UDRP/PWD/06/70/RD/015(N)
Agreement signed
|
Project: |
UDRP-RB |
Package No.: |
130 |
Package Name: |
UDRP/PWD/06/70/RD/015(N) |
Sanction Cost: |
794.32 lakhs |
District: |
Pauri |
Block: |
Rikhnikhal |
Constituency: |
Lansdowne |
Circle: |
Tehri WB Circle |
DEA: |
DEA Pauri |
DSC: |
Egis International |
DSC Scope: |
only Supervision |
No.of Sub project : |
3 |
Subproject in this package |
1 2132 Bunga Malla Motor Road (5.000 KM.) (completed) | 2 2243 Rikhanikhal- chanikhal Motor Road (9.600 KM.) (completed) | 3 2254 Satpulli- Dudhakhal MR (12.000 KM.) (completed) |
|
Procurement: |
Package No.: 130
Package Name: UDRP/PWD/06/70/RD/015(N)
Tender Date: 15-12-2016
Current Status: Agreement signed
Achieved on Date: 04-05-2017 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/06/70/RD/015(N)
Contractor Name: R K Gupta Contractor
|
Start Date: 11-05-2017
Intended Completion Date: 15-06-2019
Original End Date: 10-08-2018
|
Total Bond Cost: 71282113.06 (712.82 lakhs)
Variation Cost: -3164496.59 (-31.64 lakhs) Hence Total Bond Cost is 68117616.47 (681.18 lakhs)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: calculated LD is Rs 14078195 for 395 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Hill side Cutting & Slip clearence | 2.99 KM | 26.38 | 3.00 KM | 3.00 KM | 3.39 | 26.38 | 2. | R/Wall, B/ Wall Type Protection works | 1636.00 m | 153.01 | 1441.00 m | 1441.00 m | 21.23 | 153.01 | 3. | GSB/RBI/G-1 | 4.00 KM | 40.09 | 4.00 KM | 4.00 KM | 5.17 | 40.09 | 4. | G-2 | 10.90 KM | 84.53 | 10.90 KM | 10.90 KM | 11.83 | 84.53 | 5. | G-3 | 12.40 KM | 94.75 | 12.40 KM | 12.40 KM | 13.41 | 94.75 | 6. | PC/CC i/c Prime Coat, Tack Coat | 14.60 KM | 135.61 | 14.60 KM | 14.60 KM | 19.65 | 135.61 | 7. | Culverts/Scupper | 31.00 No | 53.72 | 31.00 No | 31.00 No | 7.66 | 53.72 | 8. | longitudinal Drain | 9979.60 m | 35.86 | 19547.00 m | 19547.00 m | 4.38 | 35.86 | 9. | Crash Barrier | 550.00 m | 15.40 | 550.00 m | 550.00 m | 2.16 | 15.40 | 10. | Parapet | 970.00 No | 28.69 | 880.00 No | 880.00 No | 3.89 | 28.69 | 11. | Road Furniture | 205.00 No | 13.20 | 203.00 No | 203.00 No | 2.08 | 13.20 | 12. | Other Allied Works & Finishing Work | 3.00 Job | 36.47 | 3.00 Job | 3.00 Job | 5.15 | 36.47 |
Total Amount: |
717.71 |
|
100 |
717.71 |
|
Remarks:
No Remarks
Work Program Made On:
18-11-2017
Updation of work program on:
30-07-2019
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 03-October-2017 | 51.45 lakhs |
2. | 30-November-2017 | 57.00 lakhs |
3. | 28-February-2018 | 36.48 lakhs |
4. | 13-April-2018 | 75.44 lakhs |
5. | 30-May-2018 | 72.89 lakhs |
6. | 30-June-2018 | 48.64 lakhs |
7. | 14-August-2018 | 24.04 lakhs |
8. | 22-October-2018 | 62.14 lakhs |
9. | 15-December-2018 | 26.10 lakhs |
