Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UK/UEAP/CA/Hangar/Package-3 Bond Terminated
Project: UEAP-CA Package No.: 2041 Package Name: UK/UEAP/CA/Hangar/Package-3 Sanction Cost: 500.00  lakhs
District: Pithoragarh Block: Pithoragarh(Bin) Constituency: Pithoragarh Circle:
DEA: DEA CA DSC: DSC Scope: supervision No.of Sub project : 1
Subproject in this package
1  7047   NainiSaini (0.000 KM.)
Procurement:
Package No.: 2041        Package Name: UK/UEAP/CA/Hangar/Package-3        Tender Date: 24-06-2016        Current Status: Bond Terminated        Achieved on Date: 04-01-2017

Construction Phase

Agreement Details
Bond/Agreement Name: UK/UEAP/CA/Hangar/Package-3        Contractor Name: Shiva Electrial       
Start Date: 12-01-2017        Intended Completion Date: 19-07-2017       
Total Bond Cost: 34378183 (343.78 lakhs)       
LD Analysis for Milestone1: calculated LD is Rs 18151584 for 1056 days        LD Analysis for Milestone2: calculated LD is Rs 18151584 for 1056 days       
Bond Terminated.
Financial Progress
No Financial Progress.
Advance Amount:  0.00  lakhs        Recovered Amount:  0.00  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Terminated Package
Quality
Test Information not Available.
Number of Pics Available on Web Repository: 6
Number of Notice(s) issued: 22

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.06-06-2017NainiseniExcavation work in progressShankar TrivediJEUEAP R&B and CA Pithoragarh See Pic
2.23-05-2017Nainiseni hangarExcavation of one tranch completedShankar TrivediJEUEAP R&B and CA Pithoragarh See Pic
3.23-05-2017Naniseni hangarLeveling at Naniseni hangar with AE sirShankar TrivediJEUEAP R&B and CA Pithoragarh See Pic
4.23-05-2017Nainiseni hangarExcavation continueShankar TrivediJEUEAP R&B and CA Pithoragarh See Pic
5.15-05-2017Nainiseni hangarExcavation workShankar TrivediJEUEAP R&B and CA Pithoragarh See Pic
6.15-05-2017Nainiseni hangarExcavation work continueShankar TrivediJEUEAP R&B and CA Pithoragarh See Pic