UDRP/PWD/06/67/RD/050(N)
Agreement signed
|
Project: |
UDRP-RB |
Package No.: |
132 |
Package Name: |
UDRP/PWD/06/67/RD/050(N) |
Sanction Cost: |
568.32 lakhs |
District: |
Pauri |
Block: |
Dogadda |
Constituency: |
Kotdwar |
Circle: |
Tehri WB Circle |
DEA: |
DEA Pauri |
DSC: |
Egis International |
DSC Scope: |
only Supervision |
No.of Sub project : |
2 |
Subproject in this package |
1 2108 Kotdwar-Pulinda motor road (12.000 KM.) (completed) | 2 2271 Badiyu-jhakhanoli kunkuli MR (10.000 KM.) (completed) |
|
Procurement: |
Package No.: 132
Package Name: UDRP/PWD/06/67/RD/050(N)
Tender Date: 15-12-2016
Current Status: Agreement signed
Achieved on Date: 04-05-2017 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/06/67/RD/050(N)
Contractor Name: SRS Promoters
|
Start Date: 11-05-2017
Intended Completion Date: 31-12-2018
Original End Date: 10-02-2018
|
Total Bond Cost: 28432575.93 (284.33 lakhs)
Variation Cost: -1882561.99 (-18.83 lakhs) Hence Total Bond Cost is 26550013.94 (265.5 lakhs)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Hill side Cutting & Slip clearence | 1.79 KM | 6.70 | 3.00 KM | 3.00 KM | 2.42 | 6.70 | 2. | R/Wall, B/ Wall Type Protection works | 591.00 m | 54.31 | 545.00 m | 545.00 m | 19.64 | 54.31 | 3. | G-3 | 5.24 KM | 39.90 | 5.00 KM | 5.00 KM | 14.43 | 39.90 | 4. | PC/CC i/c Prime Coat, Tack Coat | 12.25 KM | 113.02 | 12.25 KM | 12.25 KM | 40.88 | 113.02 | 5. | Culverts/Scupper | 5.00 No | 10.72 | 4.00 No | 4.00 No | 3.88 | 10.72 | 6. | longitudinal Drain | 9503.79 m | 12.48 | 11500.00 m | 11500.00 m | 4.51 | 12.48 | 7. | Parapet | 220.00 No | 5.68 | 164.00 No | 164.00 No | 2.05 | 5.68 | 8. | Road Furniture | 85.00 No | 1.69 | 30.00 No | 30.00 No | 0.61 | 1.69 | 9. | Other Allied Works & Finishing Work | 2.00 Job | 23.72 | 2.00 Job | 2.00 Job | 8.58 | 23.72 | 10. | GSB/RBI/G-1 | 0.00 KM | 0.00 | 0.00 KM | 0.00 KM | 0 | 0.00 | 11. | G-2 | 1.00 KM | 8.24 | 0.50 KM | 0.50 KM | 2.98 | 8.24 |
Total Amount: |
276.46 |
|
100 |
276.46 |
|
Remarks:
No Remarks
Work Program Made On:
18-11-2017
Updation of work program on:
16-10-2019
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 17-August-2017 | 16.37 lakhs |
2. | 30-November-2017 | 30.82 lakhs |
3. | 28-April-2018 | 27.84 lakhs |
4. | 22-October-2018 | 23.17 lakhs |
5. | 15-December-2018 | 16.94 lakhs |
6. | 08-July-2019 | 21.26 lakhs |
7. | 09-July-2019 | 10.44 lakhs |
8. | 30-December-2017 | 11.17 lakhs |
9. | 30-May-2018 | 21.26 lakhs |
10. | 30-June-2018 | 17.16 lakhs |
11. | 31-May-2019 | 30.70 lakhs |
12. | 18-June-2019 | 13.73 lakhs |
13. | 29-June-2019 | 19.06 lakhs |
Total |
259.92 lakhs |
% Payment |
97.9 % |
|
Advance Amount: 67.52 lakhs
Recovered Amount: 67.52 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 66 |
Number of Notice(s) issued: 38 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 17-05-2019 | Ch.2+950 | Laying of seal coat | Amit Kumar | JE | UDRP R&B Guptkashi | See Pic |
2. | 11-05-2019 | Ch.3+950 | Rolling over seal coat | Amit Kumar | JE | UDRP R&B Guptkashi | See Pic |
3. | 09-04-2019 | 1+500 | Slip clearance | Amit Kumar | JE | UDRP R&B Guptkashi | See Pic |
4. | 09-10-2018 | Km 4 ch.3+600 | Laying of PC | Amit Kumar | JE | UDRP R&B Pauri | See Pic |
5. | 25-09-2018 | Km 9 Ch.8+925 | SRMD Road Block Due to Debris Falled km 9 | Amit Kumar | JE | UDRP R&B Pauri | See Pic |
6. | 28-08-2018 | Km 3 ch.2+575 | SRMD Road Block Due to Debris Falled km 3 | Amit Kumar | JE | UDRP R&B Pauri | See Pic |
7. | 28-08-2018 | Km 3 ch.2+550 | SRMD R /Wall Damage | Amit Kumar | JE | UDRP R&B Pauri | See Pic |
8. | 28-08-2018 | Km 3 ch.2+475 | SRMD R/Wall Damage | Amit Kumar | JE | UDRP R&B Pauri | See Pic |
9. | 28-08-2018 | Km 2 ch.1+975 | SRMD Road Block Due to Debris Falled km 2 | Amit Kumar | JE | UDRP R&B Pauri | See Pic |
10. | 20-08-2018 | Km 5 ch.4+200 | SRMD Site clearance at km 5 | Amit Kumar | JE | UDRP R&B Pauri | See Pic |
11. | 20-08-2018 | Km 5 ch.4+200 | SRMD R /Wall Damage | Amit Kumar | JE | UDRP R&B Pauri | See Pic |
12. | 15-08-2018 | Km 2 ch.1+350 | SRMD Road Block Due to Debris Falled km 2 | Amit Kumar | JE | UDRP R&B Pauri | See Pic |
13. | 15-08-2018 | Km 3 ch.2+625 | SRMD Road Block Due to Debris Falled km 3 | Amit Kumar | JE | UDRP R&B Pauri | See Pic |
14. | 15-08-2018 | Km 3 ch.2+575 | SRMD R/Wall Damage | Amit Kumar | JE | UDRP R&B Pauri | See Pic |
15. | 15-08-2018 | Km 2 ch.1+550 | SRMD Road Block Due to Debris Falled km 2 | Amit Kumar | JE | UDRP R&B Pauri | See Pic |
16. | 12-04-2018 | Ch 20+525 | SE Sir inspectuon | Ankur Vishwakarma | Site Engineer | DSC2 R&B WB Pauri | See Pic |
17. | 07-04-2018 | 5/3 | Health cheakup for labour camp.... | Amit Kumar | JE | UDRP R&B Pauri | See Pic |
18. | 07-04-2018 | 5/3 | Health chackup camp for labour....... | Amit Kumar | JE | UDRP R&B Pauri | See Pic |
19. | 19-03-2018 | Ch 8/30 | Thickness checking of WBM G3 | Ankur Vishwakarma | Site Engineer | DSC2 R&B WB Pauri | See Pic |
20. | 04-12-2017 | 5+300 | Environmentall management training with environment expert of egis india and contractor.... | Noshad Qureshi | Site Supervisor | DSC2 R&B WB Pauri | See Pic |
|
|