Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UK/UEAP-WSS/UJS/GW/02 Agreement signed
Project: UEAP-WS Package No.: 2109 Package Name: UK/UEAP-WSS/UJS/GW/02 Sanction Cost: 3047.00  lakhs
District: Pauri Block: Khirsu Constituency: Srinagar Circle:
DEA: DEA WS Srinagar And Pauri DSC: DSC Scope: Design & Supervision No.of Sub project : 1
Subproject in this package
1  7109   Srinagar-And-Pauri-Water-Supply-Scheme Phase1 ( KM.) (completed)
Procurement:
Package No.: 2109        Package Name: UK/UEAP-WSS/UJS/GW/02        Tender Date: 10-10-2014        Current Status: Agreement signed        Achieved on Date: 05-12-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UK/UEAP-WSS/UJS/GW/02        Contractor Name: RK Engineers Sales Ltd       
Start Date: 19-01-2015        Intended Completion Date: 30-06-2017        Original End Date:  18-07-2016
Total Bond Cost: 333299052 (3332.99 lakhs)       
LD Analysis for Milestone1: calculated LD is Rs 30330300 for +182 days        LD Analysis for Milestone2: calculated LD is Rs 59327400 for 356 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Infiltration Well/Tube Well3.00 No384.003.00 No3.00 No12.68384.00
2.Pump House1.00 No24.651.00 No1.00 No0.8124.65
3.GLSRs3.00 No190.003.00 No3.00 No6.28190.00
4.Rehabilitation of WTP/HFRF 3.00 No247.853.00 No3.00 No8.19247.85
5.Pipe Line Works with (Main/ Distribution)37400.00 m1000.0037400.00 m37400.00 m33.031000.00
6.Electrical and Instrumentation work7.00 No795.617.00 No7.00 No26.28795.61
7.Office Building1.00 No59.201.00 No1.00 No1.9659.20
8.Env. Man & Moni Plan1.00 Job5.611.00 Job1.00 Job0.195.61
9.Provisional Sum1.00 Job321.001.00 Job1.00 Job10.6321.00
Total Amount: 3027.92 100   3027.92
Remarks: No Remarks       Work Program Made On: 30-03-2015       Updation of work program on: 30-03-2015      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.28-September-201598.85  lakhs
2.30-October-2015153.09  lakhs
3.18-December-2015120.08  lakhs
4.17-March-2016259.06  lakhs
5.22-March-2016131.20  lakhs
6.17-June-2016124.00  lakhs
7.25-June-2016107.53  lakhs
8.24-September-201652.66  lakhs
9.26-October-2016172.30  lakhs
10.07-January-2017447.06  lakhs
11.14-March-201776.28  lakhs
12.29-April-2017123.42  lakhs
13.22-June-2017450.37  lakhs
14.28-June-2017262.72  lakhs
15.24-August-2017155.70  lakhs
Total 2734.32  lakhs
% Payment 82.04 %
Advance Amount:  479.41  lakhs        Recovered Amount:  479.41  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Analysis:Bill should be issued
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 4     No. of Test Done : 4      No. of Test Passed : 4      No. of Test Failed : 0   Test report of this package
Number of Pics Available on Web Repository: 152
Number of Notice(s) issued: 181

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.28-03-2017Raw waterRaw waterAshok NegiDPMPIU WS See Pic
2.28-03-2017Panel roomRaw waterAshok NegiDPMPIU WS See Pic
3.28-03-2017Raw water pumphouseFinishingAshok NegiDPMPIU WS See Pic
4.28-03-2017Raw water p houseFinishingAshok NegiDPMPIU WS See Pic
5.28-03-2017Paving areaFinishingAshok NegiDPMPIU WS See Pic
6.28-03-2017WtpFinishingAshok NegiDPMPIU WS See Pic
7.28-03-2017Scada roomFinishingAshok NegiDPMPIU WS See Pic
8.04-03-2017Scada Rm. At WTPFinal touch is in progressDilip Chand GuptaConstruction SupervisorDSC WS ADB Pauri See Pic
9.25-01-2017TubewellPumps installationAshok NegiDPMPIU WS See Pic
10.25-01-2017WtpRepair worksAshok NegiDPMPIU WS See Pic
11.24-01-2017500kl sumpinspection being mad by the seanior officls of pmu.dsc staff membr concerned contractors staff membar at sringarRakesh SharmaContractor Project ManagerUEAP-WS Pauri See Pic
12.24-01-2017500kl and tubewell areaInspection being carried on by senior officals . Dse staff member and concerned contractors staff membersParveen SainiAEUEAP UJS Pauri See Pic
13.21-01-2017Tuble srinagerValve fixingParveen SainiAEUEAP UJS Pauri See Pic
14.20-01-2017raw water pump houselandscaping at raw water pump house sringarRakesh SharmaContractor Project ManagerUEAP-WS Pauri See Pic
15.17-01-2017clear water pump house6mld clear water pump houseRakesh SharmaContractor Project ManagerUEAP-WS Pauri See Pic
16.16-01-2017raw water pump houseraw water pump house wall workRakesh SharmaContractor Project ManagerUEAP-WS Pauri See Pic
17.04-01-2017Pump houseFinishingAshok NegiDPMPIU WS See Pic
18.04-01-2017500 kl sumpFinishingAshok NegiDPMPIU WS See Pic
19.07-12-2016sringar automation workautomation work in. progressRakesh SharmaContractor Project ManagerUEAP-WS Pauri See Pic
20.06-12-2016sringar rbf sitepump house and 500kl sumpRakesh SharmaContractor Project ManagerUEAP-WS Pauri See Pic