Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/PWD/03/40/RD/029A(N) Agreement signed
Project: UDRP-RB Package No.: 148 Package Name: UDRP/PWD/03/40/RD/029A(N) Sanction Cost: 444.87  lakhs
District: Rudraprayag Block: Ukhimath Constituency: Kedarnath Circle: Rudraprayag WB Circle
DEA: DEA Guptkashi DSC: Yongma Engineering Co. Ltd. DSC Scope: only Supervision No.of Sub project : 1
Subproject in this package
1  2519   Salya-Tulanga MR (6.000 KM.) (completed)
Procurement:
Package No.: 148        Package Name: UDRP/PWD/03/40/RD/029A(N)        Tender Date: 11-06-2018        Current Status: Agreement signed        Achieved on Date: 28-09-2018

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/03/40/RD/029A(N)        Contractor Name: Sky International       
Start Date: 05-10-2018        Intended Completion Date: 23-06-2019        Original End Date:  04-06-2019
Total Bond Cost: 29283453.75 (292.83 lakhs)        Variation Cost: 1029306.35 (10.29 lakhs)     Hence Total Bond Cost is   30312760.1 (303.13 lakhs) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence6.00 KM15.786.00 KM6.00 KM5.3915.78
2.R/Wall, B/ Wall Type Protection works835.00 m52.10889.00 m889.00 m17.7952.10
3.GSB/RBI/G-12.10 KM17.131.76 KM1.76 KM5.8517.13
4.G-24.70 KM27.244.70 KM4.70 KM9.327.24
5.G-36.00 KM35.776.00 KM6.00 KM12.2235.77
6.PC/CC i/c Prime Coat, Tack Coat6.00 KM49.126.00 KM6.00 KM16.7749.12
7.Cause Way2.00 No11.822.00 No2.00 No4.0411.82
8.Culverts/Scupper 11.00 No31.6013.00 No13.00 No10.7931.60
9.longitudinal Drain6.00 m22.156.00 m6.00 m7.5622.15
10.Parapet300.00 No8.35300.00 No300.00 No2.858.35
11.Road Furniture428.00 No11.00428.00 No428.00 No3.7611.00
12.Other Allied Works & Finishing Work 1.00 Job10.771.00 Job1.00 Job3.6810.77
Total Amount: 292.83 100   292.83
Remarks: physical 100%       Work Program Made On: 12-11-2018       Updation of work program on: 12-11-2018      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.31-December-201834.40  lakhs
2.22-February-201918.75  lakhs
3.04-April-201945.82  lakhs
4.30-April-201918.34  lakhs
5.16-May-201931.48  lakhs
6.01-June-201950.03  lakhs
7.19-June-201929.43  lakhs
8.10-July-201935.95  lakhs
9.30-July-201925.15  lakhs
Total 289.35  lakhs
% Payment 95.46 %
Advance Amount:  0.00  lakhs        Recovered Amount:  0.00  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
Test Information not Available.
Number of Pics Available on Web Repository: 115
No Notice issued.

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.27-05-20194.600G3 laying after compaction..Siddharth RangharJEUDRP R&B Guptkashi See Pic
2.27-05-2019Chainage 4.100 Hp bendCME Sir and EE Sir visit at Salya Tulangaa motor Road regarding progress.Siddharth RangharJEUDRP R&B Guptkashi See Pic
3.06-05-20195+400Site visit by CME,EE and AE sir.Anurag DevJEUDRP R&B Guptkashi See Pic
4.02-05-20192.650P.c work at Salya Tulangaa motor Road.Siddharth RangharJEUDRP R&B Guptkashi See Pic
5.07-04-20190.250Soil nail in progress for Hydroseeding work at Km 8 Guptkashi.Siddharth RangharJEUDRP R&B Guptkashi See Pic
6.02-04-20192.300G3 wbm layed at chainage 2.300. with Stone screeningSiddharth RangharJEUDRP R&B Guptkashi See Pic
7.30-03-20190.400WBM laying in progress with compaction.Siddharth RangharJEUDRP R&B Guptkashi See Pic
8.29-03-20195.200Exen Sir Visit at PKG no. 29N(A) regarding slow work progress.Siddharth RangharJEUDRP R&B Guptkashi See Pic
9.29-03-20196.000Exen sir visit at Salya Tulangaa Motor Road Guptkashi division regarding slow work progress.of pkg29N(A)Siddharth RangharJEUDRP R&B Guptkashi See Pic
10.02-03-20192.300G2 laying started on chainage 2.300 Salya Tulangaa Motor RoadSiddharth RangharJEUDRP R&B Guptkashi See Pic
11.28-02-20194.800SE sir visit at Salya Tulangaa Motor Road Pkg 29 N(A).Siddharth RangharJEUDRP R&B Guptkashi See Pic
12.08-02-20191.275Wirecrates wall in progress at chainage 1.275Siddharth RangharJEUDRP R&B Guptkashi See Pic
13.08-02-20193.300Stone ballast breaking at chainage 3.300Siddharth RangharJEUDRP R&B Guptkashi See Pic
14.31-01-20193.200Stone Ballast breaking at chainage 3.200Siddharth RangharJEUDRP R&B Guptkashi See Pic
15.15-01-20190.975Coolie wall construction under process in km 1Siddharth RangharJEUDRP R&B Guptkashi See Pic
16.15-01-20191.200Stone collection for Wbm ballast .Siddharth RangharJEUDRP R&B Guptkashi See Pic
17.09-01-20191.500Coolie wall construction in progress.Siddharth RangharJEUDRP R&B Guptkashi See Pic
18.09-01-20191.400Hp bend improvement at chainage 1.400Siddharth RangharJEUDRP R&B Guptkashi See Pic
19.09-01-20191.250Parapet casting in progress.Siddharth RangharJEUDRP R&B Guptkashi See Pic
20.07-01-20191.100Hard Rock cutting by Rock Breaker.Siddharth RangharJEUDRP R&B Guptkashi See Pic