Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UK/UEAP-WSS/UJS/GW/01/lot4 Agreement signed
Project: UEAP-WS Package No.: 2107 Package Name: UK/UEAP-WSS/UJS/GW/01/lot4 Sanction Cost: 480.00  lakhs
District: Tehri Block: Bhatwari Constituency: Gangotri Circle:
DEA: DEA WS Rudraprayag DSC: DSC Scope: Design & Supervision No.of Sub project : 1
Subproject in this package
1  7107   Uttarkashi-Water-Supply-Scheme ( KM.) (completed)
Procurement:
Package No.: 2107        Package Name: UK/UEAP-WSS/UJS/GW/01/lot4        Tender Date: 10-11-2014        Current Status: Agreement signed        Achieved on Date: 15-01-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UK/UEAP-WSS/UJS/GW/01/lot4        Contractor Name: RK Engineers Sales Ltd       
Start Date: 19-01-2015        Intended Completion Date: 30-09-2017        Original End Date:  18-07-2016
Total Bond Cost: 63357051.75 (633.57 lakhs)       
LD Analysis for Milestone1: calculated LD is Rs 3611406 for 114 days        LD Analysis for Milestone2: calculated LD is Rs 12228094 for 386 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Infiltration Well/Tube Well2.00 No112.752.00 No2.00 No17.8112.75
2.Rehabilitation of WTP/HFRF 3.00 No84.143.00 No3.00 No13.2884.14
3.Pipe Line Works with (Main/ Distribution)7680.00 m301.937680.00 m7680.00 m47.66301.93
4.Electrical and Instrumentation work1.00 No106.351.00 No1.00 No16.79106.35
5.Env. Man & Moni Plan1.00 Job5.541.00 Job1.00 Job0.875.54
6.Provisional Sum1.00 Job22.851.00 Job1.00 Job3.6122.85
Total Amount: 633.56 100   633.56
Remarks: No Remarks       Work Program Made On: 30-03-2015      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.28-September-201573.08  lakhs
2.30-October-201547.89  lakhs
3.18-December-201523.01  lakhs
4.22-March-201675.04  lakhs
5.17-June-201616.85  lakhs
6.24-October-201654.97  lakhs
7.07-January-201719.00  lakhs
8.14-March-201714.71  lakhs
9.21-June-201742.71  lakhs
10.24-August-201727.18  lakhs
Total 394.44  lakhs
% Payment 62.26 %
Advance Amount:  0.00  lakhs        Recovered Amount:  0.00  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Analysis:Bill should be issued
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 1     No. of Test Done : 1      No. of Test Passed : 1      No. of Test Failed : 0   Test report of this package
Number of Pics Available on Web Repository: 242
Number of Notice(s) issued: 120

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.06-07-2017Back side of Gufiyara wtpExcavation and disposal work is in progressMonendra Singh RanaConstruction supervisorDSC WS ADB Tehri See Pic
2.04-07-2017Back side of WTP gufiyaraExcavation and disposal work is in progressMonendra Singh RanaConstruction supervisorDSC WS ADB Tehri See Pic
3.03-07-2017Back side of Gufiyara WTPExcavation & Disposal of earth is in progressMonendra Singh RanaConstruction supervisorDSC WS ADB Tehri See Pic
4.02-07-2017Back side of Gufiyara WTPExcavation and disposal work is in progressMonendra Singh RanaConstruction supervisorDSC WS ADB Tehri See Pic
5.01-07-2017Back side of Gufiyara WTPExcavation and disposal work is in progressMonendra Singh RanaConstruction supervisorDSC WS ADB Tehri See Pic
6.29-06-2017Back side of Gufiyara WTPExcavation and disposal of surplus earthMonendra Singh RanaConstruction supervisorDSC WS ADB Tehri See Pic
7.29-06-2017Back side of Gufiyara WTPExcavation and disposal of surplus earth work is in progressMonendra Singh RanaConstruction supervisorDSC WS ADB Tehri See Pic
8.29-06-2017Back side Gufiyara WTPExcavation and disposal of surplus earth work for retaining wall is in progressMonendra Singh RanaConstruction supervisorDSC WS ADB Tehri See Pic
9.19-06-2017Back side of Gufiyara WTPDisposal of surplus earthMonendra Singh RanaConstruction supervisorDSC WS ADB Tehri See Pic
10.17-06-2017Back side of Gufiyara WTPCasting of 6th lift of retaining wallMonendra Singh RanaConstruction supervisorDSC WS ADB Tehri See Pic
11.16-06-2017Back side of Gufiyara WTPShuttering of 6th lift of retaining wallMonendra Singh RanaConstruction supervisorDSC WS ADB Tehri See Pic
12.15-06-2017Back side of Gufiyara WTPReinforcement of 6th lift of retaining wallMonendra Singh RanaConstruction supervisorDSC WS ADB Tehri See Pic
13.15-06-2017Back side of Gufiyara WTPCasting of 5th lift of retaining wallMonendra Singh RanaConstruction supervisorDSC WS ADB Tehri See Pic
14.09-06-2017Back side of Gufiyara WTPCasting of 3rd lift of retaining wall in 11 MTR lengthMonendra Singh RanaConstruction supervisorDSC WS ADB Tehri See Pic
15.09-06-2017Back side of Gufiyara WTPCasting of 3rd lift of retaining wallMonendra Singh RanaConstruction supervisorDSC WS ADB Tehri See Pic
16.08-06-2017Back side of Gufiyara WTPShuttering of 3rd lift of retaining wallMonendra Singh RanaConstruction supervisorDSC WS ADB Tehri See Pic
17.05-06-2017Back side of Gufiyara WTPCasting of 2nd lift of retaining wallMonendra Singh RanaConstruction supervisorDSC WS ADB Tehri See Pic
18.05-06-2017Back side of Gufiyara WTPCasting of 2nd lift of retaining wallMonendra Singh RanaConstruction supervisorDSC WS ADB Tehri See Pic
19.03-06-2017Back side of Gufiyara WTPShuttering of the 2nd lift of retaining wall is in progressMonendra Singh RanaConstruction supervisorDSC WS ADB Tehri See Pic
20.02-06-2017Back side of Gufiyara WTPReinforcement of 2nd liftMonendra Singh RanaConstruction supervisorDSC WS ADB Tehri See Pic