UK/UEAP-WSS/UJS/KU/01/lot1
Agreement signed
|
Project: |
UEAP-WS |
Package No.: |
2101 |
Package Name: |
UK/UEAP-WSS/UJS/KU/01/lot1 |
Sanction Cost: |
598.00 lakhs |
District: |
Bageshwar |
Block: |
Kapkot |
Constituency: |
Bageshwar |
Circle: |
|
DEA: |
DEA WS Kapkot |
DSC: |
|
DSC Scope: |
Design & Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 7101 Kapkot-Water-Supply-Scheme ( KM.) (completed) |
|
Procurement: |
Package No.: 2101
Package Name: UK/UEAP-WSS/UJS/KU/01/lot1
Tender Date: 16-09-2014
Current Status: Agreement signed
Achieved on Date: 15-11-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UK/UEAP-WSS/UJS/KU/01/lot1
Contractor Name: Kashmirilal Constructions (P) Ltd.
|
Start Date: 01-12-2014
Intended Completion Date: 28-02-2017
Original End Date: 31-05-2016
|
Total Bond Cost: 53380185 (533.8 lakhs)
Variation Cost: 1656042.84 (16.56 lakhs) Hence Total Bond Cost is 55036227.84 (550.36 lakhs)
|
LD Analysis for Milestone1: calculated LD is Rs 4163640 for 156 days
LD Analysis for Milestone2: calculated LD is Rs 3683220 for 138 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Infiltration Well/Tube Well | 1.00 No | 128.00 | 1.00 No | 1.00 No | 23.87 | 128.00 | 2. | Pipe Line Works with (Main/ Distribution) | 7641.00 m | 209.11 | 7711.00 m | 7711.00 m | 38.99 | 209.11 | 3. | Electrical and Instrumentation work | 1.00 No | 38.70 | 1.00 No | 1.00 No | 7.22 | 38.70 | 4. | Mechanical Work | 4.00 No | 128.35 | 4.00 No | 4.00 No | 23.93 | 128.35 | 5. | Env. Man & Moni Plan | 1.00 Job | 5.18 | 1.00 Job | 1.00 Job | 0.97 | 5.18 | 6. | Provisional Sum | 1.00 Job | 27.00 | 1.00 Job | 1.00 Job | 5.03 | 27.00 |
Total Amount: |
536.34 |
|
100 |
536.34 |
|
Remarks:
No Remarks
Work Program Made On:
30-03-2015
Updation of work program on:
08-06-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 20-October-2015 | 54.42 lakhs |
2. | 18-November-2015 | 100.85 lakhs |
3. | 22-March-2016 | 67.74 lakhs |
4. | 23-June-2016 | 156.55 lakhs |
5. | 17-August-2016 | 19.53 lakhs |
6. | 25-October-2016 | 40.92 lakhs |
7. | 03-March-2017 | 14.65 lakhs |
8. | 31-May-2017 | 52.01 lakhs |
Total |
506.67 lakhs |
% Payment |
92.06 % |
|
Advance Amount: 67.68 lakhs
Recovered Amount: 67.68 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
Test Information not Available. |
Number of Pics Available on Web Repository: 51 |
Number of Notice(s) issued: 118 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 20-07-2017 | Binsar Tank | Binsar Tank protection work going on progress. | Rajesh Upadhyay | Project Manager | UEAP-WS Bageshwar | See Pic |
2. | 20-07-2017 | Binsar 200KL Tank | Tank exavation work going on progress. | Rajesh Upadhyay | Project Manager | UEAP-WS Bageshwar | See Pic |
3. | 28-04-2017 | Kapkot I well | Inside view of Pump House | Rajesh Upadhyay | Project Manager | UEAP-WS Bageshwar | See Pic |
4. | 28-04-2017 | Kapkote I Well | Site view of I well | Rajesh Upadhyay | Project Manager | UEAP-WS Bageshwar | See Pic |
5. | 02-04-2017 | Kapkot I Well | All works are completed. | Rajesh Upadhyay | Project Manager | UEAP-WS Bageshwar | See Pic |
6. | 16-03-2017 | Kapkote I well | Chain link fencing work going on progress. | Rajesh Upadhyay | Project Manager | UEAP-WS Bageshwar | See Pic |
7. | 09-03-2017 | Kapkot I well | Chain link fencing work going on progress. | Rajesh Upadhyay | Project Manager | UEAP-WS Bageshwar | See Pic |
8. | 07-03-2017 | Kapkot I well | AE, JE(UJS) and CS DSC visited Kapkot I well. | Rajesh Upadhyay | Project Manager | UEAP-WS Bageshwar | See Pic |
9. | 04-03-2017 | Kapkot I well | Extra Item work inspection taken by FPIU and DSC | Rajesh Upadhyay | Project Manager | UEAP-WS Bageshwar | See Pic |
10. | 03-03-2017 | I. Well kapkot | Fencing work | Bikash Kumar Das | Constuction Supervisor | DSC WS ADB Bageshwar | See Pic |
11. | 03-03-2017 | I. Well, Kapkot | Gate fixing | Bikash Kumar Das | Constuction Supervisor | DSC WS ADB Bageshwar | See Pic |
12. | 03-03-2017 | Kapkot I well | Extra item works going on progress. | Rajesh Upadhyay | Project Manager | UEAP-WS Bageshwar | See Pic |
13. | 22-01-2017 | Kapkote I Well | Fire buckets fixed at I well. | Rajesh Upadhyay | Project Manager | UEAP-WS Bageshwar | See Pic |
14. | 13-01-2017 | Kapkot I-well | Information board fixed at Kapkot | Rajesh Upadhyay | Project Manager | UEAP-WS Bageshwar | See Pic |
15. | 12-01-2017 | Kapkot I well | I Well painting work completed. | Rajesh Upadhyay | Project Manager | UEAP-WS Bageshwar | See Pic |
16. | 31-12-2016 | Kapkote I well | Automation(SCADA) is working at Kapkote I well. | Rajesh Upadhyay | Project Manager | UEAP-WS Bageshwar | See Pic |
17. | 29-12-2016 | Kapkote I well | Final coat Painting work at Kapkote I well | Rajesh Upadhyay | Project Manager | UEAP-WS Bageshwar | See Pic |
18. | 23-12-2016 | Kapkote WSS | Environment consultation at Kapkote Nagarpanchayat Office by Dr Nutan Gupta (Environment Sp.PMU) | Rajesh Upadhyay | Project Manager | UEAP-WS Bageshwar | See Pic |
19. | 21-12-2016 | Kapkote I Well | Final coat painting and site devlopment work at I well. | Rajesh Upadhyay | Project Manager | UEAP-WS Bageshwar | See Pic |
20. | 19-12-2016 | Kapkote I well | AE UJS with DSC visited Kapkote I Well | Rajesh Upadhyay | Project Manager | UEAP-WS Bageshwar | See Pic |
|
|