Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/PWD/06/67/RD/050(N) Agreement signed
Project: UDRP-RB Package No.: 132 Package Name: UDRP/PWD/06/67/RD/050(N) Sanction Cost: 568.32  lakhs
District: Pauri Block: Dogadda Constituency: Kotdwar Circle: Tehri WB Circle
DEA: DEA Pauri DSC: Egis International DSC Scope: only Supervision No.of Sub project : 2
Subproject in this package
1  2108   Kotdwar-Pulinda motor road (12.000 KM.) (completed)
2  2271   Badiyu-jhakhanoli kunkuli MR (10.000 KM.) (completed)
Procurement:
Package No.: 132        Package Name: UDRP/PWD/06/67/RD/050(N)        Tender Date: 15-12-2016        Current Status: Agreement signed        Achieved on Date: 04-05-2017

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/06/67/RD/050(N)        Contractor Name: SRS Promoters       
Start Date: 11-05-2017        Intended Completion Date: 31-12-2018        Original End Date:  10-02-2018
Total Bond Cost: 28432575.93 (284.33 lakhs)        Variation Cost: -1882561.99 (-18.83 lakhs)     Hence Total Bond Cost is   26550013.94 (265.5 lakhs) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence1.79 KM6.703.00 KM3.00 KM2.426.70
2.R/Wall, B/ Wall Type Protection works591.00 m54.31545.00 m545.00 m19.6454.31
3.G-35.24 KM39.905.00 KM5.00 KM14.4339.90
4.PC/CC i/c Prime Coat, Tack Coat12.25 KM113.0212.25 KM12.25 KM40.88113.02
5.Culverts/Scupper 5.00 No10.724.00 No4.00 No3.8810.72
6.longitudinal Drain9503.79 m12.4811500.00 m11500.00 m4.5112.48
7.Parapet220.00 No5.68164.00 No164.00 No2.055.68
8.Road Furniture85.00 No1.6930.00 No30.00 No0.611.69
9.Other Allied Works & Finishing Work 2.00 Job23.722.00 Job2.00 Job8.5823.72
10.GSB/RBI/G-10.00 KM0.000.00 KM0.00 KM00.00
11.G-21.00 KM8.240.50 KM0.50 KM2.988.24
Total Amount: 276.46 100   276.46
Remarks: No Remarks       Work Program Made On: 18-11-2017       Updation of work program on: 16-10-2019      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.17-August-201716.37  lakhs
2.30-November-201730.82  lakhs
3.28-April-201827.84  lakhs
4.22-October-201823.17  lakhs
5.15-December-201816.94  lakhs
6.08-July-201921.26  lakhs
7.09-July-201910.44  lakhs
8.30-December-201711.17  lakhs
9.30-May-201821.26  lakhs
10.30-June-201817.16  lakhs
11.31-May-201930.70  lakhs
12.18-June-201913.73  lakhs
13.29-June-201919.06  lakhs
Total 259.92  lakhs
% Payment 97.9 %
Advance Amount:  67.52  lakhs        Recovered Amount:  67.52  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 222     No. of Test Done : 230      No. of Test Passed : 222      No. of Test Failed : 8   Test report of this package
Number of Pics Available on Web Repository: 66
Number of Notice(s) issued: 38

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.17-05-2019Ch.2+950Laying of seal coatAmit KumarJEUDRP R&B Guptkashi See Pic
2.11-05-2019Ch.3+950Rolling over seal coatAmit KumarJEUDRP R&B Guptkashi See Pic
3.09-04-20191+500Slip clearanceAmit KumarJEUDRP R&B Guptkashi See Pic
4.09-10-2018Km 4 ch.3+600Laying of PCAmit KumarJEUDRP R&B Pauri See Pic
5.25-09-2018Km 9 Ch.8+925SRMD Road Block Due to Debris Falled km 9Amit KumarJEUDRP R&B Pauri See Pic
6.28-08-2018Km 3 ch.2+575SRMD Road Block Due to Debris Falled km 3Amit KumarJEUDRP R&B Pauri See Pic
7.28-08-2018Km 3 ch.2+550SRMD R /Wall DamageAmit KumarJEUDRP R&B Pauri See Pic
8.28-08-2018Km 3 ch.2+475SRMD R/Wall DamageAmit KumarJEUDRP R&B Pauri See Pic
9.28-08-2018Km 2 ch.1+975SRMD Road Block Due to Debris Falled km 2Amit KumarJEUDRP R&B Pauri See Pic
10.20-08-2018Km 5 ch.4+200SRMD Site clearance at km 5Amit KumarJEUDRP R&B Pauri See Pic
11.20-08-2018Km 5 ch.4+200SRMD R /Wall DamageAmit KumarJEUDRP R&B Pauri See Pic
12.15-08-2018Km 2 ch.1+350SRMD Road Block Due to Debris Falled km 2Amit KumarJEUDRP R&B Pauri See Pic
13.15-08-2018Km 3 ch.2+625SRMD Road Block Due to Debris Falled km 3Amit KumarJEUDRP R&B Pauri See Pic
14.15-08-2018Km 3 ch.2+575SRMD R/Wall DamageAmit KumarJEUDRP R&B Pauri See Pic
15.15-08-2018Km 2 ch.1+550SRMD Road Block Due to Debris Falled km 2Amit KumarJEUDRP R&B Pauri See Pic
16.12-04-2018Ch 20+525SE Sir inspectuonAnkur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
17.07-04-20185/3Health cheakup for labour camp....Amit KumarJEUDRP R&B Pauri See Pic
18.07-04-20185/3Health chackup camp for labour.......Amit KumarJEUDRP R&B Pauri See Pic
19.19-03-2018Ch 8/30Thickness checking of WBM G3Ankur VishwakarmaSite EngineerDSC2 R&B WB Pauri See Pic
20.04-12-20175+300Environmentall management training with environment expert of egis india and contractor....Noshad QureshiSite SupervisorDSC2 R&B WB Pauri See Pic