Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/PWD/09/01/RD/115 Agreement signed
Project: UDRP-RB Package No.: 126 Package Name: UDRP/PWD/09/01/RD/115 Sanction Cost: 1490.25  lakhs
District: Almora Block: Lamgarha Constituency: Jageshwar Circle: Pithoragarh WB Circle
DEA: DEA Nanital DSC: Royal Haskoning DHV DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  1050   Jainti-Pipli-Valka Motor Road (11.670 KM.) (completed)
Procurement:
Package No.: 126        Package Name: UDRP/PWD/09/01/RD/115        Tender Date: 11-09-2015        Current Status: Agreement signed        Achieved on Date: 03-12-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/09/01/RD/115        Contractor Name: Patni Engineering and Construction Joint Venture       
Start Date: 10-12-2015        Intended Completion Date: 31-12-2017        Original End Date:  09-03-2017
Total Bond Cost: 100949701.8 (1009.5 lakhs)        Variation Cost: 45890032.18 (458.9 lakhs)     Hence Total Bond Cost is   146839733.98 (1468.4 lakhs) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence11.67 KM204.4611.67 KM11.67 KM15.66204.46
2.R/Wall, B/ Wall Type Protection works2600.00 m367.182600.00 m2600.00 m28.13367.18
3.GSB/RBI/G-110.67 KM84.9110.67 KM10.67 KM6.5184.91
4.G-210.67 KM58.7710.67 KM10.67 KM4.558.77
5.G-311.67 KM86.0311.40 KM11.40 KM6.5986.03
6.PC/CC i/c Prime Coat, Tack Coat11.67 KM117.6811.40 KM11.40 KM9.02117.68
7.Cause Way10.00 No7.5810.00 No10.00 No0.587.58
8.Culverts/Scupper 49.00 No320.1649.00 No49.00 No24.53320.16
9.longitudinal Drain11540.00 m17.3411230.00 m11230.00 m1.3317.34
10.Crash Barrier0.00 m0.000.00 m0.00 m00.00
11.Parapet687.00 No14.40447.00 No447.00 No1.114.40
12.Road Furniture2143.00 No4.57393.00 No393.00 No0.354.57
13.Other Allied Works & Finishing Work 4.00 Job22.184.00 Job4.00 Job1.722.18
Total Amount: 1305.26 100   1305.26
Remarks: work in progress       Work Program Made On: 25-12-2015       Updation of work program on: 14-10-2017      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.06-January-20169.50  lakhs
2.30-January-201666.01  lakhs
3.29-February-201690.03  lakhs
4.31-March-201681.95  lakhs
5.11-May-201621.95  lakhs
6.13-May-2016115.37  lakhs
7.31-May-201650.80  lakhs
8.30-July-201648.06  lakhs
9.30-August-2016152.49  lakhs
10.26-October-201626.14  lakhs
11.09-January-201743.52  lakhs
12.10-March-2017204.85  lakhs
13.29-March-201761.73  lakhs
14.31-May-201748.76  lakhs
15.22-June-2017155.77  lakhs
16.28-September-201782.47  lakhs
17.25-November-201715.43  lakhs
18.27-November-201791.63  lakhs
19.20-December-201748.56  lakhs
20.28-February-201853.27  lakhs
21.05-December-201816.55  lakhs
Total 1484.84  lakhs
% Payment 101.12 %
Advance Amount:  0.00  lakhs        Recovered Amount:  0.00  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 567     No. of Test Done : 595      No. of Test Passed : 542      No. of Test Failed : 53   Test report of this package
Number of Pics Available on Web Repository: 114
Number of Notice(s) issued: 76

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.08-12-20170+000Inspection of CEAshvani KumarJEUDRP R&B Nainital See Pic
2.08-12-201711+650Inspection of CEAshvani KumarJEUDRP R&B Nainital See Pic
3.15-11-201710+300PC workAshvani KumarJEUDRP R&B Nainital See Pic
4.13-11-20179+800Rolling of seal coatAshvani KumarJEUDRP R&B Nainital See Pic
5.13-11-201710+200Cleaning of road surface for PCAshvani KumarJEUDRP R&B Nainital See Pic
6.26-10-20172+300No labour found no work is progressAshvani KumarJEUDRP R&B Nainital See Pic
7.17-10-20172.300R/WallSatish Chand AryaEEUDRP R&B Nainital See Pic
8.08-10-20179+900Slip clearanceAshvani KumarJEUDRP R&B Nainital See Pic
9.07-10-20179+950Slip clearanceAshvani KumarJEUDRP R&B Nainital See Pic
10.07-10-20179+940Slip clearanceAshvani KumarJEUDRP R&B Nainital See Pic
11.06-10-2017At EE officeMonthly meeting with contractor at EE officeAshvani KumarJEUDRP R&B Nainital See Pic
12.07-09-20178+800SRMDAshvani KumarJEUDRP R&B Nainital See Pic
13.07-09-20179+950SRMDAshvani KumarJEUDRP R&B Nainital See Pic
14.07-09-20173+350SRMDAshvani KumarJEUDRP R&B Nainital See Pic
15.07-09-20171+700SRMDAshvani KumarJEUDRP R&B Nainital See Pic
16.02-08-20170+050PlantationAshvani KumarJEUDRP R&B Nainital See Pic
17.02-08-20170+000PlantationAshvani KumarJEUDRP R&B Nainital See Pic
18.02-08-20170+070PlantationAshvani KumarJEUDRP R&B Nainital See Pic
19.02-08-20170+100PlantationAshvani KumarJEUDRP R&B Nainital See Pic
20.12-07-20173+500SRMDAshvani KumarJEUDRP R&B Nainital See Pic