Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/PWD/08/RD/128 Agreement signed
Project: UDRP-RB Package No.: 144 Package Name: UDRP/PWD/08/RD/128 Sanction Cost: 565.24  lakhs
District: Bageshwar Block: 0074 Constituency: 46 Circle:
DEA: DEA Bageshwar DSC: Royal Haskoning DHV DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  1144   Okadi Ana Lohar Chada Gairlekh MR Phase2 (Ch-6 to 12 Km) (6.000 KM.) (in prorgress)
Procurement:
Package No.: 144        Package Name: UDRP/PWD/08/RD/128        Tender Date: 07-04-2017        Current Status: Agreement signed        Achieved on Date: 14-11-2017

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/08/RD/128        Contractor Name: Vinod Kumar Chauhan       
Start Date: 21-11-2017        Intended Completion Date: 20-02-2019       
Total Bond Cost: 52572926.3 (525.73 lakhs)       
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: 91 days remained       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence0.99 KM10.990.99 KM0.99 KM2.1610.99
2.R/Wall, B/ Wall Type Protection works631.00 m45.29631.00 m631.00 m8.9145.29
3.G-25.90 KM81.515.90 KM5.90 KM16.0481.51
4.G-35.90 KM47.065.90 KM5.90 KM9.2647.06
5.PC/CC i/c Prime Coat, Tack Coat5.90 KM77.155.90 KM5.75 KM14.875.19
6.Cause Way2.00 No4.442.00 No2.00 No0.874.44
7.Culverts/Scupper 26.00 No73.3826.00 No26.00 No14.4473.38
8.longitudinal Drain5.90 m103.055.90 m5.90 m20.28103.05
9.Crash Barrier907.00 m43.70908.00 m908.00 m8.643.70
10.Parapet400.00 No11.80468.00 No468.00 No2.3211.80
11.Road Furniture385.00 No3.75385.00 No2.00 No00.02
12.Env. Man & Moni Plan1.00 Job5.991.00 Job0.00 Job00.00
Total Amount: 508.11 97.7   496.43
Remarks: No Remarks       Work Program Made On: 04-01-2018       Updation of work program on: 18-05-2018      
Work Program Status:Work Programme workable.
Financial Progress
SNo. Date Payment
1.19-December-201765.00  lakhs
2.16-February-2018143.16  lakhs
3.26-March-2018138.03  lakhs
4.28-May-201889.18  lakhs
Total 435.37  lakhs
% Payment 82.81 %
Advance Amount:  0.00  lakhs        Recovered Amount:  0.00  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Analysis:Bill should be issued
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 490     No. of Test Done : 507      No. of Test Passed : 495      No. of Test Failed : 12   Test report of this package
Number of Pics Available on Web Repository: 123
Number of Notice(s) issued: 11

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.06-06-20186+230Shuttering for pucca drainMukesh KumarJEUDRP R&B Bageshwar See Pic
2.06-06-20188+180Seal coat over PC surfaceMukesh KumarJEUDRP R&B Bageshwar See Pic
3.06-06-20188+285Pc surface rollingMukesh KumarJEUDRP R&B Bageshwar See Pic
4.06-06-20188+300Pc laying work in progressMukesh KumarJEUDRP R&B Bageshwar See Pic
5.06-06-20188+800Hectometer stone castingMukesh KumarJEUDRP R&B Bageshwar See Pic
6.06-06-20186+250Pucca drain work in progressMukesh KumarJEUDRP R&B Bageshwar See Pic
7.06-06-20187+650Seal coat over PC surfaceMukesh KumarJEUDRP R&B Bageshwar See Pic
8.06-06-20187+700Seal coat over PC surfaceMukesh KumarJEUDRP R&B Bageshwar See Pic
9.06-06-20187+785Pc surfaceMukesh KumarJEUDRP R&B Bageshwar See Pic
10.06-06-20187+885Pc surface rollingMukesh KumarJEUDRP R&B Bageshwar See Pic
11.06-06-20187+300Pc surface rollingMukesh KumarJEUDRP R&B Bageshwar See Pic
12.06-06-20187+265Pc laying & rollingMukesh KumarJEUDRP R&B Bageshwar See Pic
13.06-06-20186+090Pucca drain (M10 ) casting work in progressMukesh KumarJEUDRP R&B Bageshwar See Pic
14.06-06-20187+220Seal coat over PC surfaceMukesh KumarJEUDRP R&B Bageshwar See Pic
15.06-06-20188+890PC surface,pucca drain, parapet, causewayMukesh KumarJEUDRP R&B Bageshwar See Pic
16.06-06-20188+900Seal coat rollingMukesh KumarJEUDRP R&B Bageshwar See Pic
17.06-06-20188+900Seal coat over PC surfaceMukesh KumarJEUDRP R&B Bageshwar See Pic
18.06-06-20189+430Tack coat before pcMukesh KumarJEUDRP R&B Bageshwar See Pic
19.06-06-20189+450Pc surface rollingMukesh KumarJEUDRP R&B Bageshwar See Pic
20.24-05-201811+550Check paper work related to progress by world Bank teamMukesh KumarJEUDRP R&B Bageshwar See Pic