UDRP/PWD/09/01/RD/013(N)
Agreement signed
|
Project: |
UDRP-RB |
Package No.: |
147 |
Package Name: |
UDRP/PWD/09/01/RD/013(N) |
Sanction Cost: |
783.84 lakhs |
District: |
Almora |
Block: |
Lamgarha |
Constituency: |
Jageshwar |
Circle: |
Pithoragarh WB Circle |
DEA: |
DEA Bageshwar |
DSC: |
Royal Haskoning DHV |
DSC Scope: |
only Supervision |
No.of Sub project : |
2 |
Subproject in this package |
1 1044 Dhora-Ratankhan Motor Road (5.850 KM.) (completed) | 2 1059 Vishnath-Jaskot Road (8.000 KM.) (in prorgress) |
|
Procurement: |
Package No.: 147
Package Name: UDRP/PWD/09/01/RD/013(N)
Tender Date: 11-06-2018
Current Status: Agreement signed
Achieved on Date: 22-10-2018 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/09/01/RD/013(N)
Contractor Name: Technical Consultant and Construction Associates
|
Start Date: 30-10-2018
Intended Completion Date: 30-11-2019
Original End Date: 29-06-2019
|
Total Bond Cost: 40389569.89 (403.9 lakhs)
Variation Cost: 546545.88 (5.47 lakhs) Hence Total Bond Cost is 40936115.77 (409.36 lakhs)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Hill side Cutting & Slip clearence | 0.69 KM | 7.86 | 0.69 KM | 0.69 KM | 2.02 | 7.86 | 2. | R/Wall, B/ Wall Type Protection works | 600.00 m | 39.43 | 600.00 m | 600.00 m | 10.05 | 39.43 | 3. | G-2 | 3.25 KM | 39.04 | 3.50 KM | 3.25 KM | 9.42 | 36.28 | 4. | G-3 | 11.90 KM | 76.96 | 11.90 KM | 11.65 KM | 19.16 | 75.41 | 5. | PC/CC i/c Prime Coat, Tack Coat | 13.75 KM | 109.73 | 13.75 KM | 12.90 KM | 26.29 | 103.14 | 6. | Cause Way | 3.00 No | 15.20 | 7.00 No | 3.00 No | 3.75 | 15.20 | 7. | Culverts/Scupper | 13.00 No | 31.22 | 13.00 No | 13.00 No | 7.96 | 31.22 | 8. | longitudinal Drain | 11450.00 m | 14.70 | 11450.00 m | 11450.00 m | 3.76 | 14.70 | 9. | Crash Barrier | 500.00 m | 18.27 | 500.00 m | 500.00 m | 4.65 | 18.27 | 10. | Parapet | 254.00 No | 6.57 | 254.00 No | 254.00 No | 1.66 | 6.57 | 11. | Road Furniture | 580.00 No | 3.69 | 580.00 No | 580.00 No | 0.94 | 3.69 | 12. | Env. Man & Moni Plan | 2.00 Job | 6.09 | 2.00 Job | 2.00 Job | 1.55 | 6.09 | 13. | Other Allied Works & Finishing Work | 2.00 Job | 23.21 | 2.00 Job | 2.00 Job | 5.92 | 23.21 |
Total Amount: |
391.97 |
|
97.14 |
381.07 |
|
Remarks:
No Remarks
Work Program Made On:
17-11-2018
Updation of work program on:
15-03-2021
|
|
Work Program Status:This Package contain more than one subproject,pleae check individua subproject for Program Expired. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 16-November-2018 | 33.66 lakhs |
2. | 13-December-2018 | 24.50 lakhs |
3. | 09-January-2019 | 27.48 lakhs |
4. | 15-February-2019 | 50.17 lakhs |
5. | 18-March-2019 | 18.82 lakhs |
6. | 17-May-2019 | 55.55 lakhs |
7. | 03-June-2019 | 30.92 lakhs |
8. | 20-September-2019 | 40.97 lakhs |
9. | 21-June-2019 | 20.71 lakhs |
10. | 25-June-2019 | 13.22 lakhs |
11. | 29-June-2019 | 15.62 lakhs |
