Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/PWD/09/03/RD/022 Agreement signed
Project: UDRP-RB Package No.: 22 Package Name: UDRP/PWD/09/03/RD/022 Sanction Cost: 1421.70  lakhs
District: Almora Block: Sult Constituency: Salt Circle: Pithoragarh WB Circle
DEA: DEA Bageshwar DSC: Royal Haskoning DHV DSC Scope: only Supervision No.of Sub project : 1
Subproject in this package
1  1024   Marchula Syalde Deghat MR (44.600 KM.) (completed)
Procurement:
Package No.: 22        Package Name: UDRP/PWD/09/03/RD/022        Tender Date: 22-02-2014        Current Status: Agreement signed        Achieved on Date: 09-09-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/09/03/RD/022        Contractor Name: Trilok Singh Ram Singh Jamnal       
Start Date: 16-09-2014        Intended Completion Date: 29-04-2016        Original End Date:  15-12-2015
Total Bond Cost: 112054759.5 (1120.55 lakhs)        Variation Cost: 31623570.90 (316.24 lakhs)     Hence Total Bond Cost is   143678330.4 (1436.78 lakhs) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence1.00 KM37.891.00 KM1.00 KM2.6437.89
2.R/Wall, B/ Wall Type Protection works2934.00 m327.802934.00 m2934.00 m22.82327.80
3.GSB/RBI/G-10.10 KM0.780.10 KM0.10 KM0.060.78
4.G-20.10 KM0.630.10 KM0.10 KM0.040.63
5.G-32.33 KM4.682.33 KM2.33 KM0.334.68
6.PC/CC i/c Prime Coat, Tack Coat44.60 KM538.7644.60 KM44.60 KM37.5538.76
7.Cause Way21.00 No65.3021.00 No21.00 No4.5565.30
8.Culverts/Scupper 51.00 No219.8251.00 No51.00 No15.3219.82
9.longitudinal Drain41800.00 m97.6841800.00 m41800.00 m6.897.68
10.Crash Barrier975.00 m23.99975.00 m975.00 m1.6723.99
11.Parapet1400.00 No54.541400.00 No1400.00 No3.854.54
12.Road Furniture339.00 No17.54339.00 No339.00 No1.2217.54
13.Other Allied Works & Finishing Work 1.00 Job47.381.00 Job1.00 Job3.347.38
Total Amount: 1436.79 100   1436.79
Remarks: No Remarks       Work Program Made On: 04-10-2014       Updation of work program on: 27-11-2017      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.03-December-2014125.54  lakhs
2.29-December-20140.40  lakhs
3.02-February-201514.38  lakhs
4.31-March-2015103.78  lakhs
5.12-June-2015202.80  lakhs
6.31-July-2015284.15  lakhs
7.30-October-2015222.48  lakhs
8.27-January-2016235.37  lakhs
9.05-March-20161.32  lakhs
10.31-March-2016105.70  lakhs
11.04-May-201642.05  lakhs
12.30-July-201698.71  lakhs
Total 1436.68  lakhs
% Payment 99.99 %
Advance Amount:  677.62  lakhs        Recovered Amount:  677.62  lakhs        Balance to be Recovered  -0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 508     No. of Test Done : 490      No. of Test Passed : 473      No. of Test Failed : 17   Test report of this package
Number of Pics Available on Web Repository: 163
Number of Notice(s) issued: 65

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.10-03-2016Ch.59.425Const of protection work u/s face of 10.00 mtr span rcc bridge.Manoj SharmaJEUDRP R&B Bageshwar See Pic
2.10-03-2016Ch. 51.650Const of causewayManoj SharmaJEUDRP R&B Bageshwar See Pic
3.10-03-2016ch.47.425Const of U type drainManoj SharmaJEUDRP R&B Bageshwar See Pic
4.10-03-2016Ch.29.650Widening and improvement of hp bend .Manoj SharmaJEUDRP R&B Bageshwar See Pic
5.07-02-2016Ch.29.650Const of R.wall and parapets near hp bendManoj SharmaJEUDRP R&B Bageshwar See Pic
6.07-02-2016Ch.59.425Inspection of 10 mtr span rcc bridge by CE sir.Manoj SharmaJEUDRP R&B Bageshwar See Pic
7.07-02-2016Ch 34.400CE and SE sir inspection the roadManoj SharmaJEUDRP R&B Bageshwar See Pic
8.05-02-2016Ch 34.400Site Inspection by C.E.SirSanjeev BhattAEUDRP R&B Bageshwar See Pic
9.05-02-201659.425Site inspection by chief engineer SirSanjeev BhattAEUDRP R&B Bageshwar See Pic
10.05-02-2016Ch 28.075Site inspection C.E.sirSanjeev BhattAEUDRP R&B Bageshwar See Pic
11.09-01-2016Ch.64.600Const of causeway and protection work.Manoj SharmaJEUDRP R&B Bageshwar See Pic
12.09-01-2016Ch. 59.825Const of rcc culvertManoj SharmaJEUDRP R&B Bageshwar See Pic
13.09-01-2016Ch.47.850Const of causewayManoj SharmaJEUDRP R&B Bageshwar See Pic
14.09-01-2016Ch.41.100Const of causewayManoj SharmaJEUDRP R&B Bageshwar See Pic
15.09-01-2016Ch.67.225Road surfaceManoj SharmaJEUDRP R&B Bageshwar See Pic
16.09-01-2016Ch.69.400Const of causewayManoj SharmaJEUDRP R&B Bageshwar See Pic
17.08-01-2016Ch 62.750Construction of B / WallSanjeev BhattAEUDRP R&B Bageshwar See Pic
18.08-01-2016Ch 60.850Construction of B/WallSanjeev BhattAEUDRP R&B Bageshwar See Pic
19.08-01-2016Ch 64.600Construction of R/Wall & Cause waySanjeev BhattAEUDRP R&B Bageshwar See Pic
20.08-01-2016Ch 66.975Construction of R/WallSanjeev BhattAEUDRP R&B Bageshwar See Pic