UDRP/PWD/04/44/RD/112
Agreement signed
|
Project: |
UDRP-RB |
Package No.: |
123 |
Package Name: |
UDRP/PWD/04/44/RD/112 |
Sanction Cost: |
582.19 lakhs |
District: |
Tehri |
Block: |
Narendra Nagar |
Constituency: |
Narendra Nagar |
Circle: |
Tehri WB Circle |
DEA: |
DEA Tehri |
DSC: |
Egis International |
DSC Scope: |
Design and Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 2662 Dabarkhal-Kunda-Mandwa- Ranichouri Motor road (7.000 KM.) (completed) |
|
Procurement: |
Package No.: 123
Package Name: UDRP/PWD/04/44/RD/112
Tender Date: 27-06-2015
Current Status: Agreement signed
Achieved on Date: 13-10-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/04/44/RD/112
Contractor Name: Ramola Construction
|
Start Date: 20-10-2015
Intended Completion Date: 31-07-2017
Original End Date: 19-01-2017
|
Total Bond Cost: 38660077 (386.6 lakhs)
Variation Cost: 15525827.27 (155.26 lakhs) Hence Total Bond Cost is 54185904.27 (541.86 lakhs)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Hill side Cutting & Slip clearence | 6.69 KM | 57.60 | 6.67 KM | 6.67 KM | 13.05 | 57.60 | 2. | R/Wall, B/ Wall Type Protection works | 2000.00 m | 173.11 | 1800.00 m | 1800.00 m | 39.21 | 173.11 | 3. | GSB/RBI/G-1 | 5.75 KM | 36.06 | 5.75 KM | 5.75 KM | 8.17 | 36.06 | 4. | G-2 | 6.61 KM | 34.83 | 6.61 KM | 6.61 KM | 7.89 | 34.83 | 5. | G-3 | 6.61 KM | 3.95 | 6.61 KM | 6.61 KM | 0.9 | 3.95 | 6. | PC/CC i/c Prime Coat, Tack Coat | 6.51 KM | 42.81 | 6.51 KM | 6.51 KM | 9.7 | 42.81 | 7. | Culverts/Scupper | 36.00 No | 67.16 | 35.00 No | 35.00 No | 15.21 | 67.16 | 8. | longitudinal Drain | 6700.00 m | 16.44 | 6500.00 m | 6500.00 m | 3.72 | 16.44 | 9. | Crash Barrier | 0.00 m | 0.00 | 0.00 m | 0.00 m | 0 | 0.00 | 10. | Parapet | 200.00 No | 6.91 | 235.00 No | 235.00 No | 1.57 | 6.91 | 11. | Road Furniture | 128.00 No | 2.61 | 110.00 No | 110.00 No | 0.59 | 2.61 |
Total Amount: |
441.48 |
|
100 |
441.48 |
|
Remarks:
No Remarks
Work Program Made On:
10-12-2015
Updation of work program on:
14-09-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 13-January-2016 | 36.68 lakhs |
2. | 11-February-2016 | 41.86 lakhs |
3. | 28-March-2016 | 62.80 lakhs |
4. | 20-May-2016 | 21.48 lakhs |
5. | 11-July-2016 | 55.12 lakhs |
6. | 21-September-2016 | 60.16 lakhs |
7. | 26-October-2016 | 18.45 lakhs |
8. | 29-November-2016 | 7.96 lakhs |
9. | 28-December-2016 | 22.22 lakhs |
10. | 30-January-2017 | 8.55 lakhs |
11. | 28-February-2017 | 28.29 lakhs |
12. | 31-March-2017 | 31.25 lakhs |
13. | 27-April-2017 | 14.61 lakhs |
14. | 26-May-2017 | 24.56 lakhs |
15. | 21-June-2017 | 23.61 lakhs |
16. | 28-June-2017 | 17.39 lakhs |
17. | 07-October-2017 | 16.61 lakhs |
18. | 27-November-2017 | 25.72 lakhs |
19. | 26-February-2018 | 20.27 lakhs |
20. | 28-March-2018 | 3.22 lakhs |