Total |
331.62 lakhs |
% Payment |
81.01 % |
|
Advance Amount: 0.00 lakhs
Recovered Amount: 0.00 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
Analysis:Bill should be issued |
|
Pending Environmental & Social issues
|
Environment & Social Compliances(Package level): | No Pending Issue | Environment & Social Compliances(Sub Project level): | Vishnath-Jaskot Road(1059) | EMP Land Owner Consent, Glove, water sprinkling, debris disposal | Vishnath-Jaskot Road(1059) | EMP Land Owner Consent, Glove, water sprinkling, debris disposal |
Detailed report of this Package
|
|
Quality
|
|
Number of Pics Available on Web Repository: 216 |
Number of Notice(s) issued: 1 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 06-11-2019 | 7+600 | World bank mission visit.. | Azhar Shad | JE | UDRP R&B Bageshwar | See Pic |
2. | 06-11-2019 | 7+500 | World Bank mission visit.. | Azhar Shad | JE | UDRP R&B Bageshwar | See Pic |
3. | 13-05-2019 | 1+600 | Rolling over p.c.. | Azhar Shad | JE | UDRP R&B Bageshwar | See Pic |
4. | 13-05-2019 | 1+700 | Rolling over P.C.. | Azhar Shad | JE | UDRP R&B Bageshwar | See Pic |
5. | 13-05-2019 | 1+700 | Rolling over P.C.. | Azhar Shad | JE | UDRP R&B Bageshwar | See Pic |
6. | 09-05-2019 | 2+575 | PC laying in progress... | Azhar Shad | JE | UDRP R&B Bageshwar | See Pic |
7. | 27-04-2019 | 5+900 | Rolling over p.c.. | Azhar Shad | JE | UDRP R&B Bageshwar | See Pic |
8. | 27-04-2019 | 2+100 | Surface cleaning is in progress.. | Azhar Shad | JE | UDRP R&B Bageshwar | See Pic |
9. | 25-04-2019 | Ch 4.200 | CE sir and SE sir and EE sir inspection | Jagdish Narayan Meena | unknown | unknown | See Pic |
10. | 25-04-2019 | Ch 5.600 | CE sir, SE sir and EE sir inspection | Jagdish Narayan Meena | unknown | unknown | See Pic |
11. | 25-04-2019 | Ch 5.600 | CE sir, SE sir and EE sir inspection | Jagdish Narayan Meena | unknown | unknown | See Pic |
12. | 28-02-2019 | 0+000 | Site visit by Rajesh pant sir C.M.E sir.. | Azhar Shad | JE | UDRP R&B Bageshwar | See Pic |
13. | 28-02-2019 | 1+325 | Rolling over G-3.. | Azhar Shad | JE | UDRP R&B Bageshwar | See Pic |
14. | 28-02-2019 | 1+300 | Rolling over G-3.. | Azhar Shad | JE | UDRP R&B Bageshwar | See Pic |
15. | 05-02-2019 | 5+290 | Excavation For K.C drain.. | Azhar Shad | JE | UDRP R&B Bageshwar | See Pic |
16. | 05-02-2019 | 5+300 | Excavation For K.C drain.. | Azhar Shad | JE | UDRP R&B Bageshwar | See Pic |
17. | 02-02-2019 | 3+300 | Fixing of crash barrier posts.. | Azhar Shad | JE | UDRP R&B Bageshwar | See Pic |
18. | 29-01-2019 | Ch 4.250 | CME and EE sir inspection | Jagdish Narayan Meena | unknown | unknown | See Pic |
19. | 19-01-2019 | 2+450 | Casting of half causeway.PQC.. | Azhar Shad | JE | UDRP R&B Bageshwar | See Pic |
20. | 19-01-2019 | 5+425 | Casting of half causeway PQC... | Azhar Shad | JE | UDRP R&B Bageshwar | See Pic |
|
|