Package Profile Report

UDRP/PWD/04/44/RD/019 Agreement signed
Project: UDRP-RB Package No.: 19 Package Name: UDRP/PWD/04/44/RD/019 Sanction Cost: 538.31  lakhs
District: Tehri Block: Chamba Constituency: Tehri Circle: Tehri WB Circle
DEA: DEA Tehri DSC: Egis International DSC Scope: only Supervision No.of Sub project : 1
Subproject in this package
1  2695   Gaja-Dandachali Motor road (10.000 KM.) (completed)
Procurement:
Package No.: 19        Package Name: UDRP/PWD/04/44/RD/019        Tender Date: 27-03-2014        Current Status: Agreement signed        Achieved on Date: 09-09-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/04/44/RD/019        Contractor Name: Shiv Shankar Construction Company       
Start Date: 16-09-2014        Intended Completion Date: 30-04-2016        Original End Date:  15-12-2015
Total Bond Cost: 48702911 (487.03 lakhs)        Variation Cost: 3414469.87 (34.14 lakhs)     Hence Total Bond Cost is   52117380.87 (521.17 lakhs) 
LD Analysis for Milestone1: calculated LD is Rs 1022742 for 42 days        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.R/Wall, B/ Wall Type Protection works900.00 m70.002155.00 m2155.00 m13.870.00
2.GSB/RBI/G-13.50 KM17.383.00 KM3.00 KM3.4317.38
3.G-23.50 KM12.503.00 KM3.00 KM2.4712.50
4.G-33.50 KM15.163.50 KM3.50 KM2.9915.16
5.BM i/c Prime Coat, Tack Coat10.00 KM220.1010.00 KM10.00 KM43.4220.10
6.SDBC i/c Tackcoat10.00 KM129.0010.00 KM10.00 KM25.44129.00
7.Cause Way2.00 No7.004.00 No4.00 No1.387.00
8.Culverts/Scupper 30.00 No3.0025.00 No25.00 No0.593.00
9.longitudinal Drain10000.00 m15.009770.00 m9770.00 m2.9615.00
10.Crash Barrier550.00 m15.00618.00 m618.00 m2.9615.00
11.Parapet400.00 No2.00415.00 No415.00 No0.392.00
12.Road Furniture50.00 No1.0061.00 No61.00 No0.21.00
Total Amount: 507.14 100   507.14
Remarks: Package completed       Work Program Made On: 02-02-2015       Updation of work program on: 22-07-2016      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.31-October-201418.36  lakhs
2.31-December-20149.03  lakhs
3.30-January-201527.18  lakhs
4.31-March-201527.57  lakhs
5.30-May-201521.29  lakhs
6.12-June-2015102.06  lakhs
7.30-June-201571.88  lakhs
8.18-August-201531.69  lakhs
9.07-September-201569.88  lakhs
10.03-December-201572.78  lakhs
11.29-January-201612.26  lakhs
12.21-March-201612.37  lakhs
13.08-June-201631.77  lakhs
14.25-January-201711.62  lakhs
Total 519.74  lakhs
% Payment 99.72 %
Advance Amount:  101.59  lakhs        Recovered Amount:  101.59  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 398     No. of Test Done : 436      No. of Test Passed : 398      No. of Test Failed : 38   Test report of this package
Number of Pics Available on Web Repository: 88
Number of Notice(s) issued: 84

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.14-12-2016Ch 6.200Road surface and Scupper completedYashpal Singh ChauhanJEUDRP R&B Tehri See Pic
2.14-12-2016Ch 7.825Road surface and Scupper completedYashpal Singh ChauhanJEUDRP R&B Tehri See Pic
3.14-12-2016Ch. 7.950Road surface and Scupper completedYashpal Singh ChauhanJEUDRP R&B Tehri See Pic
4.14-12-2016Ch.0.075Causeway work completedNawal KishoreSite SupervisorDSC2 R&B WB Tehri See Pic
5.30-04-20160+075Slump test and cube Casting of M-30.Subhash ChandraQCDSC2 R&B WB Tehri See Pic
6.30-04-20160+075Causeway M-30 in Progress.Subhash ChandraQCDSC2 R&B WB Tehri See Pic
7.28-04-20160+090Causeway M-30 Casting done without information no curing arrangement at site cracks has been developed on top surface.Subhash ChandraQCDSC2 R&B WB Tehri See Pic
8.18-04-20167.000Site inspection by DPM Sir pkg 019 Gaja Dandachali M.RSudhir Kumar AEAEUDRP R&B Tehri See Pic
9.11-04-2016Ch.0.100Excavation for CausewayNawal KishoreSite SupervisorDSC2 R&B WB Tehri See Pic
10.30-03-2016Ch.7.505Cathpit of Scupper in progressNawal KishoreSite SupervisorDSC2 R&B WB Tehri See Pic
11.30-03-2016Ch.7. 635Cathpit of Scupper in progressNawal KishoreSite SupervisorDSC2 R&B WB Tehri See Pic
12.04-03-2016Ch. 5.375R/WSudhir Kumar AEAEUDRP R&B Tehri See Pic
13.19-02-2016Ch.1/38Labour camp not as per EMPNawal KishoreSite SupervisorDSC2 R&B WB Tehri See Pic
14.19-02-2016Ch.1/38Labour camp not as per EMPNawal KishoreSite SupervisorDSC2 R&B WB Tehri See Pic
15.19-02-2016Ch.5/13R/wall on progressNawal KishoreSite SupervisorDSC2 R&B WB Tehri See Pic
16.19-02-2016Ch. 5/36Stone collection for r wall without any saftey and material spreading on main road.Nawal KishoreSite SupervisorDSC2 R&B WB Tehri See Pic
17.04-12-2015Km 0.900Inspection of pkg 019 by world Bank MissionVirendra Singh PundirEEUDRP R&B Tehri See Pic
18.04-12-2015Km o.600Inspection of pkg 019 by World Bank MissionVirendra Singh PundirEEUDRP R&B Tehri See Pic
19.04-12-2015Km0.500Inspection of pkg 019 by world Bank MissionVirendra Singh PundirEEUDRP R&B Tehri See Pic
20.04-12-20150.400Inspection of pkg 019 by world Bank MissionVirendra Singh PundirEEUDRP R&B Tehri See Pic