                            Project:               District:               Package: 

Package Profile Report

UDRP/PWD/07/RD/123 Agreement signed
Project: UDRP-RB Package No.: 139 Package Name: UDRP/PWD/07/RD/123 Sanction Cost: 1312.29  lakhs
District: Pithoragarh Block: Didihat Constituency: Didihat Circle: Pithoragarh WB Circle
DEA: DEA Munsyari DSC: Yongma Engineering Co. Ltd. DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  2311   Charma Jaurasi Lakhatigaon (18.851 KM.) (in prorgress)
Procurement:
Package No.: 139        Package Name: UDRP/PWD/07/RD/123        Tender Date: 07-04-2017        Current Status: Agreement signed        Achieved on Date: 14-11-2017

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/07/RD/123        Contractor Name: Panchghati Construction (JV)       
Start Date: 21-11-2017        Intended Completion Date: 22-02-2019       
Total Bond Cost: 114682000.5 (1146.82 lakhs)       
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 24599289 for 429 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence10.40 KM82.8618.85 KM16.00 KM6.1370.33
2.R/Wall, B/ Wall Type Protection works2000.00 m192.202000.00 m1941.00 m16.26186.53
3.G-27.23 KM106.947.23 KM0.70 KM0.910.35
4.G-37.48 KM60.127.48 KM0.70 KM0.495.63
5.PC/CC i/c Prime Coat, Tack Coat18.85 KM282.6918.85 KM0.00 KM00.00
6.Cause Way9.00 No44.119.00 No6.00 No2.5629.41
7.Culverts/Scupper 65.00 No248.8465.00 No57.00 No19.03218.21
8.longitudinal Drain18425.00 m47.8618425.00 m3000.00 m0.687.79
9.Crash Barrier195.00 m5.85195.00 m0.00 m00.00
10.Parapet1238.00 No37.161238.00 No308.00 No0.819.25
11.Road Furniture1082.00 No16.201082.00 No0.00 No00.00
12.Other Allied Works & Finishing Work 4.00 Job21.974.00 Job0.00 Job00.00
Total Amount: 1146.8 46.87   537.5
Remarks: No Remarks       Work Program Made On: 07-01-2018       Updation of work program on: 12-11-2018      
Work Program Status:Work Programme workable.
Financial Progress
SNo. Date Payment
1.30-December-201722.10  lakhs
2.16-February-201847.19  lakhs
3.27-February-201883.14  lakhs
4.27-March-201839.12  lakhs
5.23-May-201837.44  lakhs
6.31-August-201847.70  lakhs
7.29-October-201840.72  lakhs
8.27-December-201855.95  lakhs
Total 373.36  lakhs
% Payment 32.56 %
Advance Amount:  0.00  lakhs        Recovered Amount:  0.00  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Analysis:Bill should be issued
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 64     No. of Test Done : 64      No. of Test Passed : 64      No. of Test Failed : 0   Test report of this package
Number of Pics Available on Web Repository: 66
Number of Notice(s) issued: 12

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.10-01-20192+400G3 patch rolling workShoyab AliJEUDRP R&B Munsyari See Pic
2.05-01-20195+500 lab siteAIV test for g3 materialDeepak Kumar 3JEUDRP R&B Munsyari See Pic
3.20-12-20186+700Abutment masonary work in progressShoyab AliJEUDRP R&B Munsyari See Pic
4.20-12-20185+600Causeway R/W work in progressShoyab AliJEUDRP R&B Munsyari See Pic
5.20-12-20185+700Parapet curing work in progressShoyab AliJEUDRP R&B Munsyari See Pic
6.20-12-20185+300Drain excavation work in progressShoyab AliJEUDRP R&B Munsyari See Pic
7.20-12-20182+500Cooli wall work in progressShoyab AliJEUDRP R&B Munsyari See Pic
8.20-12-20182+600Scrapping work in progressShoyab AliJEUDRP R&B Munsyari See Pic
9.14-11-20185+200World Bank mission visit at charma-jorasi motor roadDeepak Kumar 3JEUDRP R&B Munsyari See Pic
10.14-11-20180+010World Bank mission visit at charma-jorasi motor roadDeepak Kumar 3JEUDRP R&B Munsyari See Pic
11.14-11-20188+400Kachha drain work on process at charma-jorasi motor roadDeepak Kumar 3JEUDRP R&B Munsyari See Pic
12.10-11-201813+400Site visit by DPM sir.Neeraj Kumar TewariAEUDRP R&B Munsyari See Pic
13.31-10-2018Ch-8+300Kutcha drain work on process at charma-jorasi motor roadDeepak Kumar 3JEUDRP R&B Munsyari See Pic
14.31-10-201818+850SE sir,AE sir visit at charma-jorasi motor roadDeepak Kumar 3JEUDRP R&B Munsyari See Pic
15.12-10-2018Ch-7+710Kacha drain work on progress at charma-jorasi motor roadDeepak Kumar 3JEUDRP R&B Munsyari See Pic
16.06-04-201814+450Site visit Se sir EE sir Re sirAnmol MadanSite EngineerDSC4 R&B WB Munsyari See Pic
17.05-04-201818+450Checking of information boardDinesh KumarREDSC4 R&B WB Munsyari See Pic
18.05-04-2018LabChecking of labDinesh KumarREDSC4 R&B WB Munsyari See Pic
19.05-04-20180+00Site visit by SE Sir EE Sir and AE SirDinesh KumarREDSC4 R&B WB Munsyari See Pic
20.29-03-201816+420Slab casting work in progressAnmol MadanSite EngineerDSC4 R&B WB Munsyari See Pic