UDRP/PWD/09/03/RD/114
Agreement signed
|
Project: |
UDRP-RB |
Package No.: |
125 |
Package Name: |
UDRP/PWD/09/03/RD/114 |
Sanction Cost: |
1948.43 lakhs |
District: |
Almora |
Block: |
Sult |
Constituency: |
Salt |
Circle: |
Pithoragarh WB Circle |
DEA: |
DEA Nanital |
DSC: |
Royal Haskoning DHV |
DSC Scope: |
Design and Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 1010 Chimtakhal-Bhonkhal MR (31.000 KM.) (completed) |
|
Procurement: |
Package No.: 125
Package Name: UDRP/PWD/09/03/RD/114
Tender Date: 27-06-2015
Current Status: Agreement signed
Achieved on Date: 31-10-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/09/03/RD/114
Contractor Name: Woodhill Infrastructure Ltd
|
Start Date: 07-11-2015
Intended Completion Date: 06-02-2017
|
Total Bond Cost: 194427007.14 (1944.27 lakhs)
Variation Cost: -1666061.83 (-16.66 lakhs) Hence Total Bond Cost is 192760945.31 (1927.61 lakhs)
|
LD Analysis for Milestone1: calculated LD is Rs 3013634 for 31 days
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Hill side Cutting & Slip clearence | 3.35 KM | 23.25 | 3.35 KM | 3.35 KM | 1.21 | 23.25 | 2. | R/Wall, B/ Wall Type Protection works | 6231.00 m | 346.24 | 6231.00 m | 6231.00 m | 18.01 | 346.24 | 3. | GSB/RBI/G-1 | 0.43 KM | 2.60 | 0.43 KM | 0.43 KM | 0.14 | 2.60 | 4. | G-3 | 11.24 KM | 100.00 | 11.24 KM | 11.24 KM | 5.2 | 100.00 | 5. | PC/CC i/c Prime Coat, Tack Coat | 0.00 KM | 0.00 | 0.00 KM | 0.00 KM | 0 | 0.00 | 6. | BM i/c Prime Coat, Tack Coat | 30.31 KM | 589.78 | 30.31 KM | 30.31 KM | 30.68 | 589.78 | 7. | SDBC i/c Tackcoat | 30.31 KM | 333.85 | 30.31 KM | 30.31 KM | 17.37 | 333.85 | 8. | Cause Way | 12.00 No | 72.46 | 12.00 No | 12.00 No | 3.77 | 72.46 | 9. | Culverts/Scupper | 41.00 No | 135.59 | 41.00 No | 41.00 No | 7.05 | 135.59 | 10. | longitudinal Drain | 29340.00 m | 77.92 | 29340.00 m | 29340.00 m | 4.05 | 77.92 | 11. | Crash Barrier | 3030.00 m | 94.36 | 3030.00 m | 3030.00 m | 4.91 | 94.36 | 12. | Parapet | 2200.00 No | 70.10 | 2200.00 No | 2200.00 No | 3.65 | 70.10 | 13. | Road Furniture | 2695.00 No | 22.36 | 2676.00 No | 2676.00 No | 1.16 | 22.36 | 14. | Other Allied Works & Finishing Work | 6.00 Job | 53.82 | 6.00 Job | 6.00 Job | 2.8 | 53.82 |
Total Amount: |
1922.33 |
|
100 |
1922.33 |
|
Remarks:
work is complited
Work Program Made On:
26-12-2015
Updation of work program on:
28-11-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 31-December-2015 | 11.05 lakhs |
2. | 30-January-2016 | 81.82 lakhs |
3. | 29-February-2016 | 49.48 lakhs |
4. | 31-March-2016 | 89.81 lakhs |
5. | 11-May-2016 | 168.41 lakhs |
6. | 23-May-2016 | 195.44 lakhs |
7. | 31-May-2016 | 133.74 lakhs |
8. | 24-June-2016 | 85.83 lakhs |
9. | 28-June-2016 | 155.87 lakhs |
10. | 15-July-2016 | 130.45 lakhs |
