Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/PWD/08/RD/127 Agreement signed
Project: UDRP-RB Package No.: 143 Package Name: UDRP/PWD/08/RD/127 Sanction Cost: 1095.89  lakhs
District: Bageshwar Block: 0074 Constituency: 46 Circle:
DEA: DEA Bageshwar DSC: Royal Haskoning DHV DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  1143   Katpudiya Chhina Seraghat MR (Ch-0 to 13 Km) (13.000 KM.) (completed)
Procurement:
Package No.: 143        Package Name: UDRP/PWD/08/RD/127        Tender Date: 07-04-2017        Current Status: Agreement signed        Achieved on Date: 14-11-2017

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/08/RD/127        Contractor Name: Tomar Construction Company       
Start Date: 21-11-2017        Intended Completion Date: 07-05-2019        Original End Date:  20-02-2019
Total Bond Cost: 87931448.3 (879.31 lakhs)        Variation Cost: 7392623.24 (73.93 lakhs)     Hence Total Bond Cost is   95324071.54 (953.24 lakhs) 
LD Analysis for Milestone1: calculated LD is Rs 4660396 for 106 days        LD Analysis for Milestone2: calculated LD is Rs 2857790 for 65 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence9.93 KM117.939.93 KM9.93 KM13.41117.93
2.R/Wall, B/ Wall Type Protection works442.00 m46.65442.00 m442.00 m5.3146.65
3.G-23.10 KM53.803.10 KM3.10 KM6.1253.80
4.G-33.10 KM33.293.10 KM3.10 KM3.7933.29
5.PC/CC i/c Prime Coat, Tack Coat15.46 KM170.9915.46 KM15.46 KM19.45170.99
6.Cause Way25.00 No18.9725.00 No25.00 No2.1618.97
7.Culverts/Scupper 30.00 No151.8930.00 No30.00 No17.27151.89
8.longitudinal Drain15455.00 m149.8415455.00 m15455.00 m17.04149.84
9.Crash Barrier2460.00 m29.002460.00 m2460.00 m3.329.00
10.Parapet1700.00 No39.411700.00 No1700.00 No4.4839.41
11.Road Furniture613.00 No8.98613.00 No613.00 No1.028.98
12.Env. Man & Moni Plan1.00 Job6.801.00 Job1.00 Job0.776.80
13.Other Allied Works & Finishing Work 1.00 Job51.781.00 Job1.00 Job5.8951.78
Total Amount: 879.33 100   879.33
Remarks: No Remarks       Work Program Made On: 01-05-2018       Updation of work program on: 22-04-2019      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.08-March-201867.85  lakhs
2.28-April-201836.44  lakhs
3.07-August-201872.21  lakhs
4.01-September-201839.98  lakhs
5.29-September-201850.70  lakhs
6.26-October-201882.76  lakhs
7.02-November-201832.30  lakhs
8.29-November-201866.56  lakhs
9.31-December-201863.82  lakhs
10.15-February-201977.20  lakhs
11.28-February-201912.67  lakhs
12.30-March-201995.10  lakhs
13.16-April-201918.55  lakhs
14.29-April-201987.10  lakhs
15.29-May-201960.92  lakhs
16.31-May-20197.62  lakhs
17.20-June-201963.06  lakhs
18.21-June-20193.00  lakhs
Total 937.84  lakhs
% Payment 98.38 %
Advance Amount:  38.94  lakhs        Recovered Amount:  38.94  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 523     No. of Test Done : 535      No. of Test Passed : 531      No. of Test Failed : 4   Test report of this package
Number of Pics Available on Web Repository: 319
Number of Notice(s) issued: 12

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.19-06-20190+005World Bank team visitMukesh KumarJEUDRP R&B Bageshwar See Pic
2.09-05-2019Plant siteLoading of PC materialMukesh KumarJEUDRP R&B Bageshwar See Pic
3.09-05-201912+450Rolling over PC surfaceMukesh KumarJEUDRP R&B Bageshwar See Pic
4.09-05-2019Plant siteLoading of PC materialMukesh KumarJEUDRP R&B Bageshwar See Pic
5.09-05-201912+900PC laying & rollingMukesh KumarJEUDRP R&B Bageshwar See Pic
6.09-05-201913+410Rolling over seal coatMukesh KumarJEUDRP R&B Bageshwar See Pic
7.09-05-2019Plant siteLoading of PC materialMukesh KumarJEUDRP R&B Bageshwar See Pic
8.09-05-2019Plant siteLoading of Seal coatMukesh KumarJEUDRP R&B Bageshwar See Pic
9.09-05-201913+825Rolling over seal coatMukesh KumarJEUDRP R&B Bageshwar See Pic
10.09-05-2019Plant siteLoading Seal coat temperatureMukesh KumarJEUDRP R&B Bageshwar See Pic
11.09-05-2019Plant siteLoading of Seal coatMukesh KumarJEUDRP R&B Bageshwar See Pic
12.01-05-201913+350Fruits & cold drink distribution on ocassion of international Labour DayMukesh KumarJEUDRP R&B Bageshwar See Pic
13.01-05-201913+350Rolling over PC surfaceMukesh KumarJEUDRP R&B Bageshwar See Pic
14.01-05-201913+445Rolling over PC surfaceMukesh KumarJEUDRP R&B Bageshwar See Pic
15.01-05-2019Plant siteLoading of PC materialMukesh KumarJEUDRP R&B Bageshwar See Pic
16.01-05-201914+715Rolling over PC surfaceMukesh KumarJEUDRP R&B Bageshwar See Pic
17.01-05-2019Plant siteLoading of Seal coatMukesh KumarJEUDRP R&B Bageshwar See Pic
18.01-05-2019Plant siteLoading of PC materialMukesh KumarJEUDRP R&B Bageshwar See Pic
19.01-05-201915+000PC laying & rollingMukesh KumarJEUDRP R&B Bageshwar See Pic
20.01-05-201915+450Rolling over PC surfaceMukesh KumarJEUDRP R&B Bageshwar See Pic