Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/PWD/07/RD/123 Agreement signed
Project: UDRP-RB Package No.: 139 Package Name: UDRP/PWD/07/RD/123 Sanction Cost: 1144.63  lakhs
District: Pithoragarh Block: Didihat Constituency: Didihat Circle: Pithoragarh WB Circle
DEA: DEA Munsyari DSC: Yongma Engineering Co. Ltd. DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  2311   Charma Jaurasi Lakhatigaon (18.851 KM.) (in prorgress)
Procurement:
Package No.: 139        Package Name: UDRP/PWD/07/RD/123        Tender Date: 07-04-2017        Current Status: Agreement signed        Achieved on Date: 14-11-2017

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/07/RD/123        Contractor Name: Panchghati Construction (JV)       
Start Date: 21-11-2017        Intended Completion Date: 22-02-2019       
Total Bond Cost: 114682000.5 (1146.82 lakhs)       
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 9002537 for 157 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence18.85 KM82.8618.85 KM16.00 KM6.1370.33
2.R/Wall, B/ Wall Type Protection works2891.00 m192.202891.00 m850.00 m4.9356.51
3.G-27.23 KM106.947.23 KM0.00 KM00.00
4.G-37.48 KM60.127.48 KM0.00 KM00.00
5.PC/CC i/c Prime Coat, Tack Coat18.86 KM282.5918.86 KM0.00 KM00.00
6.Cause Way9.00 No44.119.00 No0.00 No00.00
7.Culverts/Scupper 75.00 No248.8475.00 No31.00 No8.97102.85
8.longitudinal Drain18425.00 m47.8618425.00 m0.00 m00.00
9.Crash Barrier195.00 m5.85195.00 m0.00 m00.00
10.Parapet1238.00 No37.161238.00 No0.00 No00.00
11.Road Furniture1032.00 No16.201032.00 No0.00 No00.00
12.Other Allied Works & Finishing Work 4.00 Job21.974.00 Job0.00 Job00.00
Total Amount: 1146.7 20.03   229.69
Remarks: No Remarks       Work Program Made On: 07-01-2018       Updation of work program on: 07-01-2018      
Work Program Status:Work Programme workable.
Financial Progress
SNo. Date Payment
1.30-December-201722.10  lakhs
2.16-February-201847.19  lakhs
3.27-February-201883.14  lakhs
4.27-March-201839.12  lakhs
Total 191.55  lakhs
% Payment 16.7 %
Advance Amount:  0.00  lakhs        Recovered Amount:  0.00  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Environment & Social Compliances(Package level): labour licence
Environment & Social Compliances(Sub Project level):
Charma Jaurasi Lakhatigaon (2311)No Pending Issue
Detailed report of this Package
Quality
No. of Test Required : 25     No. of Test Done : 25      No. of Test Passed : 25      No. of Test Failed : 0   Test report of this package
Number of Pics Available on Web Repository: 51
Number of Notice(s) issued: 11

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.06-04-201814+450Site visit Se sir EE sir Re sirAnmol MadanSite EngineerDSC4 R&B WB Munsyari See Pic
2.05-04-201818+450Checking of information boardDinesh KumarREDSC4 R&B WB Munsyari See Pic
3.05-04-2018LabChecking of labDinesh KumarREDSC4 R&B WB Munsyari See Pic
4.05-04-20180+00Site visit by SE Sir EE Sir and AE SirDinesh KumarREDSC4 R&B WB Munsyari See Pic
5.29-03-201816+420Slab casting work in progressAnmol MadanSite EngineerDSC4 R&B WB Munsyari See Pic
6.29-03-201816+600Slab casting work in progressAnmol MadanSite EngineerDSC4 R&B WB Munsyari See Pic
7.29-03-201816+720Slab casting work in progressAnmol MadanSite EngineerDSC4 R&B WB Munsyari See Pic
8.20-03-201818+450Noice pollution testAnmol MadanSite EngineerDSC4 R&B WB Munsyari See Pic
9.20-03-201818+450Soil sample collectAnmol MadanSite EngineerDSC4 R&B WB Munsyari See Pic
10.20-03-201816+680Water sample collectAnmol MadanSite EngineerDSC4 R&B WB Munsyari See Pic
11.20-03-2018Water sample collect12+750Anmol MadanSite EngineerDSC4 R&B WB Munsyari See Pic
12.20-03-201812-750Soil sample collectAnmol MadanSite EngineerDSC4 R&B WB Munsyari See Pic
13.20-03-2018Noice pollution test0+000Anmol MadanSite EngineerDSC4 R&B WB Munsyari See Pic
14.20-03-20185+200Ambient air testAnmol MadanSite EngineerDSC4 R&B WB Munsyari See Pic
15.06-03-20185+980Excavation of culvert in work progressAnmol MadanSite EngineerDSC4 R&B WB Munsyari See Pic
16.17-02-201816+420Slab casting M25Dinesh KumarREDSC4 R&B WB Munsyari See Pic
17.17-02-2018Lab28 days cube testing for M25Dinesh KumarREDSC4 R&B WB Munsyari See Pic
18.17-02-2018Slab casting in progress16+600Anmol MadanSite EngineerDSC4 R&B WB Munsyari See Pic
19.11-02-2018Slab casting in progress7+225Anmol MadanSite EngineerDSC4 R&B WB Munsyari See Pic
20.11-02-2018Slab casting in progress7+135Anmol MadanSite EngineerDSC4 R&B WB Munsyari See Pic