Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UK/UEAP-WSS/UJS/KU/01/lot2 Agreement signed
Project: UEAP-WS Package No.: 2102 Package Name: UK/UEAP-WSS/UJS/KU/01/lot2 Sanction Cost: 339.00  lakhs
District: Bageshwar Block: Bageshwar Constituency: Bageshwar Circle:
DEA: DEA WS Kapkot DSC: DSC Scope: Design & Supervision No.of Sub project : 1
Subproject in this package
1  7102   Bageshwar-Water-Supply-Scheme ( KM.) (completed)
Procurement:
Package No.: 2102        Package Name: UK/UEAP-WSS/UJS/KU/01/lot2        Tender Date: 16-09-2014        Current Status: Agreement signed        Achieved on Date: 15-11-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UK/UEAP-WSS/UJS/KU/01/lot2        Contractor Name: Kashmirilal Constructions (P) Ltd.       
Start Date: 01-12-2014        Intended Completion Date: 30-06-2017        Original End Date:  31-05-2016
Total Bond Cost: 38330950 (383.31 lakhs)       
LD Analysis for Milestone1: calculated LD is Rs 4676260 for 244 days        LD Analysis for Milestone2: calculated LD is Rs 4484610 for 234 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Infiltration Well/Tube Well1.00 No130.001.00 No1.00 No33.72130.00
2.Rehabilitation of WTP/HFRF 1.00 No12.001.00 No1.00 No3.1112.00
3.Demolition of old structures1.00 No0.361.00 No1.00 No0.090.36
4.Pipe Line Works with (Main/ Distribution)500.00 m17.24500.00 m500.00 m4.4717.24
5.Electrical and Instrumentation work3.00 No93.683.00 No3.00 No24.393.68
6.Mechanical Work4.00 No111.744.00 No4.00 No28.98111.74
7.Env. Man & Moni Plan1.00 Job5.571.00 Job1.00 Job1.455.57
8.Provisional Sum1.00 Job15.001.00 Job1.00 Job3.8915.00
Total Amount: 385.59 100   385.59
Remarks: No Remarks       Work Program Made On: 30-03-2015      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.18-November-201527.52  lakhs
2.19-March-201681.08  lakhs
3.18-June-201654.84  lakhs
4.17-August-201649.63  lakhs
5.25-October-201638.22  lakhs
6.07-January-201732.96  lakhs
7.03-March-201749.85  lakhs
8.21-June-201742.93  lakhs
9.24-August-201725.04  lakhs
Total 402.07  lakhs
% Payment 104.89 %
Advance Amount:  43.07  lakhs        Recovered Amount:  43.07  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
Test Information not Available.
Number of Pics Available on Web Repository: 48
Number of Notice(s) issued: 127

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.30-04-2017Bageshwar I wellCable alignment properly done at Bageshwar I well.Rajesh UpadhyayProject ManagerUEAP-WS Bageshwar See Pic
2.18-04-2017Bageshwar I wellI well painting work Completed.Rajesh UpadhyayProject ManagerUEAP-WS Bageshwar See Pic
3.08-03-2017Bageshwar I wellChannel fixing work at I well walkway bridgeRajesh UpadhyayProject ManagerUEAP-WS Bageshwar See Pic
4.23-01-2017Bageshwar I wellAE UJS visited at I Well site for inspection of work progress.Rajesh UpadhyayProject ManagerUEAP-WS Bageshwar See Pic
5.21-01-2017Dehradun PIU OfficeEMP TrainingBikash Kumar DasConstuction SupervisorDSC WS ADB Bageshwar See Pic
6.14-01-2017Bageshwar I wellGM Sir, EE Sir, JE UJS, CS DSC visited at Bageshwar I Well site.Rajesh UpadhyayProject ManagerUEAP-WS Bageshwar See Pic
7.13-01-2017Bageshwar I wellSubmersibal pump installation work going on progress inside I well.Rajesh UpadhyayProject ManagerUEAP-WS Bageshwar See Pic
8.12-01-2017Bageshwar I wellI well Submersibal pump reached at site and installation work going on progress.Rajesh UpadhyayProject ManagerUEAP-WS Bageshwar See Pic
9.23-12-2016Bageshwar WSSEnvironment Consultation at Bageshwar by Dr. Nutan Gupta(Envir. Sp.PMU)Rajesh UpadhyayProject ManagerUEAP-WS Bageshwar See Pic
10.23-12-2016Bageshwar I wellPump is running at Bageshwar I well.Rajesh UpadhyayProject ManagerUEAP-WS Bageshwar See Pic
11.18-12-2016Thakurdwara at BageshwarAlum godown at finishing stageRajesh UpadhyayProject ManagerUEAP-WS Bageshwar See Pic
12.15-12-2016Bageshwar I wellFlooring work going on progress at I wellRajesh UpadhyayProject ManagerUEAP-WS Bageshwar See Pic
13.15-12-2016Bageshwar I wellSkirting work going on progress inside I well.Rajesh UpadhyayProject ManagerUEAP-WS Bageshwar See Pic
14.07-12-2016Bageshwar I wellLevel sensor fitting work going on progress at I well.Rajesh UpadhyayProject ManagerUEAP-WS Bageshwar See Pic
15.05-12-2016Bageshwar I wellEarthing work at Pump House Going on progress.Rajesh UpadhyayProject ManagerUEAP-WS Bageshwar See Pic
16.26-11-2016Alum Godown(WTP at Thakurdwara, Bageshwar)Final and finishing stageRajesh UpadhyayProject ManagerUEAP-WS Bageshwar See Pic
17.26-11-2016Bageshwar I wellFinishing stageRajesh UpadhyayProject ManagerUEAP-WS Bageshwar See Pic
18.02-11-2016Bageshwar I wellTrail run commissioning going on progress from the date of 01/11/16.Rajesh UpadhyayProject ManagerUEAP-WS Bageshwar See Pic
19.26-10-2016Bageshwar I well Pump houseSubmersibal Pump installation work going on progress.Rajesh UpadhyayProject ManagerUEAP-WS Bageshwar See Pic
20.18-10-2016I well bageshwarCleaningAshok NegiDPMPIU WS See Pic