21. | 30-November-2018 | 2.72 lakhs |
Total |
543.53 lakhs |
% Payment |
100.31 % |
|
Advance Amount: 38.00 lakhs
Recovered Amount: 38.00 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 229 |
Number of Notice(s) issued: 73 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 19-12-2017 | 16.600 | World Bank mission visit | Sudhir Kumar AE | AE | UDRP R&B Tehri | See Pic |
2. | 19-12-2017 | 16.600 | World Bank mission visit | Sudhir Kumar AE | AE | UDRP R&B Tehri | See Pic |
3. | 26-07-2017 | 15.890 | Tree plantation during harela | Gaurav Pant | Site Supervisor | DSC2 WB R&B Tehri | See Pic |
4. | 10-07-2017 | 10.400 | SRMD, Road blocked due to heavy boulder | Gaurav Pant | Site Supervisor | DSC2 WB R&B Tehri | See Pic |
5. | 06-06-2017 | Ch 11.100 | Laying and rolling of PC | Saurab Chauhan | AE | UDRP R&B Tehri | See Pic |
6. | 17-05-2017 | 15.305 | Compaction of PC with static Roller | Gaurav Pant | Site Supervisor | DSC2 WB R&B Tehri | See Pic |
7. | 20-04-2017 | 13+875 | Laying of P.C compacted by static Rolar. | Vikas Badoni | Site Supervisor | DSC2 R&B WB Tehri | See Pic |
8. | 20-04-2017 | 13+400 | Gradation test for Premix Carpet. | Subhash Chandra | QC | DSC2 R&B WB Tehri | See Pic |
9. | 15-04-2017 | 12+600 Lab | Bitumen Extraction Test for PC. | Subhash Chandra | QC | DSC2 R&B WB Tehri | See Pic |
10. | 12-04-2017 | 13+550 | Laying of seal coat in P.C. | Vikas Badoni | Site Supervisor | DSC2 R&B WB Tehri | See Pic |
11. | 11-04-2017 | 12+600 | Bitumen extraction test for P.C. | Vikas Badoni | Site Supervisor | DSC2 R&B WB Tehri | See Pic |
12. | 01-04-2017 | 12+620 | AIV test for Premix Carpet. | Subhash Chandra | QC | DSC2 R&B WB Tehri | See Pic |
13. | 01-04-2017 | 12+620 | Flakiness test for Premix Carpet. | Subhash Chandra | QC | DSC2 R&B WB Tehri | See Pic |
14. | 25-03-2017 | 14+500 | Laying of PC compacted by static Rolar. | Vikas Badoni | Site Supervisor | DSC2 R&B WB Tehri | See Pic |
15. | 20-03-2017 | 14+700 | Laying of P.C compacted by static Rolar. | Vikas Badoni | Site Supervisor | DSC2 R&B WB Tehri | See Pic |
16. | 19-03-2017 | 14+825 | Laying of seal coat in P.C compacted by static Rolar. | Vikas Badoni | Site Supervisor | DSC2 R&B WB Tehri | See Pic |
17. | 19-03-2017 | 14+800 | Laying of P.C compacted by static Rolar. | Vikas Badoni | Site Supervisor | DSC2 R&B WB Tehri | See Pic |
18. | 18-03-2017 | 14+925 | PC laying/Rolling in progress. | Subhash Chandra | QC | DSC2 R&B WB Tehri | See Pic |
19. | 17-03-2017 | 14+925 | Laying of P.C compacted by static Rolar. | Vikas Badoni | Site Supervisor | DSC2 R&B WB Tehri | See Pic |
20. | 16-03-2017 | 15+000 | Laying seal coat in P.C compacted by static Rolar. | Vikas Badoni | Site Supervisor | DSC2 R&B WB Tehri | See Pic |
|
|