UDRP/PWD/08/RD/127
Agreement signed
|
Project: |
UDRP-RB |
Package No.: |
143 |
Package Name: |
UDRP/PWD/08/RD/127 |
Sanction Cost: |
1095.89 lakhs |
District: |
Bageshwar |
Block: |
0074 |
Constituency: |
46 |
Circle: |
|
DEA: |
DEA Bageshwar |
DSC: |
Royal Haskoning DHV |
DSC Scope: |
Design and Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 1143 Katpudiya Chhina Seraghat MR (Ch-0 to 13 Km) (13.000 KM.) (completed) |
|
Procurement: |
Package No.: 143
Package Name: UDRP/PWD/08/RD/127
Tender Date: 07-04-2017
Current Status: Agreement signed
Achieved on Date: 14-11-2017 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/08/RD/127
Contractor Name: Tomar Construction Company
|
Start Date: 21-11-2017
Intended Completion Date: 07-05-2019
Original End Date: 20-02-2019
|
Total Bond Cost: 87931448.3 (879.31 lakhs)
Variation Cost: 7392623.24 (73.93 lakhs) Hence Total Bond Cost is 95324071.54 (953.24 lakhs)
|
LD Analysis for Milestone1: calculated LD is Rs 4660396 for 106 days
LD Analysis for Milestone2: calculated LD is Rs 2857790 for 65 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Hill side Cutting & Slip clearence | 9.93 KM | 117.93 | 9.93 KM | 9.93 KM | 13.41 | 117.93 | 2. | R/Wall, B/ Wall Type Protection works | 442.00 m | 46.65 | 442.00 m | 442.00 m | 5.31 | 46.65 | 3. | G-2 | 3.10 KM | 53.80 | 3.10 KM | 3.10 KM | 6.12 | 53.80 | 4. | G-3 | 3.10 KM | 33.29 | 3.10 KM | 3.10 KM | 3.79 | 33.29 | 5. | PC/CC i/c Prime Coat, Tack Coat | 15.46 KM | 170.99 | 15.46 KM | 15.46 KM | 19.45 | 170.99 | 6. | Cause Way | 25.00 No | 18.97 | 25.00 No | 25.00 No | 2.16 | 18.97 | 7. | Culverts/Scupper | 30.00 No | 151.89 | 30.00 No | 30.00 No | 17.27 | 151.89 | 8. | longitudinal Drain | 15455.00 m | 149.84 | 15455.00 m | 15455.00 m | 17.04 | 149.84 | 9. | Crash Barrier | 2460.00 m | 29.00 | 2460.00 m | 2460.00 m | 3.3 | 29.00 | 10. | Parapet | 1700.00 No | 39.41 | 1700.00 No | 1700.00 No | 4.48 | 39.41 | 11. | Road Furniture | 613.00 No | 8.98 | 613.00 No | 613.00 No | 1.02 | 8.98 | 12. | Env. Man & Moni Plan | 1.00 Job | 6.80 | 1.00 Job | 1.00 Job | 0.77 | 6.80 | 13. | Other Allied Works & Finishing Work | 1.00 Job | 51.78 | 1.00 Job | 1.00 Job | 5.89 | 51.78 |
Total Amount: |
879.33 |
|
100 |
879.33 |
|
Remarks:
No Remarks
Work Program Made On:
01-05-2018
Updation of work program on:
22-04-2019
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 08-March-2018 | 67.85 lakhs |
2. | 28-April-2018 | 36.44 lakhs |
3. | 07-August-2018 | 72.21 lakhs |
4. | 01-September-2018 | 39.98 lakhs |
5. | 29-September-2018 | 50.70 lakhs |
6. | 26-October-2018 | 82.76 lakhs |
7. | 02-November-2018 | 32.30 lakhs |
8. | 29-November-2018 | 66.56 lakhs |
9. | 31-December-2018 | 63.82 lakhs |
10. | 15-February-2019 | 77.20 lakhs |
11. | 28-February-2019 | 12.67 lakhs |
12. | 30-March-2019 | 95.10 lakhs |
13. | 16-April-2019 | 18.55 lakhs |
14. | 29-April-2019 | 87.10 lakhs |
15. | 29-May-2019 | 60.92 lakhs |
16. | 31-May-2019 | 7.62 lakhs |
17. | 20-June-2019 | 63.06 lakhs |
18. | 21-June-2019 | 3.00 lakhs |
Total |
937.84 lakhs |
% Payment |
98.38 % |
|
Advance Amount: 38.94 lakhs
Recovered Amount: 38.94 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 319 |
Number of Notice(s) issued: 12 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 19-06-2019 | 0+005 | World Bank team visit | Mukesh Kumar | JE | UDRP R&B Bageshwar | See Pic |
2. | 09-05-2019 | Plant site | Loading of PC material | Mukesh Kumar | JE | UDRP R&B Bageshwar | See Pic |
3. | 09-05-2019 | 12+450 | Rolling over PC surface | Mukesh Kumar | JE | UDRP R&B Bageshwar | See Pic |
4. | 09-05-2019 | Plant site | Loading of PC material | Mukesh Kumar | JE | UDRP R&B Bageshwar | See Pic |
5. | 09-05-2019 | 12+900 | PC laying & rolling | Mukesh Kumar | JE | UDRP R&B Bageshwar | See Pic |
6. | 09-05-2019 | 13+410 | Rolling over seal coat | Mukesh Kumar | JE | UDRP R&B Bageshwar | See Pic |
7. | 09-05-2019 | Plant site | Loading of PC material | Mukesh Kumar | JE | UDRP R&B Bageshwar | See Pic |
8. | 09-05-2019 | Plant site | Loading of Seal coat | Mukesh Kumar | JE | UDRP R&B Bageshwar | See Pic |
9. | 09-05-2019 | 13+825 | Rolling over seal coat | Mukesh Kumar | JE | UDRP R&B Bageshwar | See Pic |
10. | 09-05-2019 | Plant site | Loading Seal coat temperature | Mukesh Kumar | JE | UDRP R&B Bageshwar | See Pic |
11. | 09-05-2019 | Plant site | Loading of Seal coat | Mukesh Kumar | JE | UDRP R&B Bageshwar | See Pic |
12. | 01-05-2019 | 13+350 | Fruits & cold drink distribution on ocassion of international Labour Day | Mukesh Kumar | JE | UDRP R&B Bageshwar | See Pic |
13. | 01-05-2019 | 13+350 | Rolling over PC surface | Mukesh Kumar | JE | UDRP R&B Bageshwar | See Pic |
14. | 01-05-2019 | 13+445 | Rolling over PC surface | Mukesh Kumar | JE | UDRP R&B Bageshwar | See Pic |
15. | 01-05-2019 | Plant site | Loading of PC material | Mukesh Kumar | JE | UDRP R&B Bageshwar | See Pic |
16. | 01-05-2019 | 14+715 | Rolling over PC surface | Mukesh Kumar | JE | UDRP R&B Bageshwar | See Pic |
17. | 01-05-2019 | Plant site | Loading of Seal coat | Mukesh Kumar | JE | UDRP R&B Bageshwar | See Pic |
18. | 01-05-2019 | Plant site | Loading of PC material | Mukesh Kumar | JE | UDRP R&B Bageshwar | See Pic |
19. | 01-05-2019 | 15+000 | PC laying & rolling | Mukesh Kumar | JE | UDRP R&B Bageshwar | See Pic |
20. | 01-05-2019 | 15+450 | Rolling over PC surface | Mukesh Kumar | JE | UDRP R&B Bageshwar | See Pic |
|
|