UDRP/PWD/04/44/RD/019
Agreement signed
|
Project: |
UDRP-RB |
Package No.: |
19 |
Package Name: |
UDRP/PWD/04/44/RD/019 |
Sanction Cost: |
538.31 lakhs |
District: |
Tehri |
Block: |
Chamba |
Constituency: |
Tehri |
Circle: |
Tehri WB Circle |
DEA: |
DEA Tehri |
DSC: |
Egis International |
DSC Scope: |
only Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 2695 Gaja-Dandachali Motor road (10.000 KM.) (completed) |
|
Procurement: |
Package No.: 19
Package Name: UDRP/PWD/04/44/RD/019
Tender Date: 27-03-2014
Current Status: Agreement signed
Achieved on Date: 09-09-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/04/44/RD/019
Contractor Name: Shiv Shankar Construction Company
|
Start Date: 16-09-2014
Intended Completion Date: 30-04-2016
Original End Date: 15-12-2015
|
Total Bond Cost: 48702911 (487.03 lakhs)
Variation Cost: 3414469.87 (34.14 lakhs) Hence Total Bond Cost is 52117380.87 (521.17 lakhs)
|
LD Analysis for Milestone1: calculated LD is Rs 1022742 for 42 days
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | R/Wall, B/ Wall Type Protection works | 900.00 m | 70.00 | 2155.00 m | 2155.00 m | 13.8 | 70.00 | 2. | GSB/RBI/G-1 | 3.50 KM | 17.38 | 3.00 KM | 3.00 KM | 3.43 | 17.38 | 3. | G-2 | 3.50 KM | 12.50 | 3.00 KM | 3.00 KM | 2.47 | 12.50 | 4. | G-3 | 3.50 KM | 15.16 | 3.50 KM | 3.50 KM | 2.99 | 15.16 | 5. | BM i/c Prime Coat, Tack Coat | 10.00 KM | 220.10 | 10.00 KM | 10.00 KM | 43.4 | 220.10 | 6. | SDBC i/c Tackcoat | 10.00 KM | 129.00 | 10.00 KM | 10.00 KM | 25.44 | 129.00 | 7. | Cause Way | 2.00 No | 7.00 | 4.00 No | 4.00 No | 1.38 | 7.00 | 8. | Culverts/Scupper | 30.00 No | 3.00 | 25.00 No | 25.00 No | 0.59 | 3.00 | 9. | longitudinal Drain | 10000.00 m | 15.00 | 9770.00 m | 9770.00 m | 2.96 | 15.00 | 10. | Crash Barrier | 550.00 m | 15.00 | 618.00 m | 618.00 m | 2.96 | 15.00 | 11. | Parapet | 400.00 No | 2.00 | 415.00 No | 415.00 No | 0.39 | 2.00 | 12. | Road Furniture | 50.00 No | 1.00 | 61.00 No | 61.00 No | 0.2 | 1.00 |
Total Amount: |
507.14 |
|
100 |
507.14 |
|
Remarks:
Package completed
Work Program Made On:
02-02-2015
Updation of work program on:
22-07-2016
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 31-October-2014 | 18.36 lakhs |
2. | 31-December-2014 | 9.03 lakhs |
3. | 30-January-2015 | 27.18 lakhs |
4. | 31-March-2015 | 27.57 lakhs |
5. | 30-May-2015 | 21.29 lakhs |
6. | 12-June-2015 | 102.06 lakhs |
7. | 30-June-2015 | 71.88 lakhs |
8. | 18-August-2015 | 31.69 lakhs |
9. | 07-September-2015 | 69.88 lakhs |
10. | 03-December-2015 | 72.78 lakhs |
11. | 29-January-2016 | 12.26 lakhs |
12. | 21-March-2016 | 12.37 lakhs |
13. | 08-June-2016 | 31.77 lakhs |
14. | 25-January-2017 | 11.62 lakhs |
Total |
519.74 lakhs |
% Payment |
99.72 % |
|
Advance Amount: 101.59 lakhs
Recovered Amount: 101.59 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 88 |
Number of Notice(s) issued: 84 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 14-12-2016 | Ch 6.200 | Road surface and Scupper completed | Yashpal Singh Chauhan | JE | UDRP R&B Tehri | See Pic |
2. | 14-12-2016 | Ch 7.825 | Road surface and Scupper completed | Yashpal Singh Chauhan | JE | UDRP R&B Tehri | See Pic |
3. | 14-12-2016 | Ch. 7.950 | Road surface and Scupper completed | Yashpal Singh Chauhan | JE | UDRP R&B Tehri | See Pic |
4. | 14-12-2016 | Ch.0.075 | Causeway work completed | Nawal Kishore | Site Supervisor | DSC2 R&B WB Tehri | See Pic |
5. | 30-04-2016 | 0+075 | Slump test and cube Casting of M-30. | Subhash Chandra | QC | DSC2 R&B WB Tehri | See Pic |
6. | 30-04-2016 | 0+075 | Causeway M-30 in Progress. | Subhash Chandra | QC | DSC2 R&B WB Tehri | See Pic |
7. | 28-04-2016 | 0+090 | Causeway M-30 Casting done without information no curing arrangement at site cracks has been developed on top surface. | Subhash Chandra | QC | DSC2 R&B WB Tehri | See Pic |
8. | 18-04-2016 | 7.000 | Site inspection by DPM Sir pkg 019 Gaja Dandachali M.R | Sudhir Kumar AE | AE | UDRP R&B Tehri | See Pic |
9. | 11-04-2016 | Ch.0.100 | Excavation for Causeway | Nawal Kishore | Site Supervisor | DSC2 R&B WB Tehri | See Pic |
10. | 30-03-2016 | Ch.7.505 | Cathpit of Scupper in progress | Nawal Kishore | Site Supervisor | DSC2 R&B WB Tehri | See Pic |
11. | 30-03-2016 | Ch.7. 635 | Cathpit of Scupper in progress | Nawal Kishore | Site Supervisor | DSC2 R&B WB Tehri | See Pic |
12. | 04-03-2016 | Ch. 5.375 | R/W | Sudhir Kumar AE | AE | UDRP R&B Tehri | See Pic |
13. | 19-02-2016 | Ch.1/38 | Labour camp not as per EMP | Nawal Kishore | Site Supervisor | DSC2 R&B WB Tehri | See Pic |
14. | 19-02-2016 | Ch.1/38 | Labour camp not as per EMP | Nawal Kishore | Site Supervisor | DSC2 R&B WB Tehri | See Pic |
15. | 19-02-2016 | Ch.5/13 | R/wall on progress | Nawal Kishore | Site Supervisor | DSC2 R&B WB Tehri | See Pic |
16. | 19-02-2016 | Ch. 5/36 | Stone collection for r wall without any saftey and material spreading on main road. | Nawal Kishore | Site Supervisor | DSC2 R&B WB Tehri | See Pic |
17. | 04-12-2015 | Km 0.900 | Inspection of pkg 019 by world Bank Mission | Virendra Singh Pundir | EE | UDRP R&B Tehri | See Pic |
18. | 04-12-2015 | Km o.600 | Inspection of pkg 019 by World Bank Mission | Virendra Singh Pundir | EE | UDRP R&B Tehri | See Pic |
19. | 04-12-2015 | Km0.500 | Inspection of pkg 019 by world Bank Mission | Virendra Singh Pundir | EE | UDRP R&B Tehri | See Pic |
20. | 04-12-2015 | 0.400 | Inspection of pkg 019 by world Bank Mission | Virendra Singh Pundir | EE | UDRP R&B Tehri | See Pic |
|
|