UDRP/PWD/07/RD/121
Agreement signed
|
Project: |
UDRP-RB |
Package No.: |
137 |
Package Name: |
UDRP/PWD/07/RD/121 |
Sanction Cost: |
1247.88 lakhs |
District: |
Pithoragarh |
Block: |
Munakot |
Constituency: |
Didihat |
Circle: |
Pithoragarh WB Circle |
DEA: |
DEA Askot |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
Design and Supervision |
No.of Sub project : |
3 |
Subproject in this package |
1 2357 Nainipatal Madmaley MR (Ch-7 to 13.162 Km) (6.162 KM.) (completed) | 2 2390 Madmalne Bhotad MR (3.249 KM.) (completed) | 3 2392 Madmanya katpatia MR (10.000 KM.) (completed) |
|
Procurement: |
Package No.: 137
Package Name: UDRP/PWD/07/RD/121
Tender Date: 07-04-2017
Current Status: Agreement signed
Achieved on Date: 14-11-2017 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/07/RD/121
Contractor Name: R.G. Buildwell.
|
Start Date: 21-11-2017
Intended Completion Date: 25-06-2019
Original End Date: 20-02-2019
|
Total Bond Cost: 108587704.9 (1085.88 lakhs)
Variation Cost: 11680523.77 (116.81 lakhs) Hence Total Bond Cost is 120268228.67 (1202.68 lakhs)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: calculated LD is Rs 23074950 for 425 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Hill side Cutting & Slip clearence | 14.69 KM | 248.95 | 14.69 KM | 14.69 KM | 20.85 | 248.95 | 2. | R/Wall, B/ Wall Type Protection works | 3223.00 m | 212.29 | 2546.00 m | 2546.00 m | 16.86 | 212.29 | 3. | G-2 | 12.85 KM | 85.55 | 12.85 KM | 12.85 KM | 6.57 | 85.55 | 4. | G-3 | 14.60 KM | 82.72 | 14.60 KM | 14.60 KM | 6.83 | 82.72 | 5. | PC/CC i/c Prime Coat, Tack Coat | 19.51 KM | 215.02 | 19.51 KM | 19.51 KM | 18.53 | 215.02 | 6. | Cause Way | 16.00 No | 65.54 | 13.00 No | 13.00 No | 5.61 | 65.54 | 7. | Culverts/Scupper | 29.00 No | 100.56 | 32.00 No | 32.00 No | 8.41 | 100.56 | 8. | longitudinal Drain | 19326.00 m | 23.16 | 19326.00 m | 19326.00 m | 1.91 | 23.16 | 9. | Crash Barrier | 793.00 m | 22.73 | 793.00 m | 793.00 m | 1.97 | 22.73 | 10. | Parapet | 1335.00 No | 41.33 | 1335.00 No | 1335.00 No | 3.64 | 41.33 | 11. | Road Furniture | 1380.00 No | 16.27 | 1380.00 No | 1380.00 No | 1.41 | 16.27 | 12. | Other Allied Works & Finishing Work | 3.00 Job | 88.55 | 3.00 Job | 3.00 Job | 7.4 | 88.55 |
Total Amount: |
1202.67 |
|
100 |
1202.67 |
|
Remarks:
No Remarks
Work Program Made On:
04-01-2018
Updation of work program on:
22-05-2019
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 30-December-2017 | 14.58 lakhs |
2. | 16-February-2018 | 92.38 lakhs |
3. | 26-February-2018 | 23.30 lakhs |
4. | 28-March-2018 | 124.07 lakhs |
5. | 23-May-2018 | 26.03 lakhs |
6. | 30-June-2018 | 24.21 lakhs |
7. | 08-August-2018 | 19.00 lakhs |
8. | 25-September-2018 | 82.44 lakhs |
9. | 21-December-2018 | 42.11 lakhs |
10. | 31-December-2018 | 23.25 lakhs |
11. | 19-January-2019 | 105.63 lakhs |
12. | 13-February-2019 | 75.60 lakhs |
13. | 25-February-2019 | 42.61 lakhs |
14. | 30-March-2019 | 47.90 lakhs |
15. | 17-May-2019 | 54.48 lakhs |
16. | 31-May-2019 | 60.20 lakhs |
17. | 18-June-2019 | 48.84 lakhs |
18. | 29-June-2019 | 111.03 lakhs |
19. | 20-April-2019 | 29.40 lakhs |
20. | 30-April-2019 | 94.01 lakhs |
Total |
1141.07 lakhs |
% Payment |
94.88 % |
|
Advance Amount: 0.00 lakhs
Recovered Amount: 0.00 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 80 |
Number of Notice(s) issued: 12 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 03-05-2019 | 0+500 | Rolling over PC work | Tej Singh Kunwar | JE | UDRP R&B Askot | See Pic |
2. | 29-04-2019 | 1+025 | PC work on progress | Tej Singh Kunwar | JE | UDRP R&B Askot | See Pic |
3. | 29-04-2019 | 0+950 | PC work progress , E.E.sir checking | Tej Singh Kunwar | JE | UDRP R&B Askot | See Pic |
4. | 28-04-2019 | Ch 1+900 | PC work in progress | Tej Singh Kunwar | JE | UDRP R&B Askot | See Pic |
5. | 12-04-2019 | 2+875 | PC work progress | Tej Singh Kunwar | JE | UDRP R&B Askot | See Pic |
6. | 12-04-2019 | 2+600 | Rolling over seal coat | Tej Singh Kunwar | JE | UDRP R&B Askot | See Pic |
7. | 03-04-2019 | 1+900 | Cube mould filling for strength test | Tej Singh Kunwar | JE | UDRP R&B Askot | See Pic |
8. | 03-04-2019 | 3+250 | Water sprinkaling over G-3 layer | Tej Singh Kunwar | JE | UDRP R&B Askot | See Pic |
9. | 30-03-2019 | 2+425 | Causway Top layer casting work | Tej Singh Kunwar | JE | UDRP R&B Askot | See Pic |
10. | 24-03-2019 | 11+950 | PC work in progress | Tej Singh Kunwar | JE | UDRP R&B Askot | See Pic |
11. | 24-03-2019 | 1+800 | Protection work progress | Tej Singh Kunwar | JE | UDRP R&B Askot | See Pic |
12. | 24-03-2019 | 2+950 | Rolling over G-3 layer | Tej Singh Kunwar | JE | UDRP R&B Askot | See Pic |
13. | 24-03-2019 | Ch.1+100 | Filling of concrete cubes for strength test | Tej Singh Kunwar | JE | UDRP R&B Askot | See Pic |
14. | 24-03-2019 | Ch.1+100 | C/way top layer casting work | Tej Singh Kunwar | JE | UDRP R&B Askot | See Pic |
15. | 24-03-2019 | 8+200 | Rolling work progress over seal coat | Tej Singh Kunwar | JE | UDRP R&B Askot | See Pic |
16. | 23-03-2019 | 7+475 | SE ,WB PWD vizit at pakage 121 | Tej Singh Kunwar | JE | UDRP R&B Askot | See Pic |
17. | 01-02-2019 | Ch-7+000 | Snow fall at pakage 121 | Tej Singh Kunwar | JE | UDRP R&B Askot | See Pic |
18. | 01-02-2019 | 11+400 | CME PIU site vizit | Tej Singh Kunwar | JE | UDRP R&B Askot | See Pic |
19. | 31-12-2018 | Ch.2+800 | SE sir inspaction | Tej Singh Kunwar | JE | UDRP R&B Askot | See Pic |
20. | 28-12-2018 | 12+700 | PC work on progress | Tej Singh Kunwar | JE | UDRP R&B Askot | See Pic |
|
|