeds and linen has been placedSanjay GuptaProcurement OfficerUEAP-T GMVN See Pic
12.02-09-2017Hybrid Hut at RaithalWork of toilet has been completedSanjay GuptaProcurement OfficerUEAP-T GMVN See Pic
13.02-09-2017Hybrid Hut at HarsilWork of fixing of door shutter has been completedSanjay GuptaProcurement OfficerUEAP-T GMVN See Pic
14.02-09-2017Hybrid Hut at HarsilBeds and linen have been placedSanjay GuptaProcurement OfficerUEAP-T GMVN See Pic
15.02-09-2017Hybrid Hut at HarsilWork of toilet has been completedSanjay GuptaProcurement OfficerUEAP-T GMVN See Pic
16.29-07-2017Hybrid Huts at PurolaWork of fixing of doors shutter has been completedSanjay GuptaProcurement OfficerUEAP-T GMVN See Pic
17.29-07-2017Hybrid Hut at PurolaPlacing of beds mattress and curtains has been completedSanjay GuptaProcurement OfficerUEAP-T GMVN See Pic
18.29-07-2017Hybrid Hut at PurolaWork of fixing of sanitary fixtures has been completedSanjay GuptaProcurement OfficerUEAP-T GMVN See Pic
19.29-07-2017Hybrid Hut at BarkotWork of fixing of doors shutter has been completedSanjay GuptaProcurement OfficerUEAP-T GMVN See Pic
20.29-07-2017Hybrid Hut at BarkotWork of placing of beds,mattress and curtains has been completedSanjay GuptaProcurement OfficerUEAP-T GMVN See Pic