UK/UEAP-WSS/UJS/GW/01/lot3
Agreement signed
|
Project: |
UEAP-WS |
Package No.: |
2106 |
Package Name: |
UK/UEAP-WSS/UJS/GW/01/lot3 |
Sanction Cost: |
519.00 lakhs |
District: |
Chamoli |
Block: |
Karnaprayag |
Constituency: |
Karanprayag |
Circle: |
|
DEA: |
DEA WS Rudraprayag |
DSC: |
|
DSC Scope: |
Design & Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 7106 Gauchar-Water-Supply-Scheme ( KM.) (completed) |
|
Procurement: |
Package No.: 2106
Package Name: UK/UEAP-WSS/UJS/GW/01/lot3
Tender Date: 20-09-2014
Current Status: Agreement signed
Achieved on Date: 24-11-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UK/UEAP-WSS/UJS/GW/01/lot3
Contractor Name: RK Engineers Sales Ltd
|
Start Date: 19-01-2015
Intended Completion Date: 31-05-2017
Original End Date: 18-07-2016
|
Total Bond Cost: 64753076 (647.53 lakhs)
|
LD Analysis for Milestone1: calculated LD is Rs 5504090 for 170 days
LD Analysis for Milestone2: calculated LD is Rs 10522525 for 325 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Infiltration Well/Tube Well | 1.00 No | 113.40 | 1.00 No | 1.00 No | 17.51 | 113.40 | 2. | GLSRs | 1.00 No | 18.00 | 1.00 No | 1.00 No | 2.78 | 18.00 | 3. | Pipe Line Works with (Main/ Distribution) | 11150.00 m | 188.61 | 11150.00 m | 11150.00 m | 29.13 | 188.61 | 4. | Electrical and Instrumentation work | 1.00 No | 138.75 | 1.00 No | 1.00 No | 21.43 | 138.75 | 5. | Office Building | 1.00 No | 158.06 | 1.00 No | 1.00 No | 24.41 | 158.06 | 6. | Env. Man & Moni Plan | 1.00 Job | 6.01 | 1.00 Job | 1.00 Job | 0.93 | 6.01 | 7. | Provisional Sum | 1.00 Job | 24.70 | 1.00 Job | 1.00 Job | 3.81 | 24.70 |
Total Amount: |
647.53 |
|
100 |
647.53 |
|
Remarks:
No Remarks
Work Program Made On:
30-03-2015
Updation of work program on:
31-03-2015
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 28-September-2015 | 15.92 lakhs |
2. | 30-October-2015 | 70.23 lakhs |
3. | 18-December-2015 | 20.32 lakhs |
4. | 11-March-2016 | 101.22 lakhs |
5. | 22-March-2016 | 22.83 lakhs |
6. | 19-September-2016 | 36.72 lakhs |
7. | 26-October-2016 | 11.88 lakhs |
8. | 07-January-2017 | 75.01 lakhs |
9. | 14-March-2017 | 52.04 lakhs |
10. | 29-April-2017 | 30.85 lakhs |
Total |
437.02 lakhs |
% Payment |
67.49 % |
|
Advance Amount: 84.55 lakhs
Recovered Amount: 84.55 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
Analysis:Bill should be issued |
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 59 |
Number of Notice(s) issued: 138 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 19-05-2017 | Pumphouse Gaucher | Pumphouse Gaucher | Bharat Singh Bisht | Quantity Surveyor | DSC WS ADB Pithoragarh | See Pic |
2. | 19-05-2017 | I Well Gaucher | I Well Gaucher | Bharat Singh Bisht | Quantity Surveyor | DSC WS ADB Pithoragarh | See Pic |
3. | 29-03-2017 | Pumphouse and sump | Finishing works | Ashok Negi | DPM | PIU WS | See Pic |
4. | 29-03-2017 | Sump | Sump | Ashok Negi | DPM | PIU WS | See Pic |
5. | 29-03-2017 | Pumphouse | Pumphouse | Ashok Negi | DPM | PIU WS | See Pic |
6. | 29-03-2017 | Pumphouse | Running | Ashok Negi | DPM | PIU WS | See Pic |
7. | 29-03-2017 | Pumphouse | Finishing | Ashok Negi | DPM | PIU WS | See Pic |
8. | 23-03-2017 | 150kl GLSR Karanparyag. | Finishing work is going on progress. | Bharat Singh Bisht | Quantity Surveyor | DSC WS ADB Pithoragarh | See Pic |
9. | 23-03-2017 | 150KL GLSR KARANPARYAG | Finishing work is going on progress. | Bharat Singh Bisht | Quantity Surveyor | DSC WS ADB Pithoragarh | See Pic |
10. | 18-03-2017 | I well kaleswer | Civil work is complete | Bharat Singh Bisht | Quantity Surveyor | DSC WS ADB Pithoragarh | See Pic |
11. | 18-03-2017 | Pump house kaleshwer | Civil work is complete | Bharat Singh Bisht | Quantity Surveyor | DSC WS ADB Pithoragarh | See Pic |
12. | 17-03-2017 | I well gauchar | I well gauchar | Bharat Singh Bisht | Quantity Surveyor | DSC WS ADB Pithoragarh | See Pic |
13. | 17-03-2017 | Pumphouse gauchar | Pump house gauchar | Bharat Singh Bisht | Quantity Surveyor | DSC WS ADB Pithoragarh | See Pic |
14. | 05-03-2017 | Pump house area Gauchar | Construction work complete... | Goutam Sengupta | Construction Supervisor | DSC WS ADB Chamoli | See Pic |
15. | 05-03-2017 | In between I well and pump house.... | Finishing work in progress.... | Goutam Sengupta | Construction Supervisor | DSC WS ADB Chamoli | See Pic |
16. | 05-02-2017 | Pump house Gauchar | Clorinator fixing complete... | Goutam Sengupta | Construction Supervisor | DSC WS ADB Chamoli | See Pic |
17. | 31-01-2017 | Near Arto karanprayag | Installtion of electronic trivector meter at karanprayag By Upcl | vipin chauhan | unknown | unknown | See Pic |
18. | 25-01-2017 | Pumphouse | Landscaping | Ashok Negi | DPM | PIU WS | See Pic |
19. | 25-01-2017 | Gauchar I well | site visit PMU official in progress | Rakesh Sharma | Contractor Project Manager | UEAP-WS Pauri | See Pic |
20. | 23-01-2017 | Pumphouse at gauchar | Lighting works | Ashok Negi | DPM | PIU WS | See Pic |
|
|