UDRP/PWD/04/44/RD/111
Agreement signed
|
Project: |
UDRP-RB |
Package No.: |
122 |
Package Name: |
UDRP/PWD/04/44/RD/111 |
Sanction Cost: |
849.91 lakhs |
District: |
Tehri |
Block: |
Narendra Nagar |
Constituency: |
Narendra Nagar |
Circle: |
Tehri WB Circle |
DEA: |
DEA Tehri |
DSC: |
Egis International |
DSC Scope: |
Design and Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 2854 Tachla-Naour motor road (9.000 KM.) (completed) |
|
Procurement: |
Package No.: 122
Package Name: UDRP/PWD/04/44/RD/111
Tender Date: 27-06-2015
Current Status: Agreement signed
Achieved on Date: 18-12-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/04/44/RD/111
Contractor Name: VAR Associates
|
Start Date: 25-12-2015
Intended Completion Date: 28-02-2018
Original End Date: 24-03-2017
|
Total Bond Cost: 66309758.97 (663.1 lakhs)
Variation Cost: 7508282.72 (75.08 lakhs) Hence Total Bond Cost is 73818041.69 (738.18 lakhs)
|
LD Analysis for Milestone1: calculated LD is Rs 2387160 for 72 days
LD Analysis for Milestone2: calculated LD is Rs 4310150 for 130 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Hill side Cutting & Slip clearence | 8.63 KM | 61.27 | 7.75 KM | 7.75 KM | 10.77 | 61.27 | 2. | R/Wall, B/ Wall Type Protection works | 2930.00 m | 201.47 | 2930.00 m | 2930.00 m | 35.4 | 201.47 | 3. | GSB/RBI/G-1 | 6.66 KM | 67.90 | 6.66 KM | 6.66 KM | 11.93 | 67.90 | 4. | G-2 | 6.66 KM | 45.92 | 6.66 KM | 6.66 KM | 8.07 | 45.92 | 5. | G-3 | 7.97 KM | 67.43 | 7.69 KM | 7.69 KM | 11.85 | 67.43 | 6. | PC/CC i/c Prime Coat, Tack Coat | 7.69 KM | 14.34 | 7.69 KM | 7.69 KM | 2.52 | 14.34 | 7. | Culverts/Scupper | 50.00 No | 42.77 | 23.00 No | 23.00 No | 7.52 | 42.77 | 8. | longitudinal Drain | 7100.00 m | 25.89 | 7679.00 m | 7679.00 m | 4.55 | 25.89 | 9. | Crash Barrier | 1200.00 m | 31.09 | 500.00 m | 500.00 m | 5.46 | 31.09 | 10. | Parapet | 300.00 No | 8.22 | 300.00 No | 300.00 No | 1.45 | 8.22 | 11. | Road Furniture | 127.00 No | 2.84 | 127.00 No | 127.00 No | 0.5 | 2.84 |
Total Amount: |
569.14 |
|
100 |
569.14 |
|
Remarks:
No Remarks
Work Program Made On:
02-04-2016
Updation of work program on:
22-10-2016
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 01-March-2016 | 29.64 lakhs |
2. | 22-March-2016 | 9.97 lakhs |
3. | 05-May-2016 | 31.64 lakhs |
4. | 08-June-2016 | 25.01 lakhs |
5. | 22-July-2016 | 23.98 lakhs |
6. | 29-August-2016 | 33.95 lakhs |
7. | 30-September-2016 | 31.70 lakhs |
8. | 26-October-2016 | 43.80 lakhs |
9. | 29-November-2016 | 38.28 lakhs |
10. | 28-December-2016 | 11.32 lakhs |
11. | 30-January-2017 | 11.51 lakhs |
12. | 28-February-2017 | 36.59 lakhs |
13. | 17-March-2017 | 33.96 lakhs |
14. | 31-March-2017 | 16.09 lakhs |
15. | 27-April-2017 | 13.70 lakhs |
16. | 29-May-2017 | 13.93 lakhs |
17. | 17-June-2017 | 66.01 lakhs |
