Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/PWD/08/RD/127 Agreement signed
Project: UDRP-RB Package No.: 143 Package Name: UDRP/PWD/08/RD/127 Sanction Cost: 1095.89  lakhs
District: Bageshwar Block: 0074 Constituency: 46 Circle:
DEA: DEA Bageshwar DSC: Royal Haskoning DHV DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  1143   Katpudiya Chhina Seraghat MR (Ch-0 to 13 Km) (13.000 KM.) (in prorgress)
Procurement:
Package No.: 143        Package Name: UDRP/PWD/08/RD/127        Tender Date: 07-04-2017        Current Status: Agreement signed        Achieved on Date: 14-11-2017

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/08/RD/127        Contractor Name: Tomar Construction Company       
Start Date: 21-11-2017        Intended Completion Date: 20-02-2019       
Total Bond Cost: 87931448.3 (879.31 lakhs)       
LD Analysis for Milestone1: calculated LD is Rs 3956940 for 90 days        LD Analysis for Milestone2: 62 days remained       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence9.93 KM117.939.93 KM6.75 KM9.1280.16
2.R/Wall, B/ Wall Type Protection works219.00 m46.65219.00 m152.00 m3.6832.38
3.G-23.80 KM53.803.80 KM1.15 KM1.8516.28
4.G-33.80 KM33.293.80 KM0.00 KM00.00
5.PC/CC i/c Prime Coat, Tack Coat15.46 KM170.9915.46 KM0.00 KM00.00
6.Cause Way4.00 No18.974.00 No2.00 No1.089.48
7.Culverts/Scupper 68.00 No151.8968.00 No21.00 No5.3346.90
8.longitudinal Drain15455.00 m149.8415455.00 m600.00 m0.665.81
9.Crash Barrier1160.00 m29.001160.00 m0.00 m00.00
10.Parapet780.00 No39.41780.00 No0.00 No00.00
11.Road Furniture613.00 No8.98613.00 No1.00 No00.01
12.Env. Man & Moni Plan1.00 Job6.801.00 Job0.00 Job00.00
13.Other Allied Works & Finishing Work 1.00 Job51.781.00 Job0.00 Job00.00
Total Amount: 879.33 21.73   191.02
Remarks: No Remarks       Work Program Made On: 01-05-2018       Updation of work program on: 18-05-2018      
Work Program Status:Work Programme workable.
Financial Progress
SNo. Date Payment
1.08-March-201867.85  lakhs
2.28-April-201836.44  lakhs
Total 104.29  lakhs
% Payment 11.86 %
Advance Amount:  0.00  lakhs        Recovered Amount:  0.00  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 154     No. of Test Done : 162      No. of Test Passed : 158      No. of Test Failed : 4   Test report of this package
Number of Pics Available on Web Repository: 80
Number of Notice(s) issued: 12

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.19-07-2018Ch 5.650EE sir nainital and EE Sir bageshwar inspectionJagdish Narayan MeenaAEUDRP R&B Bageshwar See Pic
2.19-07-2018Ch 5.900Discussion for 3 mtr span culvertJagdish Narayan MeenaAEUDRP R&B Bageshwar See Pic
3.19-07-2018Ch 5.900EE sir nainital and EE sir bageshwar inspectionJagdish Narayan MeenaAEUDRP R&B Bageshwar See Pic
4.19-07-2018Ch 9.550EE sir nainital and EE Sir bageshwar inspectionJagdish Narayan MeenaAEUDRP R&B Bageshwar See Pic
5.19-07-2018Ch 3.625SE sir inspectionJagdish Narayan MeenaAEUDRP R&B Bageshwar See Pic
6.19-07-2018Ch 0.375Slab reinforcementJagdish Narayan MeenaAEUDRP R&B Bageshwar See Pic
7.19-07-2018Ch 2.350Steel Reinforcement for 1 mtr span culvertJagdish Narayan MeenaAEUDRP R&B Bageshwar See Pic
8.07-06-20180.375Before casrting steel in slabHarish ChandraJEUDRP R&B Bageshwar See Pic
9.07-06-20180/12Casting slabHarish ChandraJEUDRP R&B Bageshwar See Pic
10.07-06-20181/2Ecv. Of causewayHarish ChandraJEUDRP R&B Bageshwar See Pic
11.07-06-201813.675Hill cuttingHarish ChandraJEUDRP R&B Bageshwar See Pic
12.07-06-20187/5Scupper Slab castingHarish ChandraJEUDRP R&B Bageshwar See Pic
13.25-05-20185.900Discuss about 3mt. Span culvert with contractorHarish ChandraJEUDRP R&B Bageshwar See Pic
14.25-05-201815.500Lowring workHarish ChandraJEUDRP R&B Bageshwar See Pic
15.25-05-20180.000Starting pointHarish ChandraJEUDRP R&B Bageshwar See Pic
16.25-05-201814.900Cutting/lowring and filling workHarish ChandraJEUDRP R&B Bageshwar See Pic
17.25-05-201814/14Cutting / lowring workHarish ChandraJEUDRP R&B Bageshwar See Pic
18.25-05-2018Health checkup of construction team pkg 127Harish ChandraJEUDRP R&B Bageshwar See Pic
19.25-05-20183.625Dry stone kharanjaHarish ChandraJEUDRP R&B Bageshwar See Pic
20.25-05-20180.475Scupper abutment masonryHarish ChandraJEUDRP R&B Bageshwar See Pic