                            Project:               District:               Package: 

Package Profile Report

UDRP/PWD/04/43/RD/110 Agreement signed
Project: UDRP-RB Package No.: 121 Package Name: UDRP/PWD/04/43/RD/110 Sanction Cost: 1445.35  lakhs
District: Tehri Block: Jakhanidhar Constituency: Pratapnagar Circle:
DEA: DEA Tehri DSC: Egis International DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  2882   Sain Mandar MR (15.750 KM.) (completed)
Procurement:
Package No.: 121        Package Name: UDRP/PWD/04/43/RD/110        Tender Date: 11-09-2015        Current Status: Agreement signed        Achieved on Date: 03-12-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/04/43/RD/110        Contractor Name: Kailash Hillways Engineering Associates       
Start Date: 10-12-2015        Intended Completion Date: 28-05-2017        Original End Date:  09-03-2017
Total Bond Cost: 119979183.8 (1199.79 lakhs)        Variation Cost: 19569539.85 (195.7 lakhs)     Hence Total Bond Cost is   139548723.65 (1395.49 lakhs) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence3.46 KM18.433.46 KM3.46 KM1.6718.43
2.R/Wall, B/ Wall Type Protection works1792.00 m206.453200.00 m3200.00 m18.76206.45
3.GSB/RBI/G-10.84 KM16.741.23 KM1.23 KM1.5216.74
4.G-21.23 KM16.432.42 KM2.42 KM1.4916.43
5.G-34.90 KM44.385.35 KM5.35 KM4.0344.38
6.BM i/c Prime Coat, Tack Coat15.75 KM245.4415.41 KM15.41 KM22.3245.44
7.SDBC i/c Tackcoat15.75 KM133.2815.41 KM15.41 KM12.11133.28
8.Culverts/Scupper 33.00 No311.0843.00 No43.00 No28.26311.08
9.longitudinal Drain15610.00 m73.7815610.00 m15610.00 m6.773.78
10.Parapet1177.00 No32.31195.00 No195.00 No2.9432.31
11.Road Furniture124.00 No2.35102.00 No102.00 No0.212.35
Total Amount: 1100.67 100   1100.67
Remarks: Package completed       Work Program Made On: 05-05-2016       Updation of work program on: 22-07-2016      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.30-January-2016149.13  lakhs
2.29-February-2016208.08  lakhs
3.29-March-2016118.49  lakhs
4.03-June-2016147.88  lakhs
5.11-July-201663.96  lakhs
6.01-August-2016112.88  lakhs
7.30-September-201638.22  lakhs
8.26-December-201620.03  lakhs
9.17-January-2017343.37  lakhs
10.10-March-201710.51  lakhs
11.27-April-201729.15  lakhs
12.31-May-201746.84  lakhs
13.07-July-201739.32  lakhs
14.20-July-201737.12  lakhs
15.27-November-201728.29  lakhs
Total 1393.27  lakhs
% Payment 99.84 %
Advance Amount:  499.99  lakhs        Recovered Amount:  499.99  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 1915     No. of Test Done : 2002      No. of Test Passed : 1931      No. of Test Failed : 71   Test report of this package
Number of Pics Available on Web Repository: 187
Number of Notice(s) issued: 83

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.21-03-201715.240Laying and rolling of SDBC layerGaurav PantSite SupervisorDSC2 WB R&B Tehri See Pic
2.08-02-20174+725RCC slab casting for 6m span culvert.Vikas BadoniSite SupervisorDSC2 R&B WB Tehri See Pic
3.06-02-20174+725Steel checking of 6 MTR. Span Culvert.Subhash ChandraQCDSC2 R&B WB Tehri See Pic
4.17-12-201614.500Density test of BM & SDBC by Sand Replacement methodSaurab ChauhanAEUDRP R&B Tehri See Pic
5.17-12-2016Ch 1.900Checking of metal beam crash barrierSaurab ChauhanAEUDRP R&B Tehri See Pic
6.10-12-201610.650Causway Wearing CoatGaurav PantSite SupervisorDSC2 R&B WB Tehri See Pic
7.08-12-201610.650P.C.C of Causway 2nd halfGaurav PantSite SupervisorDSC2 R&B WB Tehri See Pic
8.22-11-201613.625Compaction of BM layerGaurav PantSite SupervisorDSC2 R&B WB Tehri See Pic
9.20-11-201614.580Compaction of BM layer with static rollerGaurav PantSite SupervisorDSC2 R&B WB Tehri See Pic
10.11-11-20160+860BM laying in Progress.Subhash ChandraQCDSC2 R&B WB Tehri See Pic
11.07-11-2016Ch 1.930Social environmental visitSaurab ChauhanAEUDRP R&B Tehri See Pic
12.05-11-20161.625Laying Of BMGaurav PantSite SupervisorDSC2 R&B WB Tehri See Pic
13.05-11-2016HMPBitumen Extraction for BMGaurav PantSite SupervisorDSC2 R&B WB Tehri See Pic
14.04-11-2016Ch 1.850Laying and rolling of BM at Sain Mandar Motor RoadSaurab ChauhanAEUDRP R&B Tehri See Pic
15.26-10-2016HMPBitumen Extraction For SDBCGaurav PantSite SupervisorDSC2 R&B WB Tehri See Pic
16.23-10-2016Ch 3.770Spraying of SS-1Saurab ChauhanAEUDRP R&B Tehri See Pic
17.23-10-2016Ch 4.400Laying and compaction of SDBCSaurab ChauhanAEUDRP R&B Tehri See Pic
18.21-10-2016HMPBM ProductionGaurav PantSite SupervisorDSC2 R&B WB Tehri See Pic
19.21-10-2016HMPBitumen Extraction for BMGaurav PantSite SupervisorDSC2 R&B WB Tehri See Pic
20.19-10-20165.225Laying Of BMGaurav PantSite SupervisorDSC2 R&B WB Tehri See Pic