Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/PWD/08/RD/127 Agreement signed
Project: UDRP-RB Package No.: 143 Package Name: UDRP/PWD/08/RD/127 Sanction Cost: 1095.89  lakhs
District: Bageshwar Block: 0074 Constituency: 46 Circle:
DEA: DEA Bageshwar DSC: Royal Haskoning DHV DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  1143   Katpudiya Chhina Seraghat MR (Ch-0 to 13 Km) (13.000 KM.) (in prorgress)
Procurement:
Package No.: 143        Package Name: UDRP/PWD/08/RD/127        Tender Date: 07-04-2017        Current Status: Agreement signed        Achieved on Date: 14-11-2017

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/08/RD/127        Contractor Name: Tomar Construction Company       
Start Date: 21-11-2017        Intended Completion Date: 20-02-2019       
Total Bond Cost: 87931448.3 (879.31 lakhs)        Variation Cost: 8934643.66 (89.35 lakhs)     Hence Total Bond Cost is   96866091.96 (968.66 lakhs) 
LD Analysis for Milestone1: calculated LD is Rs 4660396 for 106 days        LD Analysis for Milestone2: calculated LD is Rs 2857790 for 65 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence9.93 KM117.939.93 KM9.52 KM12.86113.06
2.R/Wall, B/ Wall Type Protection works219.00 m46.65442.00 m303.00 m3.6431.98
3.G-23.80 KM53.803.10 KM2.75 KM5.4347.72
4.G-33.80 KM33.293.10 KM0.05 KM0.060.54
5.PC/CC i/c Prime Coat, Tack Coat15.46 KM170.9915.46 KM9.75 KM12.26107.84
6.Cause Way4.00 No18.9725.00 No12.00 No1.049.10
7.Culverts/Scupper 68.00 No151.8930.00 No28.00 No16.12141.76
8.longitudinal Drain15455.00 m149.8415455.00 m9275.00 m10.2389.92
9.Crash Barrier1160.00 m29.001160.00 m0.00 m00.00
10.Parapet780.00 No39.411120.00 No650.00 No2.622.87
11.Road Furniture613.00 No8.98613.00 No1.00 No00.01
12.Env. Man & Moni Plan1.00 Job6.801.00 Job1.00 Job0.776.80
13.Other Allied Works & Finishing Work 1.00 Job51.781.00 Job1.00 Job5.8951.78
Total Amount: 879.33 70.89   623.38
Remarks: No Remarks       Work Program Made On: 01-05-2018       Updation of work program on: 20-11-2018      
Work Program Status:Work Programme workable.
Financial Progress
SNo. Date Payment
1.08-March-201867.85  lakhs
2.28-April-201836.44  lakhs
3.07-August-201872.21  lakhs
4.01-September-201839.98  lakhs
5.29-September-201850.70  lakhs
6.26-October-201882.76  lakhs
7.02-November-201832.30  lakhs
8.29-November-201866.56  lakhs
9.31-December-201863.82  lakhs
10.15-February-201977.20  lakhs
Total 589.82  lakhs
% Payment 60.89 %
Advance Amount:  26.95  lakhs        Recovered Amount:  0.00  lakhs        Balance to be Recovered  26.95  lakhs        * Advances are at package level not sub project level
Analysis:Bill should be issued
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 429     No. of Test Done : 441      No. of Test Passed : 437      No. of Test Failed : 4   Test report of this package
Number of Pics Available on Web Repository: 187
Number of Notice(s) issued: 12

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.27-12-20185+900Culvert PCCMukesh KumarJEUDRP R&B Bageshwar See Pic
2.27-12-201815+000DLC of causewayMukesh KumarJEUDRP R&B Bageshwar See Pic
3.27-12-20185+900R/W curingMukesh KumarJEUDRP R&B Bageshwar See Pic
4.27-12-20185+900Layout 3 Mtr span culvertMukesh KumarJEUDRP R&B Bageshwar See Pic
5.23-12-201814+725R/W constructionMukesh KumarJEUDRP R&B Bageshwar See Pic
6.23-12-201815+000Causeway kharanjaMukesh KumarJEUDRP R&B Bageshwar See Pic
7.23-12-201813+775R/w constructionMukesh KumarJEUDRP R&B Bageshwar See Pic
8.23-12-201813+075Village pathMukesh KumarJEUDRP R&B Bageshwar See Pic
9.23-12-201812+275Pucca drain work in progressMukesh KumarJEUDRP R&B Bageshwar See Pic
10.23-12-20182+975DLC of causewayMukesh KumarJEUDRP R&B Bageshwar See Pic
11.23-12-20185+925Toe wall construction for culvertMukesh KumarJEUDRP R&B Bageshwar See Pic
12.23-12-20185+675Causeway toe wall work in progressMukesh KumarJEUDRP R&B Bageshwar See Pic
13.23-12-20182+975Excavation for causewayMukesh KumarJEUDRP R&B Bageshwar See Pic
14.23-12-20185+825Water sample for testMukesh KumarJEUDRP R&B Bageshwar See Pic
15.23-12-201813+525Soil sample for testMukesh KumarJEUDRP R&B Bageshwar See Pic
16.23-12-201813+525Air quality test at siteMukesh KumarJEUDRP R&B Bageshwar See Pic
17.23-12-201813+525Air & Noise level testMukesh KumarJEUDRP R&B Bageshwar See Pic
18.23-12-201813+525Noise level test at siteMukesh KumarJEUDRP R&B Bageshwar See Pic
19.23-12-20186+125Air quality test at siteMukesh KumarJEUDRP R&B Bageshwar See Pic
20.23-12-20186+125Noise test at construction site permissible limitMukesh KumarJEUDRP R&B Bageshwar See Pic