UK/UEAP-WSS/UJS/GW/01/lot5
Agreement signed
|
Project: |
UEAP-WS |
Package No.: |
2108 |
Package Name: |
UK/UEAP-WSS/UJS/GW/01/lot5 |
Sanction Cost: |
440.00 lakhs |
District: |
Uttarkashi |
Block: |
Devaprayag |
Constituency: |
Deoprayag |
Circle: |
|
DEA: |
DEA WS Uttarkashi |
DSC: |
|
DSC Scope: |
Design & Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 7108 Devprayag-Water-Supply-Scheme ( KM.) (completed) |
|
Procurement: |
Package No.: 2108
Package Name: UK/UEAP-WSS/UJS/GW/01/lot5
Tender Date: 09-12-2014
Current Status: Agreement signed
Achieved on Date: 05-12-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UK/UEAP-WSS/UJS/GW/01/lot5
Contractor Name: Kashmirilal Constructions (P) Ltd.
|
Start Date: 09-03-2015
Intended Completion Date: 30-06-2017
Original End Date: 09-09-2016
|
Total Bond Cost: 51875049.6 (518.75 lakhs)
|
LD Analysis for Milestone1: calculated LD is Rs 4772592 for +184 days
LD Analysis for Milestone2: calculated LD is Rs 7651710 for 295 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | GLSRs | 1.00 No | 6.50 | 1.00 No | 1.00 No | 1.2 | 6.50 | 2. | Uttaranchal Koop | 3.00 No | 31.29 | 3.00 No | 3.00 No | 5.8 | 31.29 | 3. | Pipe Line Works with (Main/ Distribution) | 31000.00 m | 409.74 | 31000.00 m | 31000.00 m | 75.9 | 409.74 | 4. | Office Building | 1.00 No | 65.97 | 1.00 No | 1.00 No | 12.22 | 65.97 | 5. | Env. Man & Moni Plan | 1.00 Job | 13.41 | 1.00 Job | 1.00 Job | 2.48 | 13.41 | 6. | Provisional Sum | 1.00 Job | 12.90 | 1.00 Job | 1.00 Job | 2.39 | 12.90 |
Total Amount: |
539.81 |
|
100 |
539.81 |
|
Remarks:
No Remarks
Work Program Made On:
30-03-2015
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 23-November-2015 | 47.19 lakhs |
2. | 22-March-2016 | 32.78 lakhs |
3. | 29-June-2016 | 62.59 lakhs |
4. | 26-October-2016 | 62.23 lakhs |
5. | 07-January-2017 | 61.01 lakhs |
6. | 14-March-2017 | 45.31 lakhs |
7. | 29-April-2017 | 88.52 lakhs |
8. | 21-June-2017 | 55.19 lakhs |
Total |
454.82 lakhs |
% Payment |
87.68 % |
|
Advance Amount: 97.66 lakhs
Recovered Amount: 97.66 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
Analysis:Bill should be issued |
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 142 |
Number of Notice(s) issued: 113 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 26-04-2017 | 50KL GLSR Devprayag | 50KL GLSR Completed | Bhuwan Chandra Bhatt | Construction Supervisor | DSC WS ADB Tehri | See Pic |
2. | 09-04-2017 | Office Building boundary wall | Boundary wall protection work is in progress. | Bhuwan Chandra Bhatt | Construction Supervisor | DSC WS ADB Tehri | See Pic |
3. | 20-03-2017 | Diwani Gaad Source | Uttaranchal Koop installation work in progress | Bhuwan Chandra Bhatt | Construction Supervisor | DSC WS ADB Tehri | See Pic |
4. | 01-03-2017 | Raghunath Ji Mandir | Hydro testing inspection by AE UJS | Bhuwan Chandra Bhatt | Construction Supervisor | DSC WS ADB Tehri | See Pic |
5. | 28-02-2017 | Raghunath Ji Mandir Devprayag. | 100 mm dia sectional hydro testing is under observation | Bhuwan Chandra Bhatt | Construction Supervisor | DSC WS ADB Tehri | See Pic |
6. | 26-02-2017 | Bhagirathi Bridge | Sectional Hydro testing of 150mm dia pipe | Bhuwan Chandra Bhatt | Construction Supervisor | DSC WS ADB Tehri | See Pic |
7. | 18-02-2017 | Ramkund Bridge | Pipe line Anchoring with Clamp | Bhuwan Chandra Bhatt | Construction Supervisor | DSC WS ADB Tehri | See Pic |
8. | 17-02-2017 | Ramkund Bridge. | Pipe line Anchoring with Clamping | Bhuwan Chandra Bhatt | Construction Supervisor | DSC WS ADB Tehri | See Pic |
9. | 30-01-2017 | | Protection work for 50 KL GLSR | Deepak Mehra | Contractor Site Engineer | UEAP-WS Uttarkashi | See Pic |
10. | 25-01-2017 | Office building | Lighting works for Republic day celebration | Ashok Negi | DPM | PIU WS | See Pic |
11. | 24-01-2017 | 50 KL GLSR | Protection wall R R 1:6 | Bhuwan Chandra Bhatt | Construction Supervisor | DSC WS ADB Tehri | See Pic |
12. | 22-01-2017 | 50kL GLSR | R R 1:6 protection wall | Bhuwan Chandra Bhatt | Construction Supervisor | DSC WS ADB Tehri | See Pic |
13. | 20-01-2017 | Office Building Devprayag | Package information Board | Bhuwan Chandra Bhatt | Construction Supervisor | DSC WS ADB Tehri | See Pic |
14. | 12-01-2017 | Office Building | Inauguration of Devprayag package | Bhuwan Chandra Bhatt | Construction Supervisor | DSC WS ADB Tehri | See Pic |
15. | 05-01-2017 | Inauguration of Devprayag Package by Peyjal minister. | Devprayag project Lokarpan. | Bhuwan Chandra Bhatt | Construction Supervisor | DSC WS ADB Tehri | See Pic |
16. | 05-01-2017 | Near Post Office Bah Bazar | 150mm dia pipe laying & jointing | Bhuwan Chandra Bhatt | Construction Supervisor | DSC WS ADB Tehri | See Pic |
17. | 05-01-2017 | Devprayag Peyjal Yojna Ka Lokarpan | Paper news | Bhuwan Chandra Bhatt | Construction Supervisor | DSC WS ADB Tehri | See Pic |
18. | 21-12-2016 | Inauguration of Devprayag Water Supply Project by Peyjal Minister of Uttarakhand. | UEAP ADB funded Project Devprayag. | Bhuwan Chandra Bhatt | Construction Supervisor | DSC WS ADB Tehri | See Pic |
19. | 21-12-2016 | Office Building Devprayag | Inauguration of Devprayag water supply project by peyjal minister of Uttarakhand. | Bhuwan Chandra Bhatt | Construction Supervisor | DSC WS ADB Tehri | See Pic |
20. | 21-12-2016 | Office Building Devprayag | Public Gathering for Inauguration of Devprayag Package. | Bhuwan Chandra Bhatt | Construction Supervisor | DSC WS ADB Tehri | See Pic |
|
|