Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/PWD/08/RD/127 Agreement signed
Project: UDRP-RB Package No.: 143 Package Name: UDRP/PWD/08/RD/127 Sanction Cost: 1095.89  lakhs
District: Bageshwar Block: 0074 Constituency: 46 Circle:
DEA: DEA Bageshwar DSC: Royal Haskoning DHV DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  1143   Katpudiya Chhina Seraghat MR (Ch-0 to 13 Km) (13.000 KM.) (in prorgress)
Procurement:
Package No.: 143        Package Name: UDRP/PWD/08/RD/127        Tender Date: 07-04-2017        Current Status: Agreement signed        Achieved on Date: 14-11-2017

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/08/RD/127        Contractor Name: Tomar Construction Company       
Start Date: 21-11-2017        Intended Completion Date: 20-02-2019       
Total Bond Cost: 87931448.3 (879.31 lakhs)        Variation Cost: 8934643.66 (89.35 lakhs)     Hence Total Bond Cost is   96866091.96 (968.66 lakhs) 
LD Analysis for Milestone1: calculated LD is Rs 4660396 for 106 days        LD Analysis for Milestone2: calculated LD is Rs 2550028 for 58 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence9.93 KM117.939.93 KM8.13 KM10.9896.55
2.R/Wall, B/ Wall Type Protection works219.00 m46.65442.00 m239.00 m2.8725.22
3.G-23.80 KM53.803.10 KM2.60 KM5.1345.12
4.G-33.80 KM33.293.10 KM0.05 KM0.060.54
5.PC/CC i/c Prime Coat, Tack Coat15.46 KM170.9915.46 KM5.50 KM6.9260.84
6.Cause Way4.00 No18.9718.00 No5.00 No0.65.27
7.Culverts/Scupper 68.00 No151.8938.00 No27.00 No12.27107.92
8.longitudinal Drain15455.00 m149.8415455.00 m5000.00 m5.5148.47
9.Crash Barrier1160.00 m29.001160.00 m0.00 m00.00
10.Parapet780.00 No39.411120.00 No430.00 No1.7215.13
11.Road Furniture613.00 No8.98613.00 No1.00 No00.01
12.Env. Man & Moni Plan1.00 Job6.801.00 Job1.00 Job0.776.80
13.Other Allied Works & Finishing Work 1.00 Job51.781.00 Job1.00 Job5.8951.78
Total Amount: 879.33 52.73   463.65
Remarks: No Remarks       Work Program Made On: 01-05-2018       Updation of work program on: 18-05-2018      
Work Program Status:Work Programme workable.
Financial Progress
SNo. Date Payment
1.08-March-201867.85  lakhs
2.28-April-201836.44  lakhs
3.07-August-201872.21  lakhs
4.01-September-201839.98  lakhs
5.29-September-201850.70  lakhs
6.26-October-201882.76  lakhs
7.02-November-201832.30  lakhs
Total 382.24  lakhs
% Payment 39.46 %
Advance Amount:  0.00  lakhs        Recovered Amount:  0.00  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Analysis:Bill should be issued
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 310     No. of Test Done : 322      No. of Test Passed : 318      No. of Test Failed : 4   Test report of this package
Number of Pics Available on Web Repository: 154
Number of Notice(s) issued: 12

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.11-11-2018Plant siteLoading of seal coatMukesh KumarJEUDRP R&B Bageshwar See Pic
2.11-11-2018Plant siteLoading of pc materialMukesh KumarJEUDRP R&B Bageshwar See Pic
3.11-11-2018Plant siteBitumen extraction test for PCMukesh KumarJEUDRP R&B Bageshwar See Pic
4.11-11-2018Plant siteLoading of pc materialMukesh KumarJEUDRP R&B Bageshwar See Pic
5.11-11-2018Plant siteLoading of seal coatMukesh KumarJEUDRP R&B Bageshwar See Pic
6.11-11-2018Plant siteBitumen extraction for PCMukesh KumarJEUDRP R&B Bageshwar See Pic
7.11-11-2018Plant siteBitumen extraction test for PCMukesh KumarJEUDRP R&B Bageshwar See Pic
8.11-11-2018Plant siteLoading of PC materialMukesh KumarJEUDRP R&B Bageshwar See Pic
9.11-11-2018Plant siteLoading of pc materialMukesh KumarJEUDRP R&B Bageshwar See Pic
10.11-11-2018Plant siteBitumen extraction test for PCMukesh KumarJEUDRP R&B Bageshwar See Pic
11.11-11-2018Plant siteLoading of seal coatMukesh KumarJEUDRP R&B Bageshwar See Pic
12.11-11-2018Plant siteBitumen extraction for seal coatMukesh KumarJEUDRP R&B Bageshwar See Pic
13.11-11-2018Plant siteGradation for PCMukesh KumarJEUDRP R&B Bageshwar See Pic
14.11-11-2018Plant siteBitumen extraction test for PCMukesh KumarJEUDRP R&B Bageshwar See Pic
15.11-11-2018Plant siteLoading of pc materialMukesh KumarJEUDRP R&B Bageshwar See Pic
16.11-11-2018Plant siteBitumen extraction testMukesh KumarJEUDRP R&B Bageshwar See Pic
17.31-10-2018Ch 3.300PC laying with paverJagdish Narayan MeenaAEUDRP R&B Bageshwar See Pic
18.31-10-2018Ch 3.400Surface after PCJagdish Narayan MeenaAEUDRP R&B Bageshwar See Pic
19.31-10-2018Ch 3.550Surface after seal coatJagdish Narayan MeenaAEUDRP R&B Bageshwar See Pic
20.31-10-2018Ch 3.550Rolling over seal coatJagdish Narayan MeenaAEUDRP R&B Bageshwar See Pic