18. | 28-June-2017 | 29.71 lakhs |
19. | 19-July-2017 | 13.09 lakhs |
20. | 31-August-2017 | 3.90 lakhs |
21. | 07-October-2017 | 16.87 lakhs |
22. | 28-November-2017 | 49.13 lakhs |
23. | 30-December-2017 | 44.62 lakhs |
24. | 31-January-2018 | 18.37 lakhs |
25. | 28-March-2018 | 20.29 lakhs |
26. | 30-May-2018 | 49.87 lakhs |
27. | 31-October-2018 | 18.04 lakhs |
28. | 30-November-2018 | 8.01 lakhs |
Total |
742.98 lakhs |
% Payment |
100.65 % |
|
Advance Amount: 0.00 lakhs
Recovered Amount: 0.00 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 339 |
Number of Notice(s) issued: 87 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 26-04-2018 | 1.500 | Site inspection by EE Mam WB PWD Tehri, TL Sir DSC 2, | Sudhir Kumar AE | AE | UDRP R&B Tehri | See Pic |
2. | 26-04-2018 | 2.900 | Site inspection by SE Sir n EE Mam WB PWD Tehri | Sudhir Kumar AE | AE | UDRP R&B Tehri | See Pic |
3. | 09-02-2018 | 2.400 | Cons. Of Kutcha drain | Sudhir Kumar AE | AE | UDRP R&B Tehri | See Pic |
4. | 24-01-2018 | 0.350 | Pucca drain | Sudhir Kumar AE | AE | UDRP R&B Tehri | See Pic |
5. | 24-01-2018 | 5.875 | Naur village path | Sudhir Kumar AE | AE | UDRP R&B Tehri | See Pic |
6. | 09-01-2018 | 0.00 | Site inspection / | Sudhir Kumar AE | AE | UDRP R&B Tehri | See Pic |
7. | 09-01-2018 | 0.000 | Site inspection by Environment n social expert PIU Dehradun | Sudhir Kumar AE | AE | UDRP R&B Tehri | See Pic |
8. | 28-12-2017 | 0.050 | Site inspection by CE Sir ,SE sir n EE Mam | Sudhir Kumar AE | AE | UDRP R&B Tehri | See Pic |
9. | 27-12-2017 | 5.875 | Site inspection by EE Mam | Sudhir Kumar AE | AE | UDRP R&B Tehri | See Pic |
10. | 27-12-2017 | 0.525 | C/O Kutcha drain | Sudhir Kumar AE | AE | UDRP R&B Tehri | See Pic |
11. | 27-12-2017 | 3.100 | Foot track | Sudhir Kumar AE | AE | UDRP R&B Tehri | See Pic |
12. | 21-12-2017 | 3.300 | Village path (Foot Track ) | Sudhir Kumar AE | AE | UDRP R&B Tehri | See Pic |
13. | 19-12-2017 | 0.025 | Collection of stone for kharanja | Sudhir Kumar AE | AE | UDRP R&B Tehri | See Pic |
14. | 17-12-2017 | 0.525 | PC work completed | Sudhir Kumar AE | AE | UDRP R&B Tehri | See Pic |
15. | 14-12-2017 | 0.050 | G3 completed | Sudhir Kumar AE | AE | UDRP R&B Tehri | See Pic |
16. | 14-12-2017 | 0.625 | Rolling of PC surface | Sudhir Kumar AE | AE | UDRP R&B Tehri | See Pic |
17. | 14-12-2017 | 5.100 | Meeting with Naur villagers | Sudhir Kumar AE | AE | UDRP R&B Tehri | See Pic |
18. | 14-12-2017 | 5.100 | Meeting with villagers Naur | Sudhir Kumar AE | AE | UDRP R&B Tehri | See Pic |
19. | 14-12-2017 | 1.400 | Medical check up of labour | Sudhir Kumar AE | AE | UDRP R&B Tehri | See Pic |
20. | 14-12-2017 | 2.675 | Rolling of PC surface | Sudhir Kumar AE | AE | UDRP R&B Tehri | See Pic |
|
|