Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UK/UEAP-WSS/UJS/KU/01/lot1 Agreement signed
Project: UEAP-WS Package No.: 2101 Package Name: UK/UEAP-WSS/UJS/KU/01/lot1 Sanction Cost: 598.00  lakhs
District: Bageshwar Block: Kapkot Constituency: Bageshwar Circle:
DEA: DEA WS Kapkot DSC: DSC Scope: Design & Supervision No.of Sub project : 1
Subproject in this package
1  7101   Kapkot-Water-Supply-Scheme ( KM.) (completed)
Procurement:
Package No.: 2101        Package Name: UK/UEAP-WSS/UJS/KU/01/lot1        Tender Date: 16-09-2014        Current Status: Agreement signed        Achieved on Date: 15-11-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UK/UEAP-WSS/UJS/KU/01/lot1        Contractor Name: Kashmirilal Constructions (P) Ltd.       
Start Date: 01-12-2014        Intended Completion Date: 28-02-2017        Original End Date:  31-05-2016
Total Bond Cost: 53380185 (533.8 lakhs)        Variation Cost: 1656042.84 (16.56 lakhs)     Hence Total Bond Cost is   55036227.84 (550.36 lakhs) 
LD Analysis for Milestone1: calculated LD is Rs 4163640 for 156 days        LD Analysis for Milestone2: calculated LD is Rs 3683220 for 138 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Infiltration Well/Tube Well1.00 No128.001.00 No1.00 No23.87128.00
2.Pipe Line Works with (Main/ Distribution)7641.00 m209.117711.00 m7711.00 m38.99209.11
3.Electrical and Instrumentation work1.00 No38.701.00 No1.00 No7.2238.70
4.Mechanical Work4.00 No128.354.00 No4.00 No23.93128.35
5.Env. Man & Moni Plan1.00 Job5.181.00 Job1.00 Job0.975.18
6.Provisional Sum1.00 Job27.001.00 Job1.00 Job5.0327.00
Total Amount: 536.34 100   536.34
Remarks: No Remarks       Work Program Made On: 30-03-2015       Updation of work program on: 08-06-2017      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.20-October-201554.42  lakhs
2.18-November-2015100.85  lakhs
3.22-March-201667.74  lakhs
4.23-June-2016156.55  lakhs
5.17-August-201619.53  lakhs
6.25-October-201640.92  lakhs
7.03-March-201714.65  lakhs
8.31-May-201752.01  lakhs
Total 506.67  lakhs
% Payment 92.06 %
Advance Amount:  67.68  lakhs        Recovered Amount:  67.68  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
Test Information not Available.
Number of Pics Available on Web Repository: 51
Number of Notice(s) issued: 118

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.20-07-2017Binsar TankBinsar Tank protection work going on progress.Rajesh UpadhyayProject ManagerUEAP-WS Bageshwar See Pic
2.20-07-2017Binsar 200KL TankTank exavation work going on progress.Rajesh UpadhyayProject ManagerUEAP-WS Bageshwar See Pic
3.28-04-2017Kapkot I wellInside view of Pump HouseRajesh UpadhyayProject ManagerUEAP-WS Bageshwar See Pic
4.28-04-2017Kapkote I WellSite view of I wellRajesh UpadhyayProject ManagerUEAP-WS Bageshwar See Pic
5.02-04-2017Kapkot I WellAll works are completed.Rajesh UpadhyayProject ManagerUEAP-WS Bageshwar See Pic
6.16-03-2017Kapkote I wellChain link fencing work going on progress.Rajesh UpadhyayProject ManagerUEAP-WS Bageshwar See Pic
7.09-03-2017Kapkot I wellChain link fencing work going on progress.Rajesh UpadhyayProject ManagerUEAP-WS Bageshwar See Pic
8.07-03-2017Kapkot I wellAE, JE(UJS) and CS DSC visited Kapkot I well.Rajesh UpadhyayProject ManagerUEAP-WS Bageshwar See Pic
9.04-03-2017Kapkot I wellExtra Item work inspection taken by FPIU and DSCRajesh UpadhyayProject ManagerUEAP-WS Bageshwar See Pic
10.03-03-2017I. Well kapkotFencing workBikash Kumar DasConstuction SupervisorDSC WS ADB Bageshwar See Pic
11.03-03-2017I. Well, KapkotGate fixingBikash Kumar DasConstuction SupervisorDSC WS ADB Bageshwar See Pic
12.03-03-2017Kapkot I wellExtra item works going on progress.Rajesh UpadhyayProject ManagerUEAP-WS Bageshwar See Pic
13.22-01-2017Kapkote I WellFire buckets fixed at I well.Rajesh UpadhyayProject ManagerUEAP-WS Bageshwar See Pic
14.13-01-2017Kapkot I-wellInformation board fixed at KapkotRajesh UpadhyayProject ManagerUEAP-WS Bageshwar See Pic
15.12-01-2017Kapkot I wellI Well painting work completed.Rajesh UpadhyayProject ManagerUEAP-WS Bageshwar See Pic
16.31-12-2016Kapkote I wellAutomation(SCADA) is working at Kapkote I well.Rajesh UpadhyayProject ManagerUEAP-WS Bageshwar See Pic
17.29-12-2016Kapkote I wellFinal coat Painting work at Kapkote I wellRajesh UpadhyayProject ManagerUEAP-WS Bageshwar See Pic
18.23-12-2016Kapkote WSSEnvironment consultation at Kapkote Nagarpanchayat Office by Dr Nutan Gupta (Environment Sp.PMU)Rajesh UpadhyayProject ManagerUEAP-WS Bageshwar See Pic
19.21-12-2016Kapkote I WellFinal coat painting and site devlopment work at I well.Rajesh UpadhyayProject ManagerUEAP-WS Bageshwar See Pic
20.19-12-2016Kapkote I wellAE UJS with DSC visited Kapkote I WellRajesh UpadhyayProject ManagerUEAP-WS Bageshwar See Pic