Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UK/UEAP-UJS/WSS-KU/01-01 Agreement signed
Project: UEAP-WS Package No.: 2112 Package Name: UK/UEAP-UJS/WSS-KU/01-01 Sanction Cost: 216.55  lakhs
District: Bageshwar Block: 0072 Constituency: 47 Circle:
DEA: DEA WS Kapkot DSC: DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  7112   Kapkot (GLSR 2 No. & Distribution Network) (0.000 KM.) (in prorgress)
Procurement:
Package No.: 2112        Package Name: UK/UEAP-UJS/WSS-KU/01-01        Tender Date: 23-03-2017        Current Status: Agreement signed        Achieved on Date: 26-05-2017

Construction Phase

Agreement Details
Bond/Agreement Name: UK/UEAP-UJS/WSS-KU/01-01        Contractor Name: Kashmirilal Constructions (P) Ltd.       
Start Date: 26-05-2017        Intended Completion Date: 20-10-2017       
Total Bond Cost: 21021293.6 (210.21 lakhs)       
LD Analysis for Milestone1: calculated LD is Rs 9607054 for 914 days        LD Analysis for Milestone2: calculated LD is Rs 9607054 for 914 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.GLSRs2.00 No57.002.00 No1.75 No23.7349.88
2.Pipe Line Works with (Main/ Distribution)8030.00 m42.848030.00 m7200.00 m18.2738.41
3.Env. Man & Moni Plan3.00 Job4.223.00 Job1.00 Job0.671.41
4.Provisional Sum5.00 Job11.685.00 Job0.00 Job00.00
5.Site Development4.00 Job62.344.00 Job3.50 Job25.9554.54
6.Structural Frame2.00 Job7.442.00 Job2.00 Job3.547.44
7.Other Allied Works & Finishing Work 3.00 Job24.693.00 Job1.00 Job3.928.23
8.Furnishing Work0.00 Job0.000.00 Job0.00 Job00.00
Total Amount: 210.21 76.07   159.91
Remarks: No Remarks       Work Program Made On: 21-09-2017       Updation of work program on: 21-09-2017      
Work Program Status:Program Expired.
Financial Progress
No Financial Progress.
Analysis:Not applicable because there is no Physical and Financial Progress
Advance Amount:  21.02  lakhs        Recovered Amount:  0.00  lakhs        Balance to be Recovered  21.02  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Environment & Social Compliances(Package level):Staff not deputed yet
Environment & Social Compliances(Sub Project level):
Kapkot (GLSR 2 No. & Distribution Network)(7112)No Pending Issue
Detailed report of this Package
Quality
Test Information not Available.
Number of Pics Available on Web Repository: 4
Number of Notice(s) issued: 8

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.26-09-2017Binsar I wellAE Sir JE Sir visited Binsar Tank SiteRajesh UpadhyayProject ManagerUEAP-WS Bageshwar See Pic
2.26-09-2017Aithan Pipe line3115 mt Aithan pipe line alignment hydro testing.Rajesh UpadhyayProject ManagerUEAP-WS Bageshwar See Pic
3.18-09-2017Aithan TankChain link fencing work going on progress.Rajesh UpadhyayProject ManagerUEAP-WS Bageshwar See Pic
4.15-09-2017Aithan TankTank Inlet and outlet connection work is completed. Chain link fencing work going on progress.Rajesh UpadhyayProject ManagerUEAP-WS Bageshwar See Pic