UK/UEAP-WSS/UJS/KU/01/lot2
Agreement signed
|
Project: |
UEAP-WS |
Package No.: |
2102 |
Package Name: |
UK/UEAP-WSS/UJS/KU/01/lot2 |
Sanction Cost: |
339.00 lakhs |
District: |
Bageshwar |
Block: |
Bageshwar |
Constituency: |
Bageshwar |
Circle: |
|
DEA: |
DEA WS Kapkot |
DSC: |
|
DSC Scope: |
Design & Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 7102 Bageshwar-Water-Supply-Scheme ( KM.) (completed) |
|
Procurement: |
Package No.: 2102
Package Name: UK/UEAP-WSS/UJS/KU/01/lot2
Tender Date: 16-09-2014
Current Status: Agreement signed
Achieved on Date: 15-11-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UK/UEAP-WSS/UJS/KU/01/lot2
Contractor Name: Kashmirilal Constructions (P) Ltd.
|
Start Date: 01-12-2014
Intended Completion Date: 30-06-2017
Original End Date: 31-05-2016
|
Total Bond Cost: 38330950 (383.31 lakhs)
|
LD Analysis for Milestone1: calculated LD is Rs 4676260 for 244 days
LD Analysis for Milestone2: calculated LD is Rs 4484610 for 234 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Infiltration Well/Tube Well | 1.00 No | 130.00 | 1.00 No | 1.00 No | 33.72 | 130.00 | 2. | Rehabilitation of WTP/HFRF | 1.00 No | 12.00 | 1.00 No | 1.00 No | 3.11 | 12.00 | 3. | Demolition of old structures | 1.00 No | 0.36 | 1.00 No | 1.00 No | 0.09 | 0.36 | 4. | Pipe Line Works with (Main/ Distribution) | 500.00 m | 17.24 | 500.00 m | 500.00 m | 4.47 | 17.24 | 5. | Electrical and Instrumentation work | 3.00 No | 93.68 | 3.00 No | 3.00 No | 24.3 | 93.68 | 6. | Mechanical Work | 4.00 No | 111.74 | 4.00 No | 4.00 No | 28.98 | 111.74 | 7. | Env. Man & Moni Plan | 1.00 Job | 5.57 | 1.00 Job | 1.00 Job | 1.45 | 5.57 | 8. | Provisional Sum | 1.00 Job | 15.00 | 1.00 Job | 1.00 Job | 3.89 | 15.00 |
Total Amount: |
385.59 |
|
100 |
385.59 |
|
Remarks:
No Remarks
Work Program Made On:
30-03-2015
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 18-November-2015 | 27.52 lakhs |
2. | 19-March-2016 | 81.08 lakhs |
3. | 18-June-2016 | 54.84 lakhs |
4. | 17-August-2016 | 49.63 lakhs |
5. | 25-October-2016 | 38.22 lakhs |
6. | 07-January-2017 | 32.96 lakhs |
7. | 03-March-2017 | 49.85 lakhs |
8. | 21-June-2017 | 42.93 lakhs |
9. | 24-August-2017 | 25.04 lakhs |
Total |
402.07 lakhs |
% Payment |
104.89 % |
|
Advance Amount: 43.07 lakhs
Recovered Amount: 43.07 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
Test Information not Available. |
Number of Pics Available on Web Repository: 48 |
Number of Notice(s) issued: 127 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 30-04-2017 | Bageshwar I well | Cable alignment properly done at Bageshwar I well. | Rajesh Upadhyay | Project Manager | UEAP-WS Bageshwar | See Pic |
2. | 18-04-2017 | Bageshwar I well | I well painting work Completed. | Rajesh Upadhyay | Project Manager | UEAP-WS Bageshwar | See Pic |
3. | 08-03-2017 | Bageshwar I well | Channel fixing work at I well walkway bridge | Rajesh Upadhyay | Project Manager | UEAP-WS Bageshwar | See Pic |
4. | 23-01-2017 | Bageshwar I well | AE UJS visited at I Well site for inspection of work progress. | Rajesh Upadhyay | Project Manager | UEAP-WS Bageshwar | See Pic |
5. | 21-01-2017 | Dehradun PIU Office | EMP Training | Bikash Kumar Das | Constuction Supervisor | DSC WS ADB Bageshwar | See Pic |
6. | 14-01-2017 | Bageshwar I well | GM Sir, EE Sir, JE UJS, CS DSC visited at Bageshwar I Well site. | Rajesh Upadhyay | Project Manager | UEAP-WS Bageshwar | See Pic |
7. | 13-01-2017 | Bageshwar I well | Submersibal pump installation work going on progress inside I well. | Rajesh Upadhyay | Project Manager | UEAP-WS Bageshwar | See Pic |
8. | 12-01-2017 | Bageshwar I well | I well Submersibal pump reached at site and installation work going on progress. | Rajesh Upadhyay | Project Manager | UEAP-WS Bageshwar | See Pic |
9. | 23-12-2016 | Bageshwar WSS | Environment Consultation at Bageshwar by Dr. Nutan Gupta(Envir. Sp.PMU) | Rajesh Upadhyay | Project Manager | UEAP-WS Bageshwar | See Pic |
10. | 23-12-2016 | Bageshwar I well | Pump is running at Bageshwar I well. | Rajesh Upadhyay | Project Manager | UEAP-WS Bageshwar | See Pic |
11. | 18-12-2016 | Thakurdwara at Bageshwar | Alum godown at finishing stage | Rajesh Upadhyay | Project Manager | UEAP-WS Bageshwar | See Pic |
12. | 15-12-2016 | Bageshwar I well | Flooring work going on progress at I well | Rajesh Upadhyay | Project Manager | UEAP-WS Bageshwar | See Pic |
13. | 15-12-2016 | Bageshwar I well | Skirting work going on progress inside I well. | Rajesh Upadhyay | Project Manager | UEAP-WS Bageshwar | See Pic |
14. | 07-12-2016 | Bageshwar I well | Level sensor fitting work going on progress at I well. | Rajesh Upadhyay | Project Manager | UEAP-WS Bageshwar | See Pic |
15. | 05-12-2016 | Bageshwar I well | Earthing work at Pump House Going on progress. | Rajesh Upadhyay | Project Manager | UEAP-WS Bageshwar | See Pic |
16. | 26-11-2016 | Alum Godown(WTP at Thakurdwara, Bageshwar) | Final and finishing stage | Rajesh Upadhyay | Project Manager | UEAP-WS Bageshwar | See Pic |
17. | 26-11-2016 | Bageshwar I well | Finishing stage | Rajesh Upadhyay | Project Manager | UEAP-WS Bageshwar | See Pic |
18. | 02-11-2016 | Bageshwar I well | Trail run commissioning going on progress from the date of 01/11/16. | Rajesh Upadhyay | Project Manager | UEAP-WS Bageshwar | See Pic |
19. | 26-10-2016 | Bageshwar I well Pump house | Submersibal Pump installation work going on progress. | Rajesh Upadhyay | Project Manager | UEAP-WS Bageshwar | See Pic |
20. | 18-10-2016 | I well bageshwar | Cleaning | Ashok Negi | DPM | PIU WS | See Pic |
|
|