Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/PWD/04/44/RD/111 Agreement signed
Project: UDRP-RB Package No.: 122 Package Name: UDRP/PWD/04/44/RD/111 Sanction Cost: 849.91  lakhs
District: Tehri Block: Narendra Nagar Constituency: Narendra Nagar Circle: Tehri WB Circle
DEA: DEA Tehri DSC: Egis International DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  2854   Tachla-Naour motor road (9.000 KM.) (completed)
Procurement:
Package No.: 122        Package Name: UDRP/PWD/04/44/RD/111        Tender Date: 27-06-2015        Current Status: Agreement signed        Achieved on Date: 18-12-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/04/44/RD/111        Contractor Name: VAR Associates       
Start Date: 25-12-2015        Intended Completion Date: 28-02-2018        Original End Date:  24-03-2017
Total Bond Cost: 66309758.97 (663.1 lakhs)        Variation Cost: 7508282.72 (75.08 lakhs)     Hence Total Bond Cost is   73818041.69 (738.18 lakhs) 
LD Analysis for Milestone1: calculated LD is Rs 2387160 for 72 days        LD Analysis for Milestone2: calculated LD is Rs 4310150 for 130 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence8.63 KM61.277.75 KM7.75 KM10.7761.27
2.R/Wall, B/ Wall Type Protection works2930.00 m201.472930.00 m2930.00 m35.4201.47
3.GSB/RBI/G-16.66 KM67.906.66 KM6.66 KM11.9367.90
4.G-26.66 KM45.926.66 KM6.66 KM8.0745.92
5.G-37.97 KM67.437.69 KM7.69 KM11.8567.43
6.PC/CC i/c Prime Coat, Tack Coat7.69 KM14.347.69 KM7.69 KM2.5214.34
7.Culverts/Scupper 50.00 No42.7723.00 No23.00 No7.5242.77
8.longitudinal Drain7100.00 m25.897679.00 m7679.00 m4.5525.89
9.Crash Barrier1200.00 m31.09500.00 m500.00 m5.4631.09
10.Parapet300.00 No8.22300.00 No300.00 No1.458.22
11.Road Furniture127.00 No2.84127.00 No127.00 No0.52.84
Total Amount: 569.14 100   569.14
Remarks: No Remarks       Work Program Made On: 02-04-2016       Updation of work program on: 22-10-2016      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.01-March-201629.64  lakhs
2.22-March-20169.97  lakhs
3.05-May-201631.64  lakhs
4.08-June-201625.01  lakhs
5.22-July-201623.98  lakhs
6.29-August-201633.95  lakhs
7.30-September-201631.70  lakhs
8.26-October-201643.80  lakhs
9.29-November-201638.28  lakhs
10.28-December-201611.32  lakhs
11.30-January-201711.51  lakhs
12.28-February-201736.59  lakhs
13.17-March-201733.96  lakhs
14.31-March-201716.09  lakhs
15.27-April-201713.70  lakhs
16.29-May-201713.93  lakhs
17.17-June-201766.01  lakhs
18.28-June-201729.71  lakhs
19.19-July-201713.09  lakhs
20.31-August-20173.90  lakhs
21.07-October-201716.87  lakhs
22.28-November-201749.13  lakhs
23.30-December-201744.62  lakhs
24.31-January-201818.37  lakhs
25.28-March-201820.29  lakhs
26.30-May-201849.87  lakhs
27.31-October-201818.04  lakhs
28.30-November-20188.01  lakhs
Total 742.98  lakhs
% Payment 100.65 %
Advance Amount:  0.00  lakhs        Recovered Amount:  0.00  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 991     No. of Test Done : 1107      No. of Test Passed : 1058      No. of Test Failed : 49   Test report of this package
Number of Pics Available on Web Repository: 339
Number of Notice(s) issued: 87

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.26-04-20181.500Site inspection by EE Mam WB PWD Tehri, TL Sir DSC 2,Sudhir Kumar AEAEUDRP R&B Tehri See Pic
2.26-04-20182.900Site inspection by SE Sir n EE Mam WB PWD TehriSudhir Kumar AEAEUDRP R&B Tehri See Pic
3.09-02-20182.400Cons. Of Kutcha drainSudhir Kumar AEAEUDRP R&B Tehri See Pic
4.24-01-20180.350Pucca drainSudhir Kumar AEAEUDRP R&B Tehri See Pic
5.24-01-20185.875Naur village pathSudhir Kumar AEAEUDRP R&B Tehri See Pic
6.09-01-20180.00Site inspection /Sudhir Kumar AEAEUDRP R&B Tehri See Pic
7.09-01-20180.000Site inspection by Environment n social expert PIU DehradunSudhir Kumar AEAEUDRP R&B Tehri See Pic
8.28-12-20170.050Site inspection by CE Sir ,SE sir n EE MamSudhir Kumar AEAEUDRP R&B Tehri See Pic
9.27-12-20175.875Site inspection by EE MamSudhir Kumar AEAEUDRP R&B Tehri See Pic
10.27-12-20170.525C/O Kutcha drainSudhir Kumar AEAEUDRP R&B Tehri See Pic
11.27-12-20173.100Foot trackSudhir Kumar AEAEUDRP R&B Tehri See Pic
12.21-12-20173.300Village path (Foot Track )Sudhir Kumar AEAEUDRP R&B Tehri See Pic
13.19-12-20170.025Collection of stone for kharanjaSudhir Kumar AEAEUDRP R&B Tehri See Pic
14.17-12-20170.525PC work completedSudhir Kumar AEAEUDRP R&B Tehri See Pic
15.14-12-20170.050G3 completedSudhir Kumar AEAEUDRP R&B Tehri See Pic
16.14-12-20170.625Rolling of PC surfaceSudhir Kumar AEAEUDRP R&B Tehri See Pic
17.14-12-20175.100Meeting with Naur villagersSudhir Kumar AEAEUDRP R&B Tehri See Pic
18.14-12-20175.100Meeting with villagers NaurSudhir Kumar AEAEUDRP R&B Tehri See Pic
19.14-12-20171.400Medical check up of labourSudhir Kumar AEAEUDRP R&B Tehri See Pic
20.14-12-20172.675Rolling of PC surfaceSudhir Kumar AEAEUDRP R&B Tehri See Pic