UK/UEAP-T(GMVN)/DDN/03
Agreement signed
|
Project: |
UEAP-T |
Package No.: |
2201 |
Package Name: |
UK/UEAP-T(GMVN)/DDN/03 |
Sanction Cost: |
376.07 lakhs |
District: |
Uttarkashi |
Block: |
Bhatwari |
Constituency: |
Gangotri |
Circle: |
GMVN |
DEA: |
GMVN Uttarkashi |
DSC: |
|
DSC Scope: |
Design & Supervision |
No.of Sub project : |
6 |
Subproject in this package |
1 7201 FRP Huts at Raithal ( KM.) (completed) | 2 7202 FRP Huts at Barsu ( KM.) (completed) | 3 7203 Hybrid Huts at Purola ( KM.) (completed) | 4 7204 Hybrid Huts at Barkot ( KM.) (completed) | 5 7205 Hybrid Huts at Phoolchatti ( KM.) (completed) | 6 7206 Hybrid Huts at Harsil ( KM.) (completed) |
|
Procurement: |
Package No.: 2201
Package Name: UK/UEAP-T(GMVN)/DDN/03
Tender Date: 12-06-2014
Current Status: Agreement signed
Achieved on Date: 01-10-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UK/UEAP-T(GMVN)/DDN/03
Contractor Name: ACME Clean Tech Solutions Ltd
|
Start Date: 10-10-2014
Intended Completion Date: 30-06-2017
Original End Date: 09-04-2016
|
Total Bond Cost: 30317675.03 (303.18 lakhs)
Variation Cost: 4498797.22 (44.99 lakhs) Hence Total Bond Cost is 34816472.25 (348.16 lakhs)
|
LD Analysis for Milestone1: calculated LD is Rs 2774097 for 183 days
LD Analysis for Milestone2: calculated LD is Rs 9535011 for 629 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Site Development | 6.00 Job | 11.03 | 6.00 Job | 6.00 Job | 3.63 | 11.03 | 2. | Foundation and Plinth Work | 6.00 Job | 41.71 | 6.00 Job | 6.00 Job | 13.86 | 41.71 | 3. | Structural Frame | 6.00 Job | 184.70 | 6.00 Job | 6.00 Job | 60.74 | 184.70 | 4. | Water Supply and Sanitary work | 6.00 Job | 16.42 | 6.00 Job | 6.00 Job | 5.41 | 16.42 | 5. | Electrification Works | 6.00 Job | 4.85 | 6.00 Job | 6.00 Job | 1.59 | 4.85 | 6. | Other Allied Works & Finishing Work | 6.00 Job | 10.96 | 6.00 Job | 6.00 Job | 3.64 | 10.96 | 7. | Furnishing Work | 6.00 Job | 24.53 | 6.00 Job | 6.00 Job | 8.13 | 24.53 | 8. | Doors & Windows | 4.00 Job | 8.98 | 4.00 Job | 4.00 Job | 3.01 | 8.98 |
Total Amount: |
303.18 |
|
100 |
303.18 |
|
Remarks:
No Remarks
Work Program Made On:
16-01-2015
Updation of work program on:
16-01-2015
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 28-September-2015 | 35.64 lakhs |
2. | 31-October-2015 | 4.39 lakhs |
Total |
40.03 lakhs |
% Payment |
11.5 % |
|
Advance Amount: 114.74 lakhs
Recovered Amount: 114.74 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
Analysis:Bill should be issued |
|
Pending Environmental & Social issues
|
|
Quality
|
Test Information not Available. |
Number of Pics Available on Web Repository: 256 |
Number of Notice(s) issued: 69 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 02-09-2017 | Hybrid Hut at Phoolchatti | Site Development work has been completed | Sanjay Gupta | Procurement Officer | UEAP-T GMVN | See Pic |
2. | 02-09-2017 | Hybrid Hut at Phoolchatti | Hybrid Hut at Phoolchatti | Sanjay Gupta | Procurement Officer | UEAP-T GMVN | See Pic |
3. | 02-09-2017 | Hybrid Hut | Work of Hybrid Hut has been completed | Sanjay Gupta | Procurement Officer | UEAP-T GMVN | See Pic |
4. | 02-09-2017 | Hybrid Hut at Barsu | Ceiling and Panelling work have been completed | Sanjay Gupta | Procurement Officer | UEAP-T GMVN | See Pic |
5. | 02-09-2017 | Hybrid Hut at Barsu | Beds and linen have been placed | Sanjay Gupta | Procurement Officer | UEAP-T GMVN | See Pic |
6. | 02-09-2017 | Hybrid Hut at Barsu | Work of fixing of Aluminium doors shutter has been completed | Sanjay Gupta | Procurement Officer | UEAP-T GMVN | See Pic |
7. | 02-09-2017 | Hybrid Hut at Barsu | Work of Hybrid Huts have been completed | Sanjay Gupta | Procurement Officer | UEAP-T GMVN | See Pic |
8. | 02-09-2017 | Hybrid Hut at Raithal | With of fixing of door shutter has been completed | Sanjay Gupta | Procurement Officer | UEAP-T GMVN | See Pic |
9. | 02-09-2017 | Hybrid Hut at Raithal | Ceiling and Panelling work have been completed | Sanjay Gupta | Procurement Officer | UEAP-T GMVN | See Pic |
10. | 02-09-2017 | Hybrid Hut at Harsil | Ceiling and Panelling work have been completed | Sanjay Gupta | Procurement Officer | UEAP-T GMVN | See Pic |
11. | 02-09-2017 | Hybrid Hut at Raithal | Beds and linen has been placed | Sanjay Gupta | Procurement Officer | UEAP-T GMVN | See Pic |
12. | 02-09-2017 | Hybrid Hut at Raithal | Work of toilet has been completed | Sanjay Gupta | Procurement Officer | UEAP-T GMVN | See Pic |
13. | 02-09-2017 | Hybrid Hut at Harsil | Work of fixing of door shutter has been completed | Sanjay Gupta | Procurement Officer | UEAP-T GMVN | See Pic |
14. | 02-09-2017 | Hybrid Hut at Harsil | Beds and linen have been placed | Sanjay Gupta | Procurement Officer | UEAP-T GMVN | See Pic |
15. | 02-09-2017 | Hybrid Hut at Harsil | Work of toilet has been completed | Sanjay Gupta | Procurement Officer | UEAP-T GMVN | See Pic |
16. | 29-07-2017 | Hybrid Huts at Purola | Work of fixing of doors shutter has been completed | Sanjay Gupta | Procurement Officer | UEAP-T GMVN | See Pic |
17. | 29-07-2017 | Hybrid Hut at Purola | Placing of beds mattress and curtains has been completed | Sanjay Gupta | Procurement Officer | UEAP-T GMVN | See Pic |
18. | 29-07-2017 | Hybrid Hut at Purola | Work of fixing of sanitary fixtures has been completed | Sanjay Gupta | Procurement Officer | UEAP-T GMVN | See Pic |
19. | 29-07-2017 | Hybrid Hut at Barkot | Work of fixing of doors shutter has been completed | Sanjay Gupta | Procurement Officer | UEAP-T GMVN | See Pic |
20. | 29-07-2017 | Hybrid Hut at Barkot | Work of placing of beds,mattress and curtains has been completed | Sanjay Gupta | Procurement Officer | UEAP-T GMVN | See Pic |
|
|