UK/UEAP-WSS/UJS/GW/01/lot4
Agreement signed
|
Project: |
UEAP-WS |
Package No.: |
2107 |
Package Name: |
UK/UEAP-WSS/UJS/GW/01/lot4 |
Sanction Cost: |
480.00 lakhs |
District: |
Tehri |
Block: |
Bhatwari |
Constituency: |
Gangotri |
Circle: |
|
DEA: |
DEA WS Rudraprayag |
DSC: |
|
DSC Scope: |
Design & Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 7107 Uttarkashi-Water-Supply-Scheme ( KM.) (completed) |
|
Procurement: |
Package No.: 2107
Package Name: UK/UEAP-WSS/UJS/GW/01/lot4
Tender Date: 10-11-2014
Current Status: Agreement signed
Achieved on Date: 15-01-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UK/UEAP-WSS/UJS/GW/01/lot4
Contractor Name: RK Engineers Sales Ltd
|
Start Date: 19-01-2015
Intended Completion Date: 30-09-2017
Original End Date: 18-07-2016
|
Total Bond Cost: 63357051.75 (633.57 lakhs)
|
LD Analysis for Milestone1: calculated LD is Rs 3611406 for 114 days
LD Analysis for Milestone2: calculated LD is Rs 12228094 for 386 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Infiltration Well/Tube Well | 2.00 No | 112.75 | 2.00 No | 2.00 No | 17.8 | 112.75 | 2. | Rehabilitation of WTP/HFRF | 3.00 No | 84.14 | 3.00 No | 3.00 No | 13.28 | 84.14 | 3. | Pipe Line Works with (Main/ Distribution) | 7680.00 m | 301.93 | 7680.00 m | 7680.00 m | 47.66 | 301.93 | 4. | Electrical and Instrumentation work | 1.00 No | 106.35 | 1.00 No | 1.00 No | 16.79 | 106.35 | 5. | Env. Man & Moni Plan | 1.00 Job | 5.54 | 1.00 Job | 1.00 Job | 0.87 | 5.54 | 6. | Provisional Sum | 1.00 Job | 22.85 | 1.00 Job | 1.00 Job | 3.61 | 22.85 |
Total Amount: |
633.56 |
|
100 |
633.56 |
|
Remarks:
No Remarks
Work Program Made On:
30-03-2015
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 28-September-2015 | 73.08 lakhs |
2. | 30-October-2015 | 47.89 lakhs |
3. | 18-December-2015 | 23.01 lakhs |
4. | 22-March-2016 | 75.04 lakhs |
5. | 17-June-2016 | 16.85 lakhs |
6. | 24-October-2016 | 54.97 lakhs |
7. | 07-January-2017 | 19.00 lakhs |
8. | 14-March-2017 | 14.71 lakhs |
9. | 21-June-2017 | 42.71 lakhs |
10. | 24-August-2017 | 27.18 lakhs |
Total |
394.44 lakhs |
% Payment |
62.26 % |
|
Advance Amount: 0.00 lakhs
Recovered Amount: 0.00 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
Analysis:Bill should be issued |
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 242 |
Number of Notice(s) issued: 120 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 06-07-2017 | Back side of Gufiyara wtp | Excavation and disposal work is in progress | Monendra Singh Rana | Construction supervisor | DSC WS ADB Tehri | See Pic |
2. | 04-07-2017 | Back side of WTP gufiyara | Excavation and disposal work is in progress | Monendra Singh Rana | Construction supervisor | DSC WS ADB Tehri | See Pic |
3. | 03-07-2017 | Back side of Gufiyara WTP | Excavation & Disposal of earth is in progress | Monendra Singh Rana | Construction supervisor | DSC WS ADB Tehri | See Pic |
4. | 02-07-2017 | Back side of Gufiyara WTP | Excavation and disposal work is in progress | Monendra Singh Rana | Construction supervisor | DSC WS ADB Tehri | See Pic |
5. | 01-07-2017 | Back side of Gufiyara WTP | Excavation and disposal work is in progress | Monendra Singh Rana | Construction supervisor | DSC WS ADB Tehri | See Pic |
6. | 29-06-2017 | Back side of Gufiyara WTP | Excavation and disposal of surplus earth | Monendra Singh Rana | Construction supervisor | DSC WS ADB Tehri | See Pic |
7. | 29-06-2017 | Back side of Gufiyara WTP | Excavation and disposal of surplus earth work is in progress | Monendra Singh Rana | Construction supervisor | DSC WS ADB Tehri | See Pic |
8. | 29-06-2017 | Back side Gufiyara WTP | Excavation and disposal of surplus earth work for retaining wall is in progress | Monendra Singh Rana | Construction supervisor | DSC WS ADB Tehri | See Pic |
9. | 19-06-2017 | Back side of Gufiyara WTP | Disposal of surplus earth | Monendra Singh Rana | Construction supervisor | DSC WS ADB Tehri | See Pic |
10. | 17-06-2017 | Back side of Gufiyara WTP | Casting of 6th lift of retaining wall | Monendra Singh Rana | Construction supervisor | DSC WS ADB Tehri | See Pic |
11. | 16-06-2017 | Back side of Gufiyara WTP | Shuttering of 6th lift of retaining wall | Monendra Singh Rana | Construction supervisor | DSC WS ADB Tehri | See Pic |
12. | 15-06-2017 | Back side of Gufiyara WTP | Reinforcement of 6th lift of retaining wall | Monendra Singh Rana | Construction supervisor | DSC WS ADB Tehri | See Pic |
13. | 15-06-2017 | Back side of Gufiyara WTP | Casting of 5th lift of retaining wall | Monendra Singh Rana | Construction supervisor | DSC WS ADB Tehri | See Pic |
14. | 09-06-2017 | Back side of Gufiyara WTP | Casting of 3rd lift of retaining wall in 11 MTR length | Monendra Singh Rana | Construction supervisor | DSC WS ADB Tehri | See Pic |
15. | 09-06-2017 | Back side of Gufiyara WTP | Casting of 3rd lift of retaining wall | Monendra Singh Rana | Construction supervisor | DSC WS ADB Tehri | See Pic |
16. | 08-06-2017 | Back side of Gufiyara WTP | Shuttering of 3rd lift of retaining wall | Monendra Singh Rana | Construction supervisor | DSC WS ADB Tehri | See Pic |
17. | 05-06-2017 | Back side of Gufiyara WTP | Casting of 2nd lift of retaining wall | Monendra Singh Rana | Construction supervisor | DSC WS ADB Tehri | See Pic |
18. | 05-06-2017 | Back side of Gufiyara WTP | Casting of 2nd lift of retaining wall | Monendra Singh Rana | Construction supervisor | DSC WS ADB Tehri | See Pic |
19. | 03-06-2017 | Back side of Gufiyara WTP | Shuttering of the 2nd lift of retaining wall is in progress | Monendra Singh Rana | Construction supervisor | DSC WS ADB Tehri | See Pic |
20. | 02-06-2017 | Back side of Gufiyara WTP | Reinforcement of 2nd lift | Monendra Singh Rana | Construction supervisor | DSC WS ADB Tehri | See Pic |
|
|