UK/UEAP-WSS/UJS/GW/01/lot3 Agreement signed
Project: UEAP-WS Package No.: 2106 Package Name: UK/UEAP-WSS/UJS/GW/01/lot3 Sanction Cost: 519.00  lakhs
District: Chamoli Block: Karnaprayag Constituency: Karanprayag Circle:
DEA: DEA WS Rudraprayag DSC: DSC Scope: Design & Supervision No.of Sub project : 1
Subproject in this package
1  7106   Gauchar-Water-Supply-Scheme ( KM.) (completed)
Procurement:
Package No.: 2106        Package Name: UK/UEAP-WSS/UJS/GW/01/lot3        Tender Date: 20-09-2014        Current Status: Agreement signed        Achieved on Date: 24-11-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UK/UEAP-WSS/UJS/GW/01/lot3        Contractor Name: RK Engineers Sales Ltd       
Start Date: 19-01-2015        Intended Completion Date: 31-05-2017        Original End Date:  18-07-2016
Total Bond Cost: 64753076 (647.53 lakhs)       
LD Analysis for Milestone1: calculated LD is Rs 5504090 for 170 days        LD Analysis for Milestone2: calculated LD is Rs 10522525 for 325 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Infiltration Well/Tube Well1.00 No113.401.00 No1.00 No17.51113.40
2.GLSRs1.00 No18.001.00 No1.00 No2.7818.00
3.Pipe Line Works with (Main/ Distribution)11150.00 m188.6111150.00 m11150.00 m29.13188.61
4.Electrical and Instrumentation work1.00 No138.751.00 No1.00 No21.43138.75
5.Office Building1.00 No158.061.00 No1.00 No24.41158.06
6.Env. Man & Moni Plan1.00 Job6.011.00 Job1.00 Job0.936.01
7.Provisional Sum1.00 Job24.701.00 Job1.00 Job3.8124.70
Total Amount: 647.53 100   647.53
Remarks: No Remarks       Work Program Made On: 30-03-2015       Updation of work program on: 31-03-2015      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.28-September-201515.92  lakhs
2.30-October-201570.23  lakhs
3.18-December-201520.32  lakhs
4.11-March-2016101.22  lakhs
5.22-March-201622.83  lakhs
6.19-September-201636.72  lakhs
7.26-October-201611.88  lakhs
8.07-January-201775.01  lakhs
9.14-March-201752.04  lakhs
10.29-April-201730.85  lakhs
Total 437.02  lakhs
% Payment 67.49 %
Advance Amount:  84.55  lakhs        Recovered Amount:  84.55  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Analysis:Bill should be issued
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 95     No. of Test Done : 96      No. of Test Passed : 96      No. of Test Failed : 0   Test report of this package
Number of Pics Available on Web Repository: 59
Number of Notice(s) issued: 138

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.19-05-2017Pumphouse GaucherPumphouse GaucherBharat Singh BishtQuantity SurveyorDSC WS ADB Pithoragarh See Pic
2.19-05-2017I Well GaucherI Well GaucherBharat Singh BishtQuantity SurveyorDSC WS ADB Pithoragarh See Pic
3.29-03-2017Pumphouse and sumpFinishing worksAshok NegiDPMPIU WS See Pic
4.29-03-2017SumpSumpAshok NegiDPMPIU WS See Pic
5.29-03-2017PumphousePumphouseAshok NegiDPMPIU WS See Pic
6.29-03-2017PumphouseRunningAshok NegiDPMPIU WS See Pic
7.29-03-2017PumphouseFinishingAshok NegiDPMPIU WS See Pic
8.23-03-2017150kl GLSR Karanparyag.Finishing work is going on progress.Bharat Singh BishtQuantity SurveyorDSC WS ADB Pithoragarh See Pic
9.23-03-2017150KL GLSR KARANPARYAGFinishing work is going on progress.Bharat Singh BishtQuantity SurveyorDSC WS ADB Pithoragarh See Pic
10.18-03-2017I well kaleswerCivil work is completeBharat Singh BishtQuantity SurveyorDSC WS ADB Pithoragarh See Pic
11.18-03-2017Pump house kaleshwerCivil work is completeBharat Singh BishtQuantity SurveyorDSC WS ADB Pithoragarh See Pic
12.17-03-2017I well gaucharI well gaucharBharat Singh BishtQuantity SurveyorDSC WS ADB Pithoragarh See Pic
13.17-03-2017Pumphouse gaucharPump house gaucharBharat Singh BishtQuantity SurveyorDSC WS ADB Pithoragarh See Pic
14.05-03-2017Pump house area GaucharConstruction work complete...Goutam SenguptaConstruction SupervisorDSC WS ADB Chamoli See Pic
15.05-03-2017In between I well and pump house....Finishing work in progress....Goutam SenguptaConstruction SupervisorDSC WS ADB Chamoli See Pic
16.05-02-2017Pump house GaucharClorinator fixing complete...Goutam SenguptaConstruction SupervisorDSC WS ADB Chamoli See Pic
17.31-01-2017Near Arto karanprayagInstalltion of electronic trivector meter at karanprayag By Upclvipin chauhanunknownunknown See Pic
18.25-01-2017PumphouseLandscapingAshok NegiDPMPIU WS See Pic
19.25-01-2017Gauchar I wellsite visit PMU official in progressRakesh SharmaContractor Project ManagerUEAP-WS Pauri See Pic
20.23-01-2017Pumphouse at gaucharLighting worksAshok NegiDPMPIU WS See Pic