11. | 26-August-2016 | 96.06 lakhs |
12. | 04-October-2016 | 115.91 lakhs |
13. | 21-October-2016 | 177.12 lakhs |
14. | 30-November-2016 | 83.58 lakhs |
15. | 23-February-2017 | 176.67 lakhs |
16. | 29-March-2017 | 145.41 lakhs |
17. | 29-July-2017 | 25.27 lakhs |
Total |
1921.92 lakhs |
% Payment |
99.7 % |
|
Advance Amount: 194.00 lakhs
Recovered Amount: 194.00 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 28 |
Number of Notice(s) issued: 79 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 31-12-2016 | 15+700 | Inspection of Se sit with E. E and AE | Dharmendra Kumar Singh | RE | DSC5 R&B WB Nainital | See Pic |
2. | 31-12-2016 | 15+200 | Construction of C. C road inspection by S. E Sir with E. E AE and RE | Dharmendra Kumar Singh | RE | DSC5 R&B WB Nainital | See Pic |
3. | 19-12-2016 | 15+300 | Construction of CC road | Dharmendra Kumar Singh | RE | DSC5 R&B WB Nainital | See Pic |
4. | 24-10-2016 | Ch 11+550 | Density of sdbc by sand replacement method, result satisfactory | Naresh Mittal | TL | DSC5 R&B WB Bageshwar | See Pic |
5. | 24-10-2016 | Ch 0+750 | Check of superelevation, 10% | Naresh Mittal | TL | DSC5 R&B WB Bageshwar | See Pic |
6. | 22-10-2016 | 22+!00 | Construction of plumb wall | Dharmendra Kumar Singh | RE | DSC5 R&B WB Nainital | See Pic |
7. | 21-06-2016 | 26+400 | Laying of sdbc | Ajay Kumar Pandey | QC | DSC5 R&B WB Almora | See Pic |
8. | 21-06-2016 | 23+860 | Thockness test bm & sdbc with jpint magistrate | Ajay Kumar Pandey | QC | DSC5 R&B WB Almora | See Pic |
9. | 29-04-2016 | 21+300 | Sdbc work | Ajay Kumar Pandey | QC | DSC5 R&B WB Almora | See Pic |
10. | 19-04-2016 | 15+250 | Visit mr.yp joshi | Ajay Kumar Pandey | QC | DSC5 R&B WB Almora | See Pic |
11. | 12-04-2016 | 23+900 | Laying of bm | Ajay Kumar Pandey | QC | DSC5 R&B WB Almora | See Pic |
12. | 11-04-2016 | 15+00 | Trail batch for hot mix plant | Ajay Kumar Pandey | QC | DSC5 R&B WB Almora | See Pic |
13. | 09-04-2016 | 15+00 | Trail batch for hot mix plant | Ajay Kumar Pandey | QC | DSC5 R&B WB Almora | See Pic |
14. | 31-03-2016 | 15+440 | Plum work | Ajay Kumar Pandey | QC | DSC5 R&B WB Almora | See Pic |
15. | 31-03-2016 | 15+400 | Protection work plum concrete | Ajay Kumar Pandey | QC | DSC5 R&B WB Almora | See Pic |
16. | 31-03-2016 | 21+700 | Hill side cutting | Ajay Kumar Pandey | QC | DSC5 R&B WB Almora | See Pic |
17. | 26-02-2016 | Starting point | Information board | Prateek Gupta | Site Engineer | DSC5 R&B WB Almora | See Pic |
18. | 22-12-2015 | 10+120 | Causeway | Ajay Kumar Pandey | QC | DSC5 R&B WB Almora | See Pic |
19. | 22-12-2015 | 10+480 | Culvert | Ajay Kumar Pandey | QC | DSC5 R&B WB Almora | See Pic |
20. | 22-12-2015 | 10+500 | Retaining wall | Ajay Kumar Pandey | QC | DSC5 R&B WB Almora | See Pic |
|
|