Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/PWD/07/RD/121 Agreement signed
Project: UDRP-RB Package No.: 137 Package Name: UDRP/PWD/07/RD/121 Sanction Cost: 1247.88  lakhs
District: Pithoragarh Block: Munakot Constituency: Didihat Circle: Pithoragarh WB Circle
DEA: DEA Askot DSC: Yongma Engineering Co. Ltd. DSC Scope: Design and Supervision No.of Sub project : 3
Subproject in this package
1  2357   Nainipatal Madmaley MR (Ch-7 to 13.162 Km) (6.162 KM.) (completed)
2  2390   Madmalne Bhotad MR (3.249 KM.) (completed)
3  2392   Madmanya katpatia MR (10.000 KM.) (completed)
Procurement:
Package No.: 137        Package Name: UDRP/PWD/07/RD/121        Tender Date: 07-04-2017        Current Status: Agreement signed        Achieved on Date: 14-11-2017

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/07/RD/121        Contractor Name: R.G. Buildwell.       
Start Date: 21-11-2017        Intended Completion Date: 25-06-2019        Original End Date:  20-02-2019
Total Bond Cost: 108587704.9 (1085.88 lakhs)        Variation Cost: 11680523.77 (116.81 lakhs)     Hence Total Bond Cost is   120268228.67 (1202.68 lakhs) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 23074950 for 425 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence14.69 KM248.9514.69 KM14.69 KM20.85248.95
2.R/Wall, B/ Wall Type Protection works3223.00 m212.292546.00 m2546.00 m16.86212.29
3.G-212.85 KM85.5512.85 KM12.85 KM6.5785.55
4.G-314.60 KM82.7214.60 KM14.60 KM6.8382.72
5.PC/CC i/c Prime Coat, Tack Coat19.51 KM215.0219.51 KM19.51 KM18.53215.02
6.Cause Way16.00 No65.5413.00 No13.00 No5.6165.54
7.Culverts/Scupper 29.00 No100.5632.00 No32.00 No8.41100.56
8.longitudinal Drain19326.00 m23.1619326.00 m19326.00 m1.9123.16
9.Crash Barrier793.00 m22.73793.00 m793.00 m1.9722.73
10.Parapet1335.00 No41.331335.00 No1335.00 No3.6441.33
11.Road Furniture1380.00 No16.271380.00 No1380.00 No1.4116.27
12.Other Allied Works & Finishing Work 3.00 Job88.553.00 Job3.00 Job7.488.55
Total Amount: 1202.67 100   1202.67
Remarks: No Remarks       Work Program Made On: 04-01-2018       Updation of work program on: 22-05-2019      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.30-December-201714.58  lakhs
2.16-February-201892.38  lakhs
3.26-February-201823.30  lakhs
4.28-March-2018124.07  lakhs
5.23-May-201826.03  lakhs
6.30-June-201824.21  lakhs
7.08-August-201819.00  lakhs
8.25-September-201882.44  lakhs
9.21-December-201842.11  lakhs
10.31-December-201823.25  lakhs
11.19-January-2019105.63  lakhs
12.13-February-201975.60  lakhs
13.25-February-201942.61  lakhs
14.30-March-201947.90  lakhs
15.17-May-201954.48  lakhs
16.31-May-201960.20  lakhs
17.18-June-201948.84  lakhs
18.29-June-2019111.03  lakhs
19.20-April-201929.40  lakhs
20.30-April-201994.01  lakhs
Total 1141.07  lakhs
% Payment 94.88 %
Advance Amount:  0.00  lakhs        Recovered Amount:  0.00  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 266     No. of Test Done : 266      No. of Test Passed : 266      No. of Test Failed : 0   Test report of this package
Number of Pics Available on Web Repository: 80
Number of Notice(s) issued: 12

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.03-05-20190+500Rolling over PC workTej Singh KunwarJEUDRP R&B Askot See Pic
2.29-04-20191+025PC work on progressTej Singh KunwarJEUDRP R&B Askot See Pic
3.29-04-20190+950PC work progress , E.E.sir checkingTej Singh KunwarJEUDRP R&B Askot See Pic
4.28-04-2019Ch 1+900PC work in progressTej Singh KunwarJEUDRP R&B Askot See Pic
5.12-04-20192+875PC work progressTej Singh KunwarJEUDRP R&B Askot See Pic
6.12-04-20192+600Rolling over seal coatTej Singh KunwarJEUDRP R&B Askot See Pic
7.03-04-20191+900Cube mould filling for strength testTej Singh KunwarJEUDRP R&B Askot See Pic
8.03-04-20193+250Water sprinkaling over G-3 layerTej Singh KunwarJEUDRP R&B Askot See Pic
9.30-03-20192+425Causway Top layer casting workTej Singh KunwarJEUDRP R&B Askot See Pic
10.24-03-201911+950PC work in progressTej Singh KunwarJEUDRP R&B Askot See Pic
11.24-03-20191+800Protection work progressTej Singh KunwarJEUDRP R&B Askot See Pic
12.24-03-20192+950Rolling over G-3 layerTej Singh KunwarJEUDRP R&B Askot See Pic
13.24-03-2019Ch.1+100Filling of concrete cubes for strength testTej Singh KunwarJEUDRP R&B Askot See Pic
14.24-03-2019Ch.1+100C/way top layer casting workTej Singh KunwarJEUDRP R&B Askot See Pic
15.24-03-20198+200Rolling work progress over seal coatTej Singh KunwarJEUDRP R&B Askot See Pic
16.23-03-20197+475SE ,WB PWD vizit at pakage 121Tej Singh KunwarJEUDRP R&B Askot See Pic
17.01-02-2019Ch-7+000Snow fall at pakage 121Tej Singh KunwarJEUDRP R&B Askot See Pic
18.01-02-201911+400CME PIU site vizitTej Singh KunwarJEUDRP R&B Askot See Pic
19.31-12-2018Ch.2+800SE sir inspactionTej Singh KunwarJEUDRP R&B Askot See Pic
20.28-12-201812+700PC work on progressTej Singh KunwarJEUDRP R&B Askot See Pic