UDRP/PWD/02/36/RD/026N
Agreement signed
|
Project: |
UDRP-RB |
Package No.: |
146 |
Package Name: |
UDRP/PWD/02/36/RD/026N |
Sanction Cost: |
1064.17 lakhs |
District: |
Chamoli |
Block: |
Gairsain |
Constituency: |
Karanprayag |
Circle: |
Rudraprayag WB Circle |
DEA: |
DEA Karanprayag |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
only Supervision |
No.of Sub project : |
2 |
Subproject in this package |
1 1214 Panduwakhan Rohilda Motor Road (15.680 KM.) (completed) | 2 1236 Gairsain Pajiyana Motor Road (15.000 KM.) (completed) |
|
Procurement: |
Package No.: 146
Package Name: UDRP/PWD/02/36/RD/026N
Tender Date: 29-01-2018
Current Status: Agreement signed
Achieved on Date: 02-07-2018 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/02/36/RD/026N
Contractor Name: R K Gupta Contractor
|
Start Date: 12-07-2018
Intended Completion Date: 15-06-2019
Original End Date: 31-05-2019
|
Total Bond Cost: 46225278.26 (462.25 lakhs)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Hill side Cutting & Slip clearence | 30.68 KM | 15.10 | 30.68 KM | 30.68 KM | 2.87 | 15.10 | 2. | R/Wall, B/ Wall Type Protection works | 1719.00 m | 86.00 | 1719.00 m | 1719.00 m | 16.36 | 86.00 | 3. | GSB/RBI/G-1 | 4.77 KM | 54.77 | 4.77 KM | 4.77 KM | 10.42 | 54.77 | 4. | G-2 | 5.52 KM | 41.58 | 5.52 KM | 5.52 KM | 7.91 | 41.58 | 5. | G-3 | 7.29 KM | 59.82 | 7.29 KM | 7.29 KM | 11.38 | 59.82 | 6. | PC/CC i/c Prime Coat, Tack Coat | 14.32 KM | 126.84 | 14.32 KM | 14.32 KM | 24.12 | 126.84 | 7. | Culverts/Scupper | 16.00 No | 55.71 | 16.00 No | 16.00 No | 10.59 | 55.71 | 8. | longitudinal Drain | 26500.00 m | 30.98 | 26500.00 m | 26500.00 m | 5.89 | 30.98 | 9. | Crash Barrier | 650.00 m | 24.82 | 650.00 m | 650.00 m | 4.72 | 24.82 | 10. | Parapet | 531.00 No | 11.00 | 531.00 No | 531.00 No | 2.09 | 11.00 | 11. | Road Furniture | 304.00 No | 8.98 | 304.00 No | 304.00 No | 1.71 | 8.98 | 12. | Env. Man & Moni Plan | 2.00 Job | 10.25 | 2.00 Job | 2.00 Job | 1.95 | 10.25 |
Total Amount: |
525.85 |
|
100 |
525.85 |
|
Remarks:
No Remarks
Work Program Made On:
04-09-2018
Updation of work program on:
02-08-2019
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 27-September-2018 | 27.05 lakhs |
2. | 31-October-2018 | 49.68 lakhs |
3. | 29-December-2018 | 34.03 lakhs |
4. | 26-February-2019 | 20.93 lakhs |
5. | 30-March-2019 | 16.55 lakhs |
6. | 16-April-2019 | 17.79 lakhs |
7. | 30-April-2019 | 56.27 lakhs |
8. | 10-June-2019 | 96.14 lakhs |
9. | 19-June-2019 | 66.60 lakhs |
10. | 25-June-2019 | 26.28 lakhs |
11. | 12-July-2019 | 102.25 lakhs |
12. | 15-July-2019 | 12.27 lakhs |
Total |
525.84 lakhs |
% Payment |
113.76 % |
|
Advance Amount: 0.00 lakhs
Recovered Amount: 0.00 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
Analysis:Physical Progress Wrongly Reported. |
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 547 |
Number of Notice(s) issued: 7 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 15-06-2019 | Ch. 0.500 | Exen sir visit pandvakhal road | Gaurav Bhardwaj | JE | UDRP R&B Karnprayag | See Pic |
2. | 19-05-2019 | Ch.11.000 | CME sir & Exen sir visit pc work at rohida road | Gaurav Bhardwaj | JE | UDRP R&B Karnprayag | See Pic |
3. | 19-05-2019 | Ch.10.900 | CME sir & Exen Sir visit pc work | Gaurav Bhardwaj | JE | UDRP R&B Karnprayag | See Pic |
4. | 21-04-2019 | Ch.15.610 | Pc starts pandvakhal rohida road | Gaurav Bhardwaj | JE | UDRP R&B Karnprayag | See Pic |
5. | 21-04-2019 | Ch.15.630 | Exen sir visit pc work | Gaurav Bhardwaj | JE | UDRP R&B Karnprayag | See Pic |
6. | 21-04-2019 | Ch.15.680 | Exen sir visit rohida road as pc work starts today | Gaurav Bhardwaj | JE | UDRP R&B Karnprayag | See Pic |
7. | 05-04-2019 | Ch.15.680 | DPM sir visit rohida road | Gaurav Bhardwaj | JE | UDRP R&B Karnprayag | See Pic |
8. | 05-04-2019 | Ch. 13.050 | DPM sir visit rohida road | Gaurav Bhardwaj | JE | UDRP R&B Karnprayag | See Pic |
9. | 03-04-2019 | Ch.13.100 | Plum conc. For cause way | Gaurav Bhardwaj | JE | UDRP R&B Karnprayag | See Pic |
10. | 31-03-2019 | Ch. 10.650 | Breaking of G3 aggregate | Gaurav Bhardwaj | JE | UDRP R&B Karnprayag | See Pic |
11. | 29-03-2019 | Km-8 | Site visit with EE sir and stickley instructed to the contractor for maintain drainage properly at pkg 26N | Ankit Kumar | JE | UDRP R&B Gopeshwar | See Pic |
12. | 29-03-2019 | Pkg 26New | Checking super elevation 12.900 km at 26N | Ankit Kumar | JE | UDRP R&B Gopeshwar | See Pic |
13. | 28-03-2019 | Ch.13.950 | Exen sir discussion with gram pradhan & local representatives | Gaurav Bhardwaj | JE | UDRP R&B Karnprayag | See Pic |
14. | 28-03-2019 | Ch.10.600 | Exen sir visit gairsain panjiyana road | Gaurav Bhardwaj | JE | UDRP R&B Karnprayag | See Pic |
15. | 20-02-2019 | Ch 13.980 | SE sir visit pkg 26 N gairsain panjiyana road | Gaurav Bhardwaj | JE | UDRP R&B Karnprayag | See Pic |
16. | 07-02-2019 | Patch work | Ch 10.975 | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
17. | 21-01-2019 | Ch 11.400 | Plum protection on slipzone area | Naveen Kumar Sharma | AE | UDRP R&B Karanprayag | See Pic |
18. | 21-01-2019 | Ch 10.550 | Water sprinkling | Naveen Kumar Sharma | AE | UDRP R&B Karanprayag | See Pic |
19. | 08-01-2019 | Ch.11.400 | Plum concrete in critical zone rohida road | Gaurav Bhardwaj | JE | UDRP R&B Karnprayag | See Pic |
20. | 15-12-2018 | Ch.12.750 | Laying of G2 coat in km 13 in progress gairsain panjiyana road | Gaurav Bhardwaj | JE | UDRP R&B Karnprayag | See Pic |
|
|