Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/PWD/07/RD/123 Agreement signed
Project: UDRP-RB Package No.: 139 Package Name: UDRP/PWD/07/RD/123 Sanction Cost: 1312.29  lakhs
District: Pithoragarh Block: Didihat Constituency: Didihat Circle: Pithoragarh WB Circle
DEA: DEA Munsyari DSC: Yongma Engineering Co. Ltd. DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  2311   Charma Jaurasi Lakhatigaon (18.851 KM.) (completed)
Procurement:
Package No.: 139        Package Name: UDRP/PWD/07/RD/123        Tender Date: 07-04-2017        Current Status: Agreement signed        Achieved on Date: 14-11-2017

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/07/RD/123        Contractor Name: Panchghati Construction (JV)       
Start Date: 21-11-2017        Intended Completion Date: 15-06-2019        Original End Date:  22-02-2019
Total Bond Cost: 114682000.5 (1146.82 lakhs)        Variation Cost: 16547030.24 (165.47 lakhs)     Hence Total Bond Cost is   131229030.74 (1312.29 lakhs) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 27064952 for 472 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence18.85 KM104.8618.85 KM18.85 KM7.99104.86
2.R/Wall, B/ Wall Type Protection works2000.00 m267.112000.00 m2000.00 m20.36267.11
3.GSB/RBI/G-10.40 KM12.240.40 KM0.40 KM0.9312.24
4.G-27.23 KM35.567.23 KM7.23 KM2.7135.56
5.G-37.48 KM80.987.48 KM7.48 KM6.1780.98
6.PC/CC i/c Prime Coat, Tack Coat18.85 KM301.7818.85 KM18.85 KM23301.78
7.Cause Way9.00 No61.829.00 No9.00 No4.7161.82
8.Culverts/Scupper 67.00 No268.4567.00 No67.00 No20.46268.45
9.longitudinal Drain18425.00 m90.5018425.00 m18425.00 m6.990.50
10.Crash Barrier0.00 m0.000.00 m0.00 m00.00
11.Parapet1238.00 No42.871238.00 No1238.00 No3.2742.87
12.Road Furniture1082.00 No16.201082.00 No1082.00 No1.2416.20
13.Other Allied Works & Finishing Work 4.00 Job29.944.00 Job4.00 Job2.2829.94
Total Amount: 1312.31 100   1312.31
Remarks: No Remarks       Work Program Made On: 07-01-2018       Updation of work program on: 13-05-2019      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.30-December-201722.10  lakhs
2.16-February-201847.19  lakhs
3.27-February-201883.14  lakhs
4.27-March-201839.12  lakhs
5.23-May-201837.44  lakhs
6.31-August-201847.70  lakhs
7.29-October-201840.72  lakhs
8.27-December-201855.95  lakhs
9.15-February-2019117.72  lakhs
10.28-February-201973.98  lakhs
11.30-March-2019170.03  lakhs
12.30-April-2019142.07  lakhs
13.17-May-201975.62  lakhs
14.31-May-2019104.60  lakhs
15.22-June-201992.55  lakhs
16.30-June-2019136.10  lakhs
Total 1286.03  lakhs
% Payment 98 %
Advance Amount:  0.00  lakhs        Recovered Amount:  0.00  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 64     No. of Test Done : 64      No. of Test Passed : 64      No. of Test Failed : 0   Test report of this package
Number of Pics Available on Web Repository: 98
Number of Notice(s) issued: 12

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.25-05-201916+100PC WORK IN PROGRESS AT CHARMA-JAURASI-LAKHATIGAON MOTOR ROADDeepak Kumar 3JEUDRP R&B Munsyari See Pic
2.17-05-201914+400Culvert slab casting work in progressShoyab AliJEUDRP R&B Munsyari See Pic
3.17-05-201914+400Culvert slab casting work in progressShoyab AliJEUDRP R&B Munsyari See Pic
4.17-05-20199+020K.C. drain excavation work in progressShoyab AliJEUDRP R&B Munsyari See Pic
5.17-05-201914+500Parapet casting work in progressShoyab AliJEUDRP R&B Munsyari See Pic
6.15-05-201913+700Rolling over PC surfaceNeeraj Kumar TewariAEUDRP R&B Munsyari See Pic
7.10-05-201911+210PC work in progress at charma-jaurasi-lakhatigaon motor roadDeepak Kumar 3JEUDRP R&B Munsyari See Pic
8.07-05-201913+000Rolling over seal coatNeeraj Kumar TewariAEUDRP R&B Munsyari See Pic
9.27-04-20199+800PC work in progress at charma-jaurasi-lakhatigaon motor roadDeepak Kumar 3JEUDRP R&B Munsyari See Pic
10.22-04-20190+400PC work in progress at charma-jaurasi-lakhatigaon motor roadDeepak Kumar 3JEUDRP R&B Munsyari See Pic
11.21-04-20192+700PC work in progress at charma-jaurasi-lakhatigaon motor roadDeepak Kumar 3JEUDRP R&B Munsyari See Pic
12.20-04-20192+400Rolling over PC surface.Neeraj Kumar TewariAEUDRP R&B Munsyari See Pic
13.19-04-20191+400Seal coat laying work in progress at charma-jaurasi-lakhatigaon motor roadDeepak Kumar 3JEUDRP R&B Munsyari See Pic
14.12-04-20190+900PC RollingNeeraj Kumar TewariAEUDRP R&B Munsyari See Pic
15.11-04-20190+300Seal coat at charma-jaurasi-lakhatigaon motor roadDeepak Kumar 3JEUDRP R&B Munsyari See Pic
16.08-04-201917+250Ambient air quality monitoring test at charma-jaurasi-lakhatigaon motor roadDeepak Kumar 3JEUDRP R&B Munsyari See Pic
17.08-04-201918+851Ambient noise level test at charma-jaurasi-lakhatigaon motor roadDeepak Kumar 3JEUDRP R&B Munsyari See Pic
18.08-04-20197+100Air noise test at charma-jaurasi-lakhatigaon motor roadDeepak Kumar 3JEUDRP R&B Munsyari See Pic
19.08-04-20195+100Air quality monitoring test monitoring test at charma-jaurasi-lakhatigaon motor roadDeepak Kumar 3JEUDRP R&B Munsyari See Pic
20.03-04-20193+800Seal coat laying work in process at charma-jaurasi-lakhatigaon motor roadDeepak Kumar 3JEUDRP R&B Munsyari See Pic