UDRP/PWD/09/03/RD/114 Agreement signed
Project: UDRP-RB Package No.: 125 Package Name: UDRP/PWD/09/03/RD/114 Sanction Cost: 1948.43  lakhs
District: Almora Block: Sult Constituency: Salt Circle: Pithoragarh WB Circle
DEA: DEA Nanital DSC: Royal Haskoning DHV DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  1010   Chimtakhal-Bhonkhal MR (31.000 KM.) (completed)
Procurement:
Package No.: 125        Package Name: UDRP/PWD/09/03/RD/114        Tender Date: 27-06-2015        Current Status: Agreement signed        Achieved on Date: 31-10-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/09/03/RD/114        Contractor Name: Woodhill Infrastructure Ltd       
Start Date: 07-11-2015        Intended Completion Date: 06-02-2017       
Total Bond Cost: 194427007.14 (1944.27 lakhs)        Variation Cost: -1666061.83 (-16.66 lakhs)     Hence Total Bond Cost is   192760945.31 (1927.61 lakhs) 
LD Analysis for Milestone1: calculated LD is Rs 3013634 for 31 days        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence3.35 KM23.253.35 KM3.35 KM1.2123.25
2.R/Wall, B/ Wall Type Protection works6231.00 m346.246231.00 m6231.00 m18.01346.24
3.GSB/RBI/G-10.43 KM2.600.43 KM0.43 KM0.142.60
4.G-311.24 KM100.0011.24 KM11.24 KM5.2100.00
5.PC/CC i/c Prime Coat, Tack Coat0.00 KM0.000.00 KM0.00 KM00.00
6.BM i/c Prime Coat, Tack Coat30.31 KM589.7830.31 KM30.31 KM30.68589.78
7.SDBC i/c Tackcoat30.31 KM333.8530.31 KM30.31 KM17.37333.85
8.Cause Way12.00 No72.4612.00 No12.00 No3.7772.46
9.Culverts/Scupper 41.00 No135.5941.00 No41.00 No7.05135.59
10.longitudinal Drain29340.00 m77.9229340.00 m29340.00 m4.0577.92
11.Crash Barrier3030.00 m94.363030.00 m3030.00 m4.9194.36
12.Parapet2200.00 No70.102200.00 No2200.00 No3.6570.10
13.Road Furniture2695.00 No22.362676.00 No2676.00 No1.1622.36
14.Other Allied Works & Finishing Work 6.00 Job53.826.00 Job6.00 Job2.853.82
Total Amount: 1922.33 100   1922.33
Remarks: work is complited       Work Program Made On: 26-12-2015       Updation of work program on: 28-11-2017      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.31-December-201511.05  lakhs
2.30-January-201681.82  lakhs
3.29-February-201649.48  lakhs
4.31-March-201689.81  lakhs
5.11-May-2016168.41  lakhs
6.23-May-2016195.44  lakhs
7.31-May-2016133.74  lakhs
8.24-June-201685.83  lakhs
9.28-June-2016155.87  lakhs
10.15-July-2016130.45  lakhs
11.26-August-201696.06  lakhs
12.04-October-2016115.91  lakhs
13.21-October-2016177.12  lakhs
14.30-November-201683.58  lakhs
15.23-February-2017176.67  lakhs
16.29-March-2017145.41  lakhs
17.29-July-201725.27  lakhs
Total 1921.92  lakhs
% Payment 99.7 %
Advance Amount:  194.00  lakhs        Recovered Amount:  194.00  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 607     No. of Test Done : 612      No. of Test Passed : 605      No. of Test Failed : 7   Test report of this package
Number of Pics Available on Web Repository: 28
Number of Notice(s) issued: 79

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.31-12-201615+700Inspection of Se sit with E. E and AEDharmendra Kumar SinghREDSC5 R&B WB Nainital See Pic
2.31-12-201615+200Construction of C. C road inspection by S. E Sir with E. E AE and REDharmendra Kumar SinghREDSC5 R&B WB Nainital See Pic
3.19-12-201615+300Construction of CC roadDharmendra Kumar SinghREDSC5 R&B WB Nainital See Pic
4.24-10-2016Ch 11+550Density of sdbc by sand replacement method, result satisfactoryNaresh MittalTLDSC5 R&B WB Bageshwar See Pic
5.24-10-2016Ch 0+750Check of superelevation, 10%Naresh MittalTLDSC5 R&B WB Bageshwar See Pic
6.22-10-201622+!00Construction of plumb wallDharmendra Kumar SinghREDSC5 R&B WB Nainital See Pic
7.21-06-201626+400Laying of sdbcAjay Kumar PandeyQCDSC5 R&B WB Almora See Pic
8.21-06-201623+860Thockness test bm & sdbc with jpint magistrateAjay Kumar PandeyQCDSC5 R&B WB Almora See Pic
9.29-04-201621+300Sdbc workAjay Kumar PandeyQCDSC5 R&B WB Almora See Pic
10.19-04-201615+250Visit mr.yp joshiAjay Kumar PandeyQCDSC5 R&B WB Almora See Pic
11.12-04-201623+900Laying of bmAjay Kumar PandeyQCDSC5 R&B WB Almora See Pic
12.11-04-201615+00Trail batch for hot mix plantAjay Kumar PandeyQCDSC5 R&B WB Almora See Pic
13.09-04-201615+00Trail batch for hot mix plantAjay Kumar PandeyQCDSC5 R&B WB Almora See Pic
14.31-03-201615+440Plum workAjay Kumar PandeyQCDSC5 R&B WB Almora See Pic
15.31-03-201615+400Protection work plum concreteAjay Kumar PandeyQCDSC5 R&B WB Almora See Pic
16.31-03-201621+700Hill side cuttingAjay Kumar PandeyQCDSC5 R&B WB Almora See Pic
17.26-02-2016Starting pointInformation boardPrateek GuptaSite EngineerDSC5 R&B WB Almora See Pic
18.22-12-201510+120CausewayAjay Kumar PandeyQCDSC5 R&B WB Almora See Pic
19.22-12-201510+480CulvertAjay Kumar PandeyQCDSC5 R&B WB Almora See Pic
20.22-12-201510+500Retaining wallAjay Kumar PandeyQCDSC5 R&B WB Almora See Pic