Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UK/UEAP-CA/PKG1/01 Agreement signed
Project: UEAP-CA Package No.: 2001 Package Name: UK/UEAP-CA/PKG1/01 Sanction Cost: 819.02  lakhs
District: Chamoli Block: unknown Constituency: unknown Circle:
DEA: DEA CA DSC: DSC Scope: supervision No.of Sub project : 11
Subproject in this package
1  7001   Auli ( KM.) (in prorgress)
2  7003   Agastyamuni ( KM.) (in prorgress)
3  7004   Rudraprayag ( KM.) (in prorgress)
4  7008   Pauri (Ransi) ( KM.) (in prorgress)
5  7010   Chamba ( KM.) (in prorgress)
6  7011   Narendra Nagar ( KM.) (in prorgress)
7  7015   Dwarahat ( KM.) (in prorgress)
8  7016   Chaukhutia ( KM.) (in prorgress)
9  7017   Kapkot ( KM.) (in prorgress)
10  7018   Khati ( KM.) (in prorgress)
11  7019   Champawat ( KM.) (in prorgress)
Procurement:
Package No.: 2001        Package Name: UK/UEAP-CA/PKG1/01        Tender Date: 05-09-2014        Current Status: Agreement signed        Achieved on Date: 26-11-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UK/UEAP-CA/PKG1/01        Contractor Name: Woodhill Infrastructure Ltd       
Start Date: 20-03-2015        Intended Completion Date: 20-06-2016       
Total Bond Cost: 114957868 (1149.58 lakhs)       
LD Analysis for Milestone1: calculated LD is Rs 8736808 for +152 days        LD Analysis for Milestone2: calculated LD is Rs 8794287 for 153 days       
Component Wise Progress
No Physical Progress.
Remarks: No Remarks      
Work Program Status:This Package contain more than one subproject,pleae check individua subproject for Program Expired.
Financial Progress
SNo. Date Payment
1.29-October-2015104.71  lakhs
2.31-October-20150.17  lakhs
3.11-January-201644.88  lakhs
4.16-February-201669.86  lakhs
5.10-March-201646.88  lakhs
6.31-May-201636.29  lakhs
7.21-January-2017103.86  lakhs
8.25-February-201754.06  lakhs
Total 460.71  lakhs
% Payment 40.08 %
Advance Amount:  114.96  lakhs        Recovered Amount:  16.63  lakhs        Balance to be Recovered  98.32  lakhs        * Advances are at package level not sub project level
Analysis:Physical Progress Wrongly Reported.
Pending Environmental & Social issues
Environment & Social Compliances(Package level): PUC vehicles
Environment & Social Compliances(Sub Project level):
Auli(7001) Signs, Query, Borrow pits, DG set
Agastyamuni(7003) Query, Borrow pits, DG set
Rudraprayag(7004) Query, Borrow pits, DG set
Pauri (Ransi)(7008) Query, Borrow pits, DG set
Chamba(7010) Query, Borrow pits, DG set
Narendra Nagar(7011) Query, Borrow pits, DG set
Dwarahat(7015) Query, Borrow pits, DG set
Chaukhutia(7016) Query, Borrow pits, DG set
Kapkot(7017) Query, Borrow pits, DG set
Khati(7018) Query, Borrow pits, DG set
Champawat(7019) debris disposal, Query, Borrow pits, DG set
Detailed report of this Package
Quality
Test Information not Available.
Number of Pics Available on Web Repository: 74
Number of Notice(s) issued: 73

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.04-03-2017Kapkot I.well fencing workKapkot i.wellBikash Kumar DasConstuction SupervisorDSC WS ADB Bageshwar See Pic
2.29-10-2016Narendra nagar helipadLatest photo of Narendra nagar helipadShivendra PrakashAEUEAP- CA Tehri See Pic
3.29-10-2016Narendra nagar helipadSafety area development has remainingShivendra PrakashAEUEAP- CA Tehri See Pic
4.29-10-2016Narendra nagar helipadSafety area development has remainingShivendra PrakashAEUEAP- CA Tehri See Pic
5.29-10-2016Chamba helipadFato marking has not according to drawing in Chamba helipad siteShivendra PrakashAEUEAP- CA Tehri See Pic
6.29-10-2016Chamba helipadFato marking has done but not according to drawingShivendra PrakashAEUEAP- CA Tehri See Pic
7.24-10-2016Bhatwari road WTPFixing steel section in settling tank for PVC tube settler supportMonendra Singh RanaConstruction supervisorDSC WS ADB Tehri See Pic
8.28-09-2016Champawat helipadWork in not progressShankar TrivediJEUEAP R&B and CA Pithoragarh See Pic
9.28-09-2016Champawat helipadCutting work stoppedShankar TrivediJEUEAP R&B and CA Pithoragarh See Pic
10.24-08-2016Chamba helipadMarking of fato area has remainingShivendra PrakashAEUEAP- CA Tehri See Pic
11.24-08-2016Chamba helipadNo safety area development had doneShivendra PrakashAEUEAP- CA Tehri See Pic
12.24-08-2016Chamba helipadJoint filling of panel is not in proper wayShivendra PrakashAEUEAP- CA Tehri See Pic
13.24-08-2016Chamba helipadLatest photo of Chamba helipadShivendra PrakashAEUEAP- CA Tehri See Pic
14.24-08-2016Narendra nagarSafety area development is remaining.Shivendra PrakashAEUEAP- CA Tehri See Pic
15.24-08-2016Narendra nagar helipadJoint filling has not done in proper way.Shivendra PrakashAEUEAP- CA Tehri See Pic
16.24-08-2016Narendra nagar helipadNo any work is going on Narendra nagar helipadShivendra PrakashAEUEAP- CA Tehri See Pic
17.24-08-2016Narendra nagar Helipad siteLatest photo of Narendra nagar helipadShivendra PrakashAEUEAP- CA Tehri See Pic
18.19-03-2016Narendra nagar helipadNarendra nagar helipadShivendra PrakashAEUEAP- CA Tehri See Pic
19.19-03-2016Narendra nagar HelipadJoint filling by silicone sealantShivendra PrakashAEUEAP- CA Tehri See Pic
20.09-03-2016Chamba helipadJoint filling start at Chamba helipadShivendra PrakashAEUEAP- CA Tehri See Pic