Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/PWD/02/36/RD/026N Agreement signed
Project: UDRP-RB Package No.: 146 Package Name: UDRP/PWD/02/36/RD/026N Sanction Cost: 1064.17  lakhs
District: Chamoli Block: Gairsain Constituency: Karanprayag Circle: Rudraprayag WB Circle
DEA: DEA Karanprayag DSC: Yongma Engineering Co. Ltd. DSC Scope: only Supervision No.of Sub project : 2
Subproject in this package
1  1214   Panduwakhan Rohilda Motor Road (15.680 KM.) (completed)
2  1236   Gairsain Pajiyana Motor Road (15.000 KM.) (completed)
Procurement:
Package No.: 146        Package Name: UDRP/PWD/02/36/RD/026N        Tender Date: 29-01-2018        Current Status: Agreement signed        Achieved on Date: 02-07-2018

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/02/36/RD/026N        Contractor Name: R K Gupta Contractor       
Start Date: 12-07-2018        Intended Completion Date: 15-06-2019        Original End Date:  31-05-2019
Total Bond Cost: 46225278.26 (462.25 lakhs)       
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence30.68 KM15.1030.68 KM30.68 KM2.8715.10
2.R/Wall, B/ Wall Type Protection works1719.00 m86.001719.00 m1719.00 m16.3686.00
3.GSB/RBI/G-14.77 KM54.774.77 KM4.77 KM10.4254.77
4.G-25.52 KM41.585.52 KM5.52 KM7.9141.58
5.G-37.29 KM59.827.29 KM7.29 KM11.3859.82
6.PC/CC i/c Prime Coat, Tack Coat14.32 KM126.8414.32 KM14.32 KM24.12126.84
7.Culverts/Scupper 16.00 No55.7116.00 No16.00 No10.5955.71
8.longitudinal Drain26500.00 m30.9826500.00 m26500.00 m5.8930.98
9.Crash Barrier650.00 m24.82650.00 m650.00 m4.7224.82
10.Parapet531.00 No11.00531.00 No531.00 No2.0911.00
11.Road Furniture304.00 No8.98304.00 No304.00 No1.718.98
12.Env. Man & Moni Plan2.00 Job10.252.00 Job2.00 Job1.9510.25
Total Amount: 525.85 100   525.85
Remarks: No Remarks       Work Program Made On: 04-09-2018       Updation of work program on: 02-08-2019      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.27-September-201827.05  lakhs
2.31-October-201849.68  lakhs
3.29-December-201834.03  lakhs
4.26-February-201920.93  lakhs
5.30-March-201916.55  lakhs
6.16-April-201917.79  lakhs
7.30-April-201956.27  lakhs
8.10-June-201996.14  lakhs
9.19-June-201966.60  lakhs
10.25-June-201926.28  lakhs
11.12-July-2019102.25  lakhs
12.15-July-201912.27  lakhs
Total 525.84  lakhs
% Payment 113.76 %
Advance Amount:  0.00  lakhs        Recovered Amount:  0.00  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Analysis:Physical Progress Wrongly Reported.
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 261     No. of Test Done : 321      No. of Test Passed : 321      No. of Test Failed : 0   Test report of this package
Number of Pics Available on Web Repository: 547
Number of Notice(s) issued: 7

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.15-06-2019Ch. 0.500Exen sir visit pandvakhal roadGaurav BhardwajJEUDRP R&B Karnprayag See Pic
2.19-05-2019Ch.11.000CME sir & Exen sir visit pc work at rohida roadGaurav BhardwajJEUDRP R&B Karnprayag See Pic
3.19-05-2019Ch.10.900CME sir & Exen Sir visit pc workGaurav BhardwajJEUDRP R&B Karnprayag See Pic
4.21-04-2019Ch.15.610Pc starts pandvakhal rohida roadGaurav BhardwajJEUDRP R&B Karnprayag See Pic
5.21-04-2019Ch.15.630Exen sir visit pc workGaurav BhardwajJEUDRP R&B Karnprayag See Pic
6.21-04-2019Ch.15.680Exen sir visit rohida road as pc work starts todayGaurav BhardwajJEUDRP R&B Karnprayag See Pic
7.05-04-2019Ch.15.680DPM sir visit rohida roadGaurav BhardwajJEUDRP R&B Karnprayag See Pic
8.05-04-2019Ch. 13.050DPM sir visit rohida roadGaurav BhardwajJEUDRP R&B Karnprayag See Pic
9.03-04-2019Ch.13.100Plum conc. For cause wayGaurav BhardwajJEUDRP R&B Karnprayag See Pic
10.31-03-2019Ch. 10.650Breaking of G3 aggregateGaurav BhardwajJEUDRP R&B Karnprayag See Pic
11.29-03-2019Km-8Site visit with EE sir and stickley instructed to the contractor for maintain drainage properly at pkg 26NAnkit KumarJEUDRP R&B Gopeshwar See Pic
12.29-03-2019Pkg 26NewChecking super elevation 12.900 km at 26NAnkit KumarJEUDRP R&B Gopeshwar See Pic
13.28-03-2019Ch.13.950Exen sir discussion with gram pradhan & local representativesGaurav BhardwajJEUDRP R&B Karnprayag See Pic
14.28-03-2019Ch.10.600Exen sir visit gairsain panjiyana roadGaurav BhardwajJEUDRP R&B Karnprayag See Pic
15.20-02-2019Ch 13.980SE sir visit pkg 26 N gairsain panjiyana roadGaurav BhardwajJEUDRP R&B Karnprayag See Pic
16.07-02-2019Patch workCh 10.975Lalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
17.21-01-2019Ch 11.400Plum protection on slipzone areaNaveen Kumar SharmaAEUDRP R&B Karanprayag See Pic
18.21-01-2019Ch 10.550Water sprinklingNaveen Kumar SharmaAEUDRP R&B Karanprayag See Pic
19.08-01-2019Ch.11.400Plum concrete in critical zone rohida roadGaurav BhardwajJEUDRP R&B Karnprayag See Pic
20.15-12-2018Ch.12.750Laying of G2 coat in km 13 in progress gairsain panjiyana roadGaurav BhardwajJEUDRP R&B Karnprayag See Pic