UDRP/PWD/09/01/RD/115
Agreement signed
|
Project: |
UDRP-RB |
Package No.: |
126 |
Package Name: |
UDRP/PWD/09/01/RD/115 |
Sanction Cost: |
1490.25 lakhs |
District: |
Almora |
Block: |
Lamgarha |
Constituency: |
Jageshwar |
Circle: |
Pithoragarh WB Circle |
DEA: |
DEA Nanital |
DSC: |
Royal Haskoning DHV |
DSC Scope: |
Design and Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 1050 Jainti-Pipli-Valka Motor Road (11.670 KM.) (completed) |
|
Procurement: |
Package No.: 126
Package Name: UDRP/PWD/09/01/RD/115
Tender Date: 11-09-2015
Current Status: Agreement signed
Achieved on Date: 03-12-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/09/01/RD/115
Contractor Name: Patni Engineering and Construction Joint Venture
|
Start Date: 10-12-2015
Intended Completion Date: 31-12-2017
Original End Date: 09-03-2017
|
Total Bond Cost: 100949701.8 (1009.5 lakhs)
Variation Cost: 45890032.18 (458.9 lakhs) Hence Total Bond Cost is 146839733.98 (1468.4 lakhs)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Hill side Cutting & Slip clearence | 11.67 KM | 204.46 | 11.67 KM | 11.67 KM | 15.66 | 204.46 | 2. | R/Wall, B/ Wall Type Protection works | 2600.00 m | 367.18 | 2600.00 m | 2600.00 m | 28.13 | 367.18 | 3. | GSB/RBI/G-1 | 10.67 KM | 84.91 | 10.67 KM | 10.67 KM | 6.51 | 84.91 | 4. | G-2 | 10.67 KM | 58.77 | 10.67 KM | 10.67 KM | 4.5 | 58.77 | 5. | G-3 | 11.67 KM | 86.03 | 11.40 KM | 11.40 KM | 6.59 | 86.03 | 6. | PC/CC i/c Prime Coat, Tack Coat | 11.67 KM | 117.68 | 11.40 KM | 11.40 KM | 9.02 | 117.68 | 7. | Cause Way | 10.00 No | 7.58 | 10.00 No | 10.00 No | 0.58 | 7.58 | 8. | Culverts/Scupper | 49.00 No | 320.16 | 49.00 No | 49.00 No | 24.53 | 320.16 | 9. | longitudinal Drain | 11540.00 m | 17.34 | 11230.00 m | 11230.00 m | 1.33 | 17.34 | 10. | Crash Barrier | 0.00 m | 0.00 | 0.00 m | 0.00 m | 0 | 0.00 | 11. | Parapet | 687.00 No | 14.40 | 447.00 No | 447.00 No | 1.1 | 14.40 | 12. | Road Furniture | 2143.00 No | 4.57 | 393.00 No | 393.00 No | 0.35 | 4.57 | 13. | Other Allied Works & Finishing Work | 4.00 Job | 22.18 | 4.00 Job | 4.00 Job | 1.7 | 22.18 |
Total Amount: |
1305.26 |
|
100 |
1305.26 |
|
Remarks:
work in progress
Work Program Made On:
25-12-2015
Updation of work program on:
14-10-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 06-January-2016 | 9.50 lakhs |
2. | 30-January-2016 | 66.01 lakhs |
3. | 29-February-2016 | 90.03 lakhs |
4. | 31-March-2016 | 81.95 lakhs |
5. | 11-May-2016 | 21.95 lakhs |
6. | 13-May-2016 | 115.37 lakhs |
7. | 31-May-2016 | 50.80 lakhs |
8. | 30-July-2016 | 48.06 lakhs |
9. | 30-August-2016 | 152.49 lakhs |
10. | 26-October-2016 | 26.14 lakhs |
11. | 09-January-2017 | 43.52 lakhs |
12. | 10-March-2017 | 204.85 lakhs |
13. | 29-March-2017 | 61.73 lakhs |
14. | 31-May-2017 | 48.76 lakhs |
15. | 22-June-2017 | 155.77 lakhs |
16. | 28-September-2017 | 82.47 lakhs |
17. | 25-November-2017 | 15.43 lakhs |
18. | 27-November-2017 | 91.63 lakhs |
19. | 20-December-2017 | 48.56 lakhs |
20. | 28-February-2018 | 53.27 lakhs |
21. | 05-December-2018 | 16.55 lakhs |
Total |
1484.84 lakhs |
% Payment |
101.12 % |
|
Advance Amount: 0.00 lakhs
Recovered Amount: 0.00 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 114 |
Number of Notice(s) issued: 76 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 08-12-2017 | 0+000 | Inspection of CE | Ashvani Kumar | JE | UDRP R&B Nainital | See Pic |
2. | 08-12-2017 | 11+650 | Inspection of CE | Ashvani Kumar | JE | UDRP R&B Nainital | See Pic |
3. | 15-11-2017 | 10+300 | PC work | Ashvani Kumar | JE | UDRP R&B Nainital | See Pic |
4. | 13-11-2017 | 9+800 | Rolling of seal coat | Ashvani Kumar | JE | UDRP R&B Nainital | See Pic |
5. | 13-11-2017 | 10+200 | Cleaning of road surface for PC | Ashvani Kumar | JE | UDRP R&B Nainital | See Pic |
6. | 26-10-2017 | 2+300 | No labour found no work is progress | Ashvani Kumar | JE | UDRP R&B Nainital | See Pic |
7. | 17-10-2017 | 2.300 | R/Wall | Satish Chand Arya | EE | UDRP R&B Nainital | See Pic |
8. | 08-10-2017 | 9+900 | Slip clearance | Ashvani Kumar | JE | UDRP R&B Nainital | See Pic |
9. | 07-10-2017 | 9+950 | Slip clearance | Ashvani Kumar | JE | UDRP R&B Nainital | See Pic |
10. | 07-10-2017 | 9+940 | Slip clearance | Ashvani Kumar | JE | UDRP R&B Nainital | See Pic |
11. | 06-10-2017 | At EE office | Monthly meeting with contractor at EE office | Ashvani Kumar | JE | UDRP R&B Nainital | See Pic |
12. | 07-09-2017 | 8+800 | SRMD | Ashvani Kumar | JE | UDRP R&B Nainital | See Pic |
13. | 07-09-2017 | 9+950 | SRMD | Ashvani Kumar | JE | UDRP R&B Nainital | See Pic |
14. | 07-09-2017 | 3+350 | SRMD | Ashvani Kumar | JE | UDRP R&B Nainital | See Pic |
15. | 07-09-2017 | 1+700 | SRMD | Ashvani Kumar | JE | UDRP R&B Nainital | See Pic |
16. | 02-08-2017 | 0+050 | Plantation | Ashvani Kumar | JE | UDRP R&B Nainital | See Pic |
17. | 02-08-2017 | 0+000 | Plantation | Ashvani Kumar | JE | UDRP R&B Nainital | See Pic |
18. | 02-08-2017 | 0+070 | Plantation | Ashvani Kumar | JE | UDRP R&B Nainital | See Pic |
19. | 02-08-2017 | 0+100 | Plantation | Ashvani Kumar | JE | UDRP R&B Nainital | See Pic |
20. | 12-07-2017 | 3+500 | SRMD | Ashvani Kumar | JE | UDRP R&B Nainital | See Pic |
|
|