Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/PWD/02/38/RD/109 Agreement signed
Project: UDRP-RB Package No.: 120 Package Name: UDRP/PWD/02/38/RD/109 Sanction Cost: 884.92  lakhs
District: Chamoli Block: Pokhari Constituency: Badrinath Circle: Rudraprayag WB Circle
DEA: DEA Karanprayag DSC: Yongma Engineering Co. Ltd. DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  1280   Gauchar Rano Quithi MR (8.500 KM.) (completed)
Procurement:
Package No.: 120        Package Name: UDRP/PWD/02/38/RD/109        Tender Date: 27-06-2015        Current Status: Agreement signed        Achieved on Date: 20-11-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/02/38/RD/109        Contractor Name: Anupam Construction Co.       
Start Date: 27-11-2015        Intended Completion Date: 15-03-2018        Original End Date:  26-02-2017
Total Bond Cost: 78303995.33 (783.04 lakhs)        Variation Cost: 4056459.00 (40.56 lakhs)     Hence Total Bond Cost is   82360454.33 (823.6 lakhs) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 2858096 for 73 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence8.00 KM92.718.00 KM8.00 KM11.0392.71
2.R/Wall, B/ Wall Type Protection works4200.00 m417.584200.00 m4200.00 m49.66417.58
3.GSB/RBI/G-18.50 KM31.478.50 KM8.50 KM3.7431.47
4.G-28.50 KM35.928.50 KM8.50 KM4.2735.92
5.G-38.50 KM49.598.50 KM8.50 KM5.949.59
6.PC/CC i/c Prime Coat, Tack Coat8.50 KM72.738.50 KM8.50 KM8.6572.73
7.Cause Way9.00 No40.999.00 No9.00 No4.8840.99
8.Culverts/Scupper 19.00 No64.4319.00 No19.00 No7.6664.43
9.longitudinal Drain8500.00 m16.168500.00 m8500.00 m1.9216.16
10.Crash Barrier0.00 m0.000.00 m0.00 m00.00
11.Parapet400.00 No10.96400.00 No400.00 No1.310.96
12.Road Furniture45.00 No1.7545.00 No45.00 No0.211.75
13.Env. Man & Moni Plan1.00 Job6.531.00 Job1.00 Job0.786.53
Total Amount: 840.82 100   840.82
Remarks: No Remarks       Work Program Made On: 22-12-2015       Updation of work program on: 02-08-2019      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.23-December-201514.62  lakhs
2.24-December-201558.80  lakhs
3.25-December-201519.14  lakhs
4.23-January-201651.33  lakhs
5.04-March-201646.20  lakhs
6.21-March-201631.82  lakhs
7.11-May-201672.36  lakhs
8.30-June-201669.14  lakhs
9.30-August-201617.42  lakhs
10.30-December-201612.15  lakhs
11.15-March-201712.70  lakhs
12.16-March-201716.37  lakhs
13.23-March-201745.93  lakhs
14.12-June-201766.81  lakhs
15.28-July-201723.55  lakhs
16.13-October-201731.56  lakhs
17.24-November-201736.13  lakhs
18.30-November-201725.12  lakhs
19.22-December-201741.23  lakhs
20.31-January-201849.12  lakhs
21.28-March-201827.74  lakhs
22.30-June-201827.06  lakhs
23.31-October-201827.32  lakhs
24.27-February-201917.23  lakhs
Total 840.85  lakhs
% Payment 102.09 %
Advance Amount:  19.14  lakhs        Recovered Amount:  0.00  lakhs        Balance to be Recovered  19.14  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 408     No. of Test Done : 505      No. of Test Passed : 445      No. of Test Failed : 60   Test report of this package
Number of Pics Available on Web Repository: 213
Number of Notice(s) issued: 79

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.11-06-2019Ch 11.550Causeway in progressNaveen Kumar SharmaAEUDRP R&B Karanprayag See Pic
2.28-03-2019LabAIV test of G2Naveen Kumar SharmaAEUDRP R&B Karanprayag See Pic
3.15-10-2018Ch 6+350 to 6+400Site visit by SE rudraprayag with E E and A E WB KarnprayagDhwajvir SinghJEUDRP R&B Karnprayag See Pic
4.15-02-2018Ch 6.400Making a base on hard rock by CC and T/W under progressDhwajvir SinghJEUDRP R&B Karnprayag See Pic
5.19-01-2018Ch 5.800Checking of Causeway R/W and giving a alignment for causeway.Dhwajvir SinghJEUDRP R&B Karnprayag See Pic
6.19-01-20186.800R wall work completedLalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
7.04-01-2018CH 5.400Giving a layout of causewayRajeev KumarJEUDRP R&B Karnprayag See Pic
8.20-12-2017Ch 8.400Resolving the local problem Demand for RWall near village.Lalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
9.20-12-2017Ch5.950kmConstruction of RWall completeLalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
10.19-12-2017At office WB KaranparyagMeeting with villager regarding site issuesRajeev KumarJEUDRP R&B Karnprayag See Pic
11.16-12-2017CH 7.85 kmSecond time shuttering damaged and collapsed due to slip.Rajeev KumarJEUDRP R&B Karnprayag See Pic
12.29-11-20172nd kmConstruction of causewayLalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
13.29-11-2017Ch.5700Banded wall under progressLalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
14.27-11-2017Km 5.600Improvement of causeway and haipinband.Lalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
15.16-11-2017Km1Medical checkup of labourersLalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
16.16-11-2017Ch 7.200Top coat under progressLalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
17.16-11-2017Ch3.8 kmConcreting work under progressLalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
18.10-11-2017Km 4Reconstruction of damaged Wall which was washed out during last monsoon.Lalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
19.10-11-2017Km 4.900Prime coat completed and making site ready for pC work.Lalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
20.01-11-2017Ch 5.450Construction of RWall with plum and banded wall.Lalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic