Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/PWD/07/RD/121 Agreement signed
Project: UDRP-RB Package No.: 137 Package Name: UDRP/PWD/07/RD/121 Sanction Cost: 1247.88  lakhs
District: Pithoragarh Block: Munakot Constituency: Didihat Circle: Pithoragarh WB Circle
DEA: DEA Askot DSC: Yongma Engineering Co. Ltd. DSC Scope: Design and Supervision No.of Sub project : 3
Subproject in this package
1  2357   Nainipatal Madmaley MR (Ch-7 to 13.162 Km) (6.162 KM.) (in prorgress)
2  2390   Madmalne Bhotad MR (3.249 KM.) (in prorgress)
3  2392   Madmanya katpatia MR (10.000 KM.) (in prorgress)
Procurement:
Package No.: 137        Package Name: UDRP/PWD/07/RD/121        Tender Date: 07-04-2017        Current Status: Agreement signed        Achieved on Date: 14-11-2017

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/07/RD/121        Contractor Name: R.G. Buildwell.       
Start Date: 21-11-2017        Intended Completion Date: 20-02-2019       
Total Bond Cost: 108587704.9 (1085.88 lakhs)        Variation Cost: 11680523.77 (116.81 lakhs)     Hence Total Bond Cost is   120268228.67 (1202.68 lakhs) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 23074950 for 425 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence14.69 KM238.7914.69 KM14.69 KM21.99238.79
2.R/Wall, B/ Wall Type Protection works2943.00 m174.002246.00 m1690.00 m12.03130.63
3.G-212.85 KM68.7612.85 KM2.80 KM1.4816.11
4.G-314.50 KM82.1214.50 KM1.00 KM0.485.18
5.PC/CC i/c Prime Coat, Tack Coat19.41 KM213.9019.41 KM5.00 KM5.1155.54
6.Cause Way13.00 No52.9713.00 No3.00 No1.0611.46
7.Culverts/Scupper 30.00 No98.4629.00 No16.00 No5.0855.11
8.longitudinal Drain19326.00 m23.4519326.00 m11600.00 m1.4415.62
9.Crash Barrier793.00 m22.73793.00 m0.00 m00.00
10.Parapet1335.00 No41.331335.00 No0.00 No00.00
11.Road Furniture1380.00 No16.271380.00 No0.00 No00.00
12.Other Allied Works & Finishing Work 3.00 Job53.093.00 Job0.20 Job0.262.81
Total Amount: 1085.87 48.92   531.25
Remarks: No Remarks       Work Program Made On: 04-01-2018       Updation of work program on: 31-05-2018      
Work Program Status:This Package contain more than one subproject,pleae check individua subproject for Program Expired.
Financial Progress
SNo. Date Payment
1.30-December-201714.58  lakhs
2.16-February-201892.38  lakhs
3.26-February-201823.30  lakhs
4.28-March-2018124.07  lakhs
5.23-May-201826.03  lakhs
6.30-June-201824.21  lakhs
7.08-August-201819.00  lakhs
8.25-September-201882.44  lakhs
9.21-December-201842.11  lakhs
10.31-December-201823.25  lakhs
11.19-January-2019105.63  lakhs
Total 577  lakhs
% Payment 47.98 %
Advance Amount:  0.00  lakhs        Recovered Amount:  0.00  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 201     No. of Test Done : 201      No. of Test Passed : 201      No. of Test Failed : 0   Test report of this package
Number of Pics Available on Web Repository: 64
Number of Notice(s) issued: 12

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.01-02-2019Ch-7+000Snow fall at pakage 121Tej Singh KunwarJEUDRP R&B Askot See Pic
2.01-02-201911+400CME PIU site vizitTej Singh KunwarJEUDRP R&B Askot See Pic
3.31-12-2018Ch.2+800SE sir inspactionTej Singh KunwarJEUDRP R&B Askot See Pic
4.28-12-201812+700PC work on progressTej Singh KunwarJEUDRP R&B Askot See Pic
5.26-09-2018Ch-8+850Construction of wing wallTej Singh KunwarJEUDRP R&B Askot See Pic
6.30-08-2018Ch.12+400Casting of culvert slabTej Singh KunwarJEUDRP R&B Askot See Pic
7.30-08-201812+6751m span slab casting workTej Singh KunwarJEUDRP R&B Askot See Pic
8.18-08-20181+200slip dew to SRMDTej Singh KunwarJEUDRP R&B Askot See Pic
9.18-08-20181+350Slip over Road dew to SRMDTej Singh KunwarJEUDRP R&B Askot See Pic
10.18-08-20181+000Slip & boulder Over road dew to SRMDTej Singh KunwarJEUDRP R&B Askot See Pic
11.18-08-20180+950Skip & boulder cleaningTej Singh KunwarJEUDRP R&B Askot See Pic
12.18-08-20180+950Road opening SRMD 2018-19Arun Kumar PandeyEEUDRP R&B Askot See Pic
13.18-08-20181+550mSlip under SRMDArun Kumar PandeyEEUDRP R&B Askot See Pic
14.04-08-2018Ch.9+975Construction schedule informatory BoardTej Singh KunwarJEUDRP R&B Askot See Pic
15.04-08-2018Ch.4+850Construction schedule BoardTej Singh KunwarJEUDRP R&B Askot See Pic
16.04-08-2018Ch.1+450Construction scheduleTej Singh KunwarJEUDRP R&B Askot See Pic
17.20-06-201813.050Aggregate impact value checkingTej Singh KunwarJEUDRP R&B Askot See Pic
18.20-06-2018Ch.8+850H.P.stone filling work in back of culvert abutmentsTej Singh KunwarJEUDRP R&B Askot See Pic
19.20-06-2018Ch.2+275Breast wall construction work in progressTej Singh KunwarJEUDRP R&B Askot See Pic
20.28-05-2018Ch 8.425Construction of culvert in progressSatendra Mohan UpadhyayAEUDRP R&B Askot See Pic