Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/PWD/08/RD/128 Agreement signed
Project: UDRP-RB Package No.: 144 Package Name: UDRP/PWD/08/RD/128 Sanction Cost: 565.24  lakhs
District: Bageshwar Block: 0074 Constituency: 46 Circle:
DEA: DEA Bageshwar DSC: Royal Haskoning DHV DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  1144   Okadi Ana Lohar Chada Gairlekh MR Phase2 (Ch-6 to 12 Km) (6.000 KM.) (completed)
Procurement:
Package No.: 144        Package Name: UDRP/PWD/08/RD/128        Tender Date: 07-04-2017        Current Status: Agreement signed        Achieved on Date: 14-11-2017

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/08/RD/128        Contractor Name: Vinod Kumar Chauhan       
Start Date: 21-11-2017        Intended Completion Date: 20-02-2019       
Total Bond Cost: 52572926.3 (525.73 lakhs)       
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence0.99 KM10.990.99 KM0.99 KM2.1610.99
2.R/Wall, B/ Wall Type Protection works631.00 m45.29631.00 m631.00 m8.9145.29
3.G-25.90 KM81.515.90 KM5.90 KM16.0481.51
4.G-35.90 KM47.065.90 KM5.90 KM9.2647.06
5.PC/CC i/c Prime Coat, Tack Coat5.90 KM77.155.90 KM5.90 KM15.1877.15
6.Cause Way2.00 No4.442.00 No2.00 No0.874.44
7.Culverts/Scupper 26.00 No73.3826.00 No26.00 No14.4473.38
8.longitudinal Drain5.90 m103.055.90 m5.90 m20.28103.05
9.Crash Barrier907.00 m43.70908.00 m908.00 m8.643.70
10.Parapet400.00 No11.80468.00 No468.00 No2.3211.80
11.Road Furniture385.00 No3.75354.00 No354.00 No0.743.75
12.Env. Man & Moni Plan1.00 Job5.991.00 Job1.00 Job1.185.99
Total Amount: 508.11 100   508.11
Remarks: No Remarks       Work Program Made On: 04-01-2018       Updation of work program on: 18-05-2018      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.19-December-201765.00  lakhs
2.16-February-2018143.16  lakhs
3.26-March-2018138.03  lakhs
4.28-May-201889.18  lakhs
5.13-July-201855.27  lakhs
6.27-August-20186.24  lakhs
Total 496.88  lakhs
% Payment 94.51 %
Advance Amount:  0.00  lakhs        Recovered Amount:  0.00  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 522     No. of Test Done : 541      No. of Test Passed : 528      No. of Test Failed : 13   Test report of this package
Number of Pics Available on Web Repository: 175
Number of Notice(s) issued: 12

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.31-07-201811+000SRMD, Slip clearanceMukesh KumarJEUDRP R&B Bageshwar See Pic
2.31-07-201811+350SRMD, Slip clearanceMukesh KumarJEUDRP R&B Bageshwar See Pic
3.31-07-20187+900SRMD, Slip clearanceMukesh KumarJEUDRP R&B Bageshwar See Pic
4.31-07-20187+100SRMD, Slip clearanceMukesh KumarJEUDRP R&B Bageshwar See Pic
5.31-07-20187+100SRMD,Slip due to heavy rainMukesh KumarJEUDRP R&B Bageshwar See Pic
6.31-07-20187+850SRMD,Slip due to heavy rainMukesh KumarJEUDRP R&B Bageshwar See Pic
7.31-07-20188+250Hp bandMukesh KumarJEUDRP R&B Bageshwar See Pic
8.31-07-201810+220SRMD,Slip due to heavy rainMukesh KumarJEUDRP R&B Bageshwar See Pic
9.31-07-201811+000SRMD,Slip due to heavy rainMukesh KumarJEUDRP R&B Bageshwar See Pic
10.31-07-201811+050SRMD,Slip due to heavy rainMukesh KumarJEUDRP R&B Bageshwar See Pic
11.31-07-201811+100SRMD Slip due to heavy rainMukesh KumarJEUDRP R&B Bageshwar See Pic
12.31-07-201811+350SRMD,Slip due to heavy rainMukesh KumarJEUDRP R&B Bageshwar See Pic
13.30-07-2018Ch 8.200Road surface after pc and crash barrierJagdish Narayan Meenaunknownunknown See Pic
14.30-07-2018Ch 8.200Road surface after pc and crash barrierJagdish Narayan Meenaunknownunknown See Pic
15.30-07-2018Ch 8.220HP bend with crash barrier and pucca drainJagdish Narayan Meenaunknownunknown See Pic
16.30-07-2018Ch 8.250HP bend with crash barrier and pucca drainJagdish Narayan Meenaunknownunknown See Pic
17.30-07-2018Ch 10.220SRMD, slip due to heavy rainJagdish Narayan Meenaunknownunknown See Pic
18.30-07-2018Ch 11.000SRMD, slip due to heavy rainJagdish Narayan Meenaunknownunknown See Pic
19.30-07-2018Ch 11.050SRMD, slip due to heavy rain.Jagdish Narayan Meenaunknownunknown See Pic
20.30-07-2018Ch 10.790Surface after PC and parapetJagdish Narayan Meenaunknownunknown See Pic