UDRP/PWD/03/RD/129 Agreement signed
Project: UDRP-RB Package No.: 145 Package Name: UDRP/PWD/03/RD/129 Sanction Cost: 918.72  lakhs
District: Rudraprayag Block: 0017 Constituency: 7 Circle:
DEA: DEA Guptkashi DSC: Yongma Engineering Co. Ltd. DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  2568   Kandai Kamoldi Molkakhal MR Phase2 (Ch-0 to 10 Km) (10.000 KM.) (in prorgress)
Procurement:
Package No.: 145        Package Name: UDRP/PWD/03/RD/129        Tender Date: 07-04-2017        Current Status: Agreement signed        Achieved on Date: 14-11-2017

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/03/RD/129        Contractor Name: Tomar Construction Company       
Start Date: 21-11-2017        Intended Completion Date: 20-02-2019       
Total Bond Cost: 73800626.64 (738.01 lakhs)       
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 10258200 for 278 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence10.00 KM82.6810.00 KM9.00 KM10.0874.41
2.R/Wall, B/ Wall Type Protection works1384.00 m148.661384.00 m600.00 m8.7364.45
3.G-214.25 KM89.0114.25 KM7.25 KM6.1445.29
4.G-37.65 KM45.657.65 KM0.00 KM00.00
5.PC/CC i/c Prime Coat, Tack Coat10.00 KM115.9810.00 KM0.00 KM00.00
6.Cause Way3.00 No15.993.00 No0.00 No00.00
7.Culverts/Scupper 28.00 No66.4128.00 No12.00 No3.8628.46
8.longitudinal Drain9955.00 m40.689955.00 m2000.00 m1.118.17
9.Crash Barrier1450.00 m36.251450.00 m0.00 m00.00
10.Parapet950.00 No34.30950.00 No0.00 No00.00
11.Road Furniture594.00 No18.18594.00 No0.00 No00.00
12.Other Allied Works & Finishing Work 1.00 Job44.331.00 Job0.00 Job00.00
Total Amount: 738.12 29.91   220.78
Remarks: No Remarks       Work Program Made On: 29-12-2017       Updation of work program on: 22-05-2018      
Work Program Status:Work Programme workable.
Financial Progress
SNo. Date Payment
1.17-February-201848.18  lakhs
2.28-March-201855.24  lakhs
3.16-May-201826.32  lakhs
4.05-July-201835.17  lakhs
Total 164.91  lakhs
% Payment 22.35 %
Advance Amount:  0.00  lakhs        Recovered Amount:  0.00  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 347     No. of Test Done : 366      No. of Test Passed : 361      No. of Test Failed : 5   Test report of this package
Number of Pics Available on Web Repository: 61
Number of Notice(s) issued: 32

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.19-08-20187/000Scupper bed block castingSuresh Chandra SharmaJEUDRP R&B Guptkashi See Pic
2.17-08-20181/000R/wall drySuresh Chandra SharmaJEUDRP R&B Guptkashi See Pic
3.17-08-20188/250E.e sir sait vigitSuresh Chandra SharmaJEUDRP R&B Guptkashi See Pic
4.16-08-2018Km 4.7Scupper abutment work in progressRavi BishtJEUDRP R&B Guptkashi See Pic
5.13-08-2018Km 0.9Casting of Scupper slabRavi BishtJEUDRP R&B Guptkashi See Pic
6.11-08-2018Km 2.800Casting of Scupper bed blockRavi BishtJEUDRP R&B Guptkashi See Pic
7.11-08-2018Km 1.060SRMD, Kandai kamoldi road excavation for R/WRavi BishtJEUDRP R&B Guptkashi See Pic
8.08-08-20182/800Road clearing in progressSuresh Chandra SharmaJEUDRP R&B Guptkashi See Pic
9.30-07-20181/150thickness checking of wbm, 2 layer g2, totel thickness 17 cm.Suresh Chandra SharmaJEUDRP R&B Guptkashi See Pic
10.25-07-20185/200Wire create workSuresh Chandra SharmaJEUDRP R&B Guptkashi See Pic
11.23-07-20184/900Scupper slab castingSuresh Chandra SharmaJEUDRP R&B Guptkashi See Pic
12.23-07-20183/975Scupper slab reinforcementSuresh Chandra SharmaJEUDRP R&B Guptkashi See Pic
13.18-07-20183/195Scupper slab castingSuresh Chandra SharmaJEUDRP R&B Guptkashi See Pic
14.14-07-20185/500E.E. sir sait visitSuresh Chandra SharmaJEUDRP R&B Guptkashi See Pic
15.14-07-20181/135Hill side cuttingSuresh Chandra SharmaJEUDRP R&B Guptkashi See Pic
16.10-07-20181/350Scupper slab castingSuresh Chandra SharmaJEUDRP R&B Guptkashi See Pic
17.05-07-20181/450Scupper slab castingSuresh Chandra SharmaJEUDRP R&B Guptkashi See Pic
18.05-07-20181/135Scupper slab castingSuresh Chandra SharmaJEUDRP R&B Guptkashi See Pic
19.30-06-20180/470Slip ClearanceSuresh Chandra SharmaJEUDRP R&B Guptkashi See Pic
20.30-06-20186/575Hill side cuttingSuresh Chandra SharmaJEUDRP R&B Guptkashi See Pic