Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/PWD/07/RD/120 Agreement signed
Project: UDRP-RB Package No.: 136 Package Name: UDRP/PWD/07/RD/120 Sanction Cost: 1220.10  lakhs
District: Pithoragarh Block: Gangolihat Constituency: Gangolihat Circle: Pithoragarh WB Circle
DEA: DEA Munsyari DSC: Yongma Engineering Co. Ltd. DSC Scope: only Supervision No.of Sub project : 1
Subproject in this package
1  2331   Kunalta motor road (10.500 KM.) (completed)
Procurement:
Package No.: 136        Package Name: UDRP/PWD/07/RD/120        Tender Date: 07-04-2017        Current Status: Agreement signed        Achieved on Date: 14-11-2017

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/07/RD/120        Contractor Name: Dinesh Chandra Patni       
Start Date: 21-11-2017        Intended Completion Date: 15-06-2019        Original End Date:  20-02-2019
Total Bond Cost: 103717243.78 (1037.17 lakhs)        Variation Cost: 17501106.75 (175.01 lakhs)     Hence Total Bond Cost is   121218350.53 (1212.18 lakhs) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 11305262 for 218 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence10.18 KM92.5210.18 KM10.18 KM7.6392.52
2.R/Wall, B/ Wall Type Protection works2749.00 m327.672749.00 m2749.00 m27.03327.67
3.G-220.36 KM173.4220.36 KM20.36 KM14.31173.42
4.G-310.18 KM97.7510.18 KM10.18 KM8.0697.75
5.PC/CC i/c Prime Coat, Tack Coat10.18 KM133.3510.18 KM10.18 KM11133.35
6.Cause Way16.00 No75.9016.00 No16.00 No6.2675.90
7.Culverts/Scupper 52.00 No201.2652.00 No52.00 No16.6201.26
8.longitudinal Drain10500.00 m23.5810180.00 m10180.00 m1.9523.58
9.Crash Barrier0.00 m0.000.00 m0.00 m00.00
10.Parapet681.00 No25.12681.00 No681.00 No2.0725.12
11.Road Furniture750.00 No12.83750.00 No750.00 No1.0612.83
12.Other Allied Works & Finishing Work 4.00 Job48.784.00 Job4.00 Job4.0248.78
Total Amount: 1212.18 100   1212.18
Remarks: No Remarks       Work Program Made On: 06-01-2018       Updation of work program on: 13-05-2019      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.30-December-201740.43  lakhs
2.16-February-2018106.33  lakhs
3.01-March-201891.66  lakhs
4.27-March-201897.83  lakhs
5.23-May-201877.93  lakhs
6.30-May-201886.18  lakhs
7.07-August-201859.94  lakhs
8.29-September-201887.85  lakhs
9.29-October-201864.74  lakhs
10.30-November-201855.07  lakhs
11.27-December-201879.27  lakhs
12.21-January-201987.73  lakhs
13.15-February-201929.74  lakhs
14.30-March-201928.17  lakhs
15.17-May-201985.65  lakhs
16.12-June-201952.67  lakhs
17.30-June-201936.99  lakhs
Total 1168.18  lakhs
% Payment 96.37 %
Advance Amount:  0.00  lakhs        Recovered Amount:  0.00  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 99     No. of Test Done : 101      No. of Test Passed : 99      No. of Test Failed : 2   Test report of this package
Number of Pics Available on Web Repository: 27
Number of Notice(s) issued: 12

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.18-05-2019At plant siteBitumin extraction at plant sitePrem PrakashAEUDRP R&B Munsyari See Pic
2.18-05-2019At plant siteBitumin extraction test at plantPrem PrakashAEUDRP R&B Munsyari See Pic
3.18-05-2019Ch 0.850PC laying work in progressPrem PrakashAEUDRP R&B Munsyari See Pic
4.17-05-20191+800P.C. laying work in progressShoyab AliJEUDRP R&B Munsyari See Pic
5.08-05-20196+350P.C. laying work in progressShoyab AliJEUDRP R&B Munsyari See Pic
6.12-11-2018Chainage 2.700Water sprinkling in progressPrem PrakashAEUDRP R&B Munsyari See Pic
7.12-10-2018Chainage 6.550G3 laying in progressPrem PrakashAEUDRP R&B Munsyari See Pic
8.04-04-20182+100Thickness checking of G2 materialDinesh KumarREDSC4 R&B WB Munsyari See Pic
9.04-04-20180+00Site visit by SE Sir EE Sir and AE sir.Dinesh KumarREDSC4 R&B WB Munsyari See Pic
10.22-03-20182+375Thickness checking of G2 layer found 150 mmDinesh KumarREDSC4 R&B WB Munsyari See Pic
11.22-03-20181+985Loose thickness checking of G2 material found120 mm.Dinesh KumarREDSC4 R&B WB Munsyari See Pic
12.22-03-2018LabLab checking by CME SirDinesh KumarREDSC4 R&B WB Munsyari See Pic
13.23-02-2018In labGrading of G2 materialDinesh KumarREDSC4 R&B WB Munsyari See Pic
14.06-02-2018Aiv testing in labAiv testing for G2 material result found 12.68 ,20.0, and 27.78.Dinesh KumarREDSC4 R&B WB Munsyari See Pic
15.06-02-2018LabAiv testing in lab for G2 materialDinesh KumarREDSC4 R&B WB Munsyari See Pic
16.20-01-20188.450Hillside cutting work in progressPramod JoshiSite EngineerDSC4 R&B WB Munsyari See Pic
17.09-01-20188.100Hillside cutting work in progressPramod JoshiSite EngineerDSC4 R&B WB Munsyari See Pic
18.05-01-20187+900Hill cutting in progress cutting with rock breakerDinesh KumarREDSC4 R&B WB Munsyari See Pic
19.31-12-20177.725Hillside cutting work in progressPramod JoshiSite EngineerDSC4 R&B WB Munsyari See Pic
20.26-12-20170+785Construction of culvert Abutment in progressDinesh KumarREDSC4 R&B WB Munsyari See Pic