UDRP/PWD/01/30/RD/002
Agreement signed
|
Project: |
UDRP-RB |
Package No.: |
2 |
Package Name: |
UDRP/PWD/01/30/RD/002 |
Sanction Cost: |
191.75 lakhs |
District: |
Uttarkashi |
Block: |
Dunda |
Constituency: |
Gangotri |
Circle: |
Rudraprayag WB Circle |
DEA: |
DEA Uttarkashi |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
only Supervision |
No.of Sub project : |
5 |
Subproject in this package |
1 3114 Barethi Kanwa Motor road (2.000 KM.) (completed) | 2 3146 Dunda Kurha Motor road Phase1 (2.000 KM.) (completed) | 3 3148 From Gangotri NH to ITBP Motor road (0.820 KM.) (completed) | 4 3183 Nakuri Singoth Motor road (6.000 KM.) (completed) | 5 3188 Newgaon Sari Shrikalkhal Motor road phase1 (10.000 KM.) (completed) |
|
Procurement: |
Package No.: 2
Package Name: UDRP/PWD/01/30/RD/002
Tender Date: 20-11-2014
Current Status: Agreement signed
Achieved on Date: 03-06-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/01/30/RD/002
Contractor Name: Vinod Kumar Chauhan
|
Start Date: 10-06-2015
Intended Completion Date: 09-09-2016
|
Total Bond Cost: 18394419.74 (183.94 lakhs)
Variation Cost: 1403503.13 (14.04 lakhs) Hence Total Bond Cost is 19797922.87 (197.98 lakhs)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Hill side Cutting & Slip clearence | 7.00 KM | 1.01 | 7.00 KM | 7.00 KM | 1.04 | 1.01 | 2. | R/Wall, B/ Wall Type Protection works | 889.00 m | 118.16 | 889.00 m | 889.00 m | 73.65 | 118.16 | 3. | G-3 | 3.00 KM | 5.65 | 3.00 KM | 3.00 KM | 1.52 | 5.65 | 4. | PC/CC i/c Prime Coat, Tack Coat | 3.00 KM | 32.18 | 3.00 KM | 3.00 KM | 8.66 | 32.18 | 5. | longitudinal Drain | 2125.00 m | 35.35 | 2125.00 m | 2125.00 m | 8.21 | 35.35 | 6. | Road Furniture | 66.00 No | 4.30 | 66.00 No | 66.00 No | 4.18 | 4.30 | 7. | Env. Man & Moni Plan | 5.00 Job | 2.42 | 5.00 Job | 5.00 Job | 1.18 | 2.42 | 8. | Cause Way | 1.00 No | 1.11 | 1.00 No | 1.00 No | 1.55 | 1.11 |
Total Amount: |
200.18 |
|
100 |
200.18 |
|
Remarks:
No Remarks
Work Program Made On:
05-08-2015
Updation of work program on:
16-10-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 26-September-2015 | 47.00 lakhs |
2. | 30-September-2015 | 17.41 lakhs |
3. | 13-October-2015 | 45.19 lakhs |
4. | 09-November-2015 | 31.87 lakhs |
5. | 22-June-2016 | 19.79 lakhs |
6. | 21-August-2015 | 34.08 lakhs |
7. | 19-February-2016 | 2.37 lakhs |
Total |
197.71 lakhs |
% Payment |
99.87 % |
|
Advance Amount: 10.20 lakhs
Recovered Amount: 10.20 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 400 |
Number of Notice(s) issued: 93 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 30-12-2016 | 0.525 | Road surface PC damaged due to blockage of the Pucca drain. | Ashish Anthwal | Environment Specialist | PIU UDRP R&B Dehradun | See Pic |
2. | 20-10-2016 | Ch 1/18 | PC Work in progress | Naveen Kumar Sharma | AE | UDRP R&B Karanprayag | See Pic |
3. | 28-07-2016 | Ch3/29 | Wbm g1 thinkness checking | Neeraj Pathak | QC | DSC1 R&B WB Uttarkashi | See Pic |
4. | 28-07-2016 | Ch3/28 | Wbm g2 laying on progress | Neeraj Pathak | QC | DSC1 R&B WB Uttarkashi | See Pic |
5. | 28-07-2016 | Km2 to 3 | WBM g2 material preparation at site | Neeraj Pathak | QC | DSC1 R&B WB Uttarkashi | See Pic |
6. | 11-07-2016 | 1/11 | inspection of completed road by T.L Sheladia associates | Praveen Gupta | RE | DSC1 R&B WB Uttarkashi | See Pic |
7. | 10-07-2016 | Km 2 | Site visit with TL sir | Neeraj Pathak | QC | DSC1 R&B WB Uttarkashi | See Pic |
8. | 10-07-2016 | Ch0/0 | Site visit with TL sir | Neeraj Pathak | QC | DSC1 R&B WB Uttarkashi | See Pic |
9. | 10-07-2016 | Ch0/4 | Site visit with TL sir | Neeraj Pathak | QC | DSC1 R&B WB Uttarkashi | See Pic |
10. | 10-07-2016 | Km1 | Drain work completed | Neeraj Pathak | QC | DSC1 R&B WB Uttarkashi | See Pic |
11. | 19-06-2016 | Ch 9/38 | Culvert in progress | Naveen Kumar Sharma | AE | UDRP R&B WB Karanprayag | See Pic |
12. | 17-06-2016 | Culliwall work in progress km 1/21 | Culliwall | Sadhan Negi | Site Supervisor | DSC1 R&B WB Uttarkashi | See Pic |
13. | 14-06-2016 | 0/20 | Cooli wall | Chandra Lal Bharti | JE | UDRP R&B Uttarkashi | See Pic |
14. | 14-06-2016 | 4/27 | B wall | Chandra Lal Bharti | JE | UDRP R&B Uttarkashi | See Pic |
15. | 14-06-2016 | 1/20 | Colli wall | Chandra Lal Bharti | JE | UDRP R&B Uttarkashi | See Pic |
16. | 13-06-2016 | 2/16 | G3 layer | Chandra Lal Bharti | JE | UDRP R&B Uttarkashi | See Pic |
17. | 13-06-2016 | 1/33 | G1+G2+G3 Layer | Chandra Lal Bharti | JE | UDRP R&B Uttarkashi | See Pic |
18. | 13-06-2016 | Laying of G3 | 0/26 | Chandra Lal Bharti | JE | UDRP R&B Uttarkashi | See Pic |
19. | 07-06-2016 | 4/20 | Retaining wall | Chandra Lal Bharti | JE | UDRP R&B Uttarkashi | See Pic |
20. | 01-06-2016 | Retaining wall Ley out km 4/22 | Retaining wall | Sadhan Negi | Site Supervisor | DSC1 R&B WB Uttarkashi | See Pic |
|
|