UDRP/PWD/10/19/RD/014
Agreement signed
|
Project: |
UDRP-RB |
Package No.: |
14 |
Package Name: |
UDRP/PWD/10/19/RD/014 |
Sanction Cost: |
393.54 lakhs |
District: |
Champawat |
Block: |
Champawat |
Constituency: |
Champawat |
Circle: |
Pithoragarh WB Circle |
DEA: |
DEA Champawat |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
only Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 1301 Laiuwapani-Banlekh Motor Road (8.400 KM.) (completed) |
|
Procurement: |
Package No.: 14
Package Name: UDRP/PWD/10/19/RD/014
Tender Date: 01-02-2014
Current Status: Agreement signed
Achieved on Date: 15-05-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/10/19/RD/014
Contractor Name: Panchghati Constructions
|
Start Date: 23-05-2014
Intended Completion Date: 01-11-2015
Original End Date: 22-08-2015
|
Total Bond Cost: 33230845 (332.31 lakhs)
Variation Cost: 2293192.78 (22.93 lakhs) Hence Total Bond Cost is 35524037.78 (355.24 lakhs)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | R/Wall, B/ Wall Type Protection works | 1700.00 m | 39.03 | 1700.00 m | 1700.00 m | 10.99 | 39.03 | 2. | G-2 | 1.96 KM | 5.42 | 1.96 KM | 1.96 KM | 1.53 | 5.42 | 3. | G-3 | 3.40 KM | 9.55 | 3.40 KM | 3.40 KM | 2.69 | 9.55 | 4. | PC/CC i/c Prime Coat, Tack Coat | 8.40 KM | 114.05 | 8.40 KM | 8.40 KM | 32.1 | 114.05 | 5. | Cause Way | 6.00 No | 21.63 | 6.00 No | 6.00 No | 6.09 | 21.63 | 6. | Culverts/Scupper | 49.00 No | 119.08 | 49.00 No | 49.00 No | 33.52 | 119.08 | 7. | longitudinal Drain | 8000.00 m | 19.56 | 8000.00 m | 8000.00 m | 5.51 | 19.56 | 8. | Crash Barrier | 161.30 m | 4.28 | 161.30 m | 161.30 m | 1.2 | 4.28 | 9. | Parapet | 365.00 No | 14.06 | 365.00 No | 365.00 No | 3.96 | 14.06 | 10. | Road Furniture | 124.00 No | 0.61 | 124.00 No | 124.00 No | 0.17 | 0.61 | 11. | Other Allied Works & Finishing Work | 1.00 Job | 7.99 | 1.00 Job | 1.00 Job | 2.25 | 7.99 |
Total Amount: |
355.26 |
|
100 |
355.26 |
|
Remarks:
Lab established, Work of 42 no. Scupper in Progress
Work Program Made On:
23-06-2014
Updation of work program on:
20-11-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 01-October-2014 | 78.88 lakhs |
2. | 31-December-2014 | 25.80 lakhs |
3. | 31-March-2015 | 48.59 lakhs |
4. | 16-June-2015 | 36.00 lakhs |
5. | 30-June-2015 | 54.00 lakhs |
6. | 31-July-2015 | 60.81 lakhs |
7. | 29-September-2015 | 29.41 lakhs |
8. | 31-October-2015 | 11.00 lakhs |
9. | 29-September-2016 | 10.57 lakhs |
Total |
355.06 lakhs |
% Payment |
99.95 % |
|
Advance Amount: 0.00 lakhs
Recovered Amount: 0.00 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 136 |
Number of Notice(s) issued: 57 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 19-05-2016 | 2+000 | World bank mission on site visit | Sanjeev Kumar | JE | UDRP R&B Champawat | See Pic |
2. | 19-05-2016 | 8+400 | World bank mission on site visit | Sanjeev Kumar | JE | UDRP R&B Champawat | See Pic |
3. | 19-05-2016 | 2+020 | World bank mission on site visit | Sanjeev Kumar | JE | UDRP R&B Champawat | See Pic |
4. | 19-05-2016 | 2+020 | World bank mission on site visit | Sanjeev Kumar | JE | UDRP R&B Champawat | See Pic |
5. | 19-05-2016 | 0+015 | World bank mission on site visit | Sanjeev Kumar | JE | UDRP R&B Champawat | See Pic |
6. | 19-05-2016 | 0+000 | World bank mission on site visit | Sanjeev Kumar | JE | UDRP R&B Champawat | See Pic |
7. | 03-02-2016 | 8+400 | Project information Board | Devki Nandan Sharma | RE | DSC4 R&B WB Champawat | See Pic |
8. | 03-02-2016 | 3+800 | Plum Concrete breast walls | Devki Nandan Sharma | RE | DSC4 R&B WB Champawat | See Pic |
9. | 03-02-2016 | 3+800 | W Metal Beam Crash Barriers | Devki Nandan Sharma | RE | DSC4 R&B WB Champawat | See Pic |
10. | 03-02-2016 | 3+720 | Parapet walls | Devki Nandan Sharma | RE | DSC4 R&B WB Champawat | See Pic |
11. | 03-02-2016 | 2+600 | Hectometer Stones | Devki Nandan Sharma | RE | DSC4 R&B WB Champawat | See Pic |
12. | 03-02-2016 | 2+600 | Traffic Signage | Devki Nandan Sharma | RE | DSC4 R&B WB Champawat | See Pic |
13. | 03-02-2016 | 1+000 | BC work above scupper | Devki Nandan Sharma | RE | DSC4 R&B WB Champawat | See Pic |
14. | 03-02-2016 | 1+000 | KM Stones | Devki Nandan Sharma | RE | DSC4 R&B WB Champawat | See Pic |
15. | 03-02-2016 | 1+000 | Traffic Signage | Devki Nandan Sharma | RE | DSC4 R&B WB Champawat | See Pic |
16. | 03-02-2016 | O+750 | BC above | Devki Nandan Sharma | RE | DSC4 R&B WB Champawat | See Pic |
17. | 03-02-2016 | O+750 | Catch Pit | Devki Nandan Sharma | RE | DSC4 R&B WB Champawat | See Pic |
18. | 03-02-2016 | O+750 | Parapet Walls | Devki Nandan Sharma | RE | DSC4 R&B WB Champawat | See Pic |
19. | 03-02-2016 | 0+450 | BC work above Scupper | Devki Nandan Sharma | RE | DSC4 R&B WB Champawat | See Pic |
20. | 03-02-2016 | 0+500 | Traffic Signage | Devki Nandan Sharma | RE | DSC4 R&B WB Champawat | See Pic |
|
|