10. | 30-January-2019 | 20.72 lakhs |
11. | 28-February-2019 | 22.58 lakhs |
12. | 30-March-2019 | 61.00 lakhs |
13. | 30-April-2019 | 40.35 lakhs |
14. | 31-May-2019 | 7.63 lakhs |
15. | 18-June-2019 | 29.15 lakhs |
16. | 29-June-2019 | 11.27 lakhs |
17. | 09-July-2019 | 44.14 lakhs |
18. | 30-December-2017 | 34.32 lakhs |
Total |
725.34 lakhs |
% Payment |
106.48 % |
|
Advance Amount: 14.32 lakhs
Recovered Amount: 14.32 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 83 |
Number of Notice(s) issued: 47 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 28-08-2018 | X-s 10/15-16 | Lanslide | Pramod Gauniyal | JE | UDRP R&B Pauri | See Pic |
2. | 28-08-2018 | X_s 12/36-37 | Landslide | Pramod Gauniyal | JE | UDRP R&B Pauri | See Pic |
3. | 28-08-2018 | X-s 11/26-27 | Landslide | Pramod Gauniyal | JE | UDRP R&B Pauri | See Pic |
4. | 28-08-2018 | X-s9/32-33 | Landslide | Pramod Gauniyal | JE | UDRP R&B Pauri | See Pic |
5. | 16-08-2018 | 8+150 | Parapet construction in progress. | Subhash Chandra | QC | DSC2 R&B WB Tehri | See Pic |
6. | 02-06-2018 | 2+650 | Spreading and screaning of WBM gr-3 in Progress | Manoj Bhatt | RE | DSC2 R&B WB Pauri | See Pic |
7. | 28-05-2018 | 0+250 | PC laying/rolling in progress. | Subhash Chandra | QC | DSC2 R&B WB Tehri | See Pic |
8. | 25-05-2018 | 7/22 | PC laying in progress. | Subhash Chandra | QC | DSC2 R&B WB Tehri | See Pic |
9. | 17-05-2018 | 8+800 | PC laying in progress. | Subhash Chandra | QC | DSC2 R&B WB Tehri | See Pic |
10. | 09-05-2018 | 9+600 | PC laying Started today. | Subhash Chandra | QC | DSC2 R&B WB Tehri | See Pic |
11. | 08-05-2018 | 9+550 | WBM G3 laying in progress. | Subhash Chandra | QC | DSC2 R&B WB Tehri | See Pic |
12. | 13-04-2018 | Ch 11/18 | Excavation of drain is in progress | Ankur Vishwakarma | Site Engineer | DSC2 R&B WB Pauri | See Pic |
13. | 13-04-2018 | Ch 12/11 | Stacking of WBM G3 is in progress | Ankur Vishwakarma | Site Engineer | DSC2 R&B WB Pauri | See Pic |
14. | 13-04-2018 | Ch 13/30 | Compacted surface of WBM G3 | Ankur Vishwakarma | Site Engineer | DSC2 R&B WB Pauri | See Pic |
15. | 07-04-2018 | 0+270 | WBM G3 laying. | Subhash Chandra | QC | DSC2 R&B WB Tehri | See Pic |
16. | 25-03-2018 | Ch. 1/11 | Excavation of Cutcha Drain | Sagar Kumar | JE | UDRP R&B Pauri | See Pic |
17. | 11-03-2018 | 0+175 | Chainage Marking. | Subhash Chandra | QC | DSC2 R&B WB Tehri | See Pic |
18. | 23-02-2018 | 6+900 | Excavation for katcha drain. | Subhash Chandra | QC | DSC2 R&B WB Tehri | See Pic |
19. | 19-02-2018 | Ch. 6+000 | Noise Pollution Testing | Sagar Kumar | JE | UDRP R&B Pauri | See Pic |
20. | 19-02-2018 | Ch. 0/9 | Air & Noise pollution Testing | Sagar Kumar | JE | UDRP R&B Pauri | See Pic |
|
|