UDRP/PWD/04/43/RD/110
Agreement signed
|
Project: |
UDRP-RB |
Package No.: |
121 |
Package Name: |
UDRP/PWD/04/43/RD/110 |
Sanction Cost: |
1445.35 lakhs |
District: |
Tehri |
Block: |
Jakhanidhar |
Constituency: |
Pratapnagar |
Circle: |
|
DEA: |
DEA Tehri |
DSC: |
Egis International |
DSC Scope: |
Design and Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 2882 Sain Mandar MR (15.750 KM.) (completed) |
|
Procurement: |
Package No.: 121
Package Name: UDRP/PWD/04/43/RD/110
Tender Date: 11-09-2015
Current Status: Agreement signed
Achieved on Date: 03-12-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/04/43/RD/110
Contractor Name: Kailash Hillways Engineering Associates
|
Start Date: 10-12-2015
Intended Completion Date: 28-05-2017
Original End Date: 09-03-2017
|
Total Bond Cost: 119979183.8 (1199.79 lakhs)
Variation Cost: 19569539.85 (195.7 lakhs) Hence Total Bond Cost is 139548723.65 (1395.49 lakhs)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Hill side Cutting & Slip clearence | 3.46 KM | 18.43 | 3.46 KM | 3.46 KM | 1.67 | 18.43 | 2. | R/Wall, B/ Wall Type Protection works | 1792.00 m | 206.45 | 3200.00 m | 3200.00 m | 18.76 | 206.45 | 3. | GSB/RBI/G-1 | 0.84 KM | 16.74 | 1.23 KM | 1.23 KM | 1.52 | 16.74 | 4. | G-2 | 1.23 KM | 16.43 | 2.42 KM | 2.42 KM | 1.49 | 16.43 | 5. | G-3 | 4.90 KM | 44.38 | 5.35 KM | 5.35 KM | 4.03 | 44.38 | 6. | BM i/c Prime Coat, Tack Coat | 15.75 KM | 245.44 | 15.41 KM | 15.41 KM | 22.3 | 245.44 | 7. | SDBC i/c Tackcoat | 15.75 KM | 133.28 | 15.41 KM | 15.41 KM | 12.11 | 133.28 | 8. | Culverts/Scupper | 33.00 No | 311.08 | 43.00 No | 43.00 No | 28.26 | 311.08 | 9. | longitudinal Drain | 15610.00 m | 73.78 | 15610.00 m | 15610.00 m | 6.7 | 73.78 | 10. | Parapet | 1177.00 No | 32.31 | 195.00 No | 195.00 No | 2.94 | 32.31 | 11. | Road Furniture | 124.00 No | 2.35 | 102.00 No | 102.00 No | 0.21 | 2.35 |
Total Amount: |
1100.67 |
|
100 |
1100.67 |
|
Remarks:
Package completed
Work Program Made On:
05-05-2016
Updation of work program on:
22-07-2016
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 30-January-2016 | 149.13 lakhs |
2. | 29-February-2016 | 208.08 lakhs |
3. | 29-March-2016 | 118.49 lakhs |
4. | 03-June-2016 | 147.88 lakhs |
5. | 11-July-2016 | 63.96 lakhs |
6. | 01-August-2016 | 112.88 lakhs |
7. | 30-September-2016 | 38.22 lakhs |
8. | 26-December-2016 | 20.03 lakhs |
9. | 17-January-2017 | 343.37 lakhs |
10. | 10-March-2017 | 10.51 lakhs |
11. | 27-April-2017 | 29.15 lakhs |
12. | 31-May-2017 | 46.84 lakhs |
13. | 07-July-2017 | 39.32 lakhs |
14. | 20-July-2017 | 37.12 lakhs |
15. | 27-November-2017 | 28.29 lakhs |
Total |
1393.27 lakhs |
% Payment |
99.84 % |
|
Advance Amount: 499.99 lakhs
Recovered Amount: 499.99 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 187 |
Number of Notice(s) issued: 83 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 21-03-2017 | 15.240 | Laying and rolling of SDBC layer | Gaurav Pant | Site Supervisor | DSC2 WB R&B Tehri | See Pic |
2. | 08-02-2017 | 4+725 | RCC slab casting for 6m span culvert. | Vikas Badoni | Site Supervisor | DSC2 R&B WB Tehri | See Pic |
3. | 06-02-2017 | 4+725 | Steel checking of 6 MTR. Span Culvert. | Subhash Chandra | QC | DSC2 R&B WB Tehri | See Pic |
4. | 17-12-2016 | 14.500 | Density test of BM & SDBC by Sand Replacement method | Saurab Chauhan | AE | UDRP R&B Tehri | See Pic |
5. | 17-12-2016 | Ch 1.900 | Checking of metal beam crash barrier | Saurab Chauhan | AE | UDRP R&B Tehri | See Pic |
6. | 10-12-2016 | 10.650 | Causway Wearing Coat | Gaurav Pant | Site Supervisor | DSC2 R&B WB Tehri | See Pic |
7. | 08-12-2016 | 10.650 | P.C.C of Causway 2nd half | Gaurav Pant | Site Supervisor | DSC2 R&B WB Tehri | See Pic |
8. | 22-11-2016 | 13.625 | Compaction of BM layer | Gaurav Pant | Site Supervisor | DSC2 R&B WB Tehri | See Pic |
9. | 20-11-2016 | 14.580 | Compaction of BM layer with static roller | Gaurav Pant | Site Supervisor | DSC2 R&B WB Tehri | See Pic |
10. | 11-11-2016 | 0+860 | BM laying in Progress. | Subhash Chandra | QC | DSC2 R&B WB Tehri | See Pic |
11. | 07-11-2016 | Ch 1.930 | Social environmental visit | Saurab Chauhan | AE | UDRP R&B Tehri | See Pic |
12. | 05-11-2016 | 1.625 | Laying Of BM | Gaurav Pant | Site Supervisor | DSC2 R&B WB Tehri | See Pic |
13. | 05-11-2016 | HMP | Bitumen Extraction for BM | Gaurav Pant | Site Supervisor | DSC2 R&B WB Tehri | See Pic |
14. | 04-11-2016 | Ch 1.850 | Laying and rolling of BM at Sain Mandar Motor Road | Saurab Chauhan | AE | UDRP R&B Tehri | See Pic |
15. | 26-10-2016 | HMP | Bitumen Extraction For SDBC | Gaurav Pant | Site Supervisor | DSC2 R&B WB Tehri | See Pic |
16. | 23-10-2016 | Ch 3.770 | Spraying of SS-1 | Saurab Chauhan | AE | UDRP R&B Tehri | See Pic |
17. | 23-10-2016 | Ch 4.400 | Laying and compaction of SDBC | Saurab Chauhan | AE | UDRP R&B Tehri | See Pic |
18. | 21-10-2016 | HMP | BM Production | Gaurav Pant | Site Supervisor | DSC2 R&B WB Tehri | See Pic |
19. | 21-10-2016 | HMP | Bitumen Extraction for BM | Gaurav Pant | Site Supervisor | DSC2 R&B WB Tehri | See Pic |
20. | 19-10-2016 | 5.225 | Laying Of BM | Gaurav Pant | Site Supervisor | DSC2 R&B WB Tehri | See Pic |
|
|