Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/PWD/07/20/RD/012 Agreement signed
Project: UDRP-RB Package No.: 12 Package Name: UDRP/PWD/07/20/RD/012 Sanction Cost: 575.81  lakhs
District: Pithoragarh Block: Gangolihat Constituency: Gangolihat Circle: Pithoragarh WB Circle
DEA: DEA Munsyari DSC: Yongma Engineering Co. Ltd. DSC Scope: only Supervision No.of Sub project : 1
Subproject in this package
1  2322   Ganai Bankot motor road (13.000 KM.) (completed)
Procurement:
Package No.: 12        Package Name: UDRP/PWD/07/20/RD/012        Tender Date: 27-03-2014        Current Status: Agreement signed        Achieved on Date: 06-08-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/07/20/RD/012        Contractor Name: ESPAN Infrastructure Ltd       
Start Date: 20-08-2014        Intended Completion Date: 28-07-2016        Original End Date:  19-11-2015
Total Bond Cost: 48862983.5 (488.63 lakhs)        Variation Cost: 5673825.41 (56.74 lakhs)     Hence Total Bond Cost is   54536808.91 (545.37 lakhs) 
LD Analysis for Milestone1: calculated LD is Rs 781792 for 32 days        LD Analysis for Milestone2: calculated LD is Rs 171017 for 7 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.R/Wall, B/ Wall Type Protection works1511.00 m108.971985.00 m1985.00 m22.37108.97
2.GSB/RBI/G-10.25 KM14.660.20 KM0.20 KM3.0114.66
3.G-30.35 KM2.760.35 KM0.35 KM0.572.76
4.PC/CC i/c Prime Coat, Tack Coat13.00 KM135.4613.00 KM13.00 KM27.81135.46
5.Cause Way17.00 No52.3717.00 No17.00 No10.7552.37
6.Culverts/Scupper 35.00 No60.4927.00 No27.00 No12.4260.49
7.longitudinal Drain10850.00 m31.569350.00 m9350.00 m6.4831.56
8.Parapet1950.00 No77.631140.00 No1140.00 No15.9477.63
9.Road Furniture116.00 No3.26118.00 No118.00 No0.673.26
Total Amount: 487.16 100   487.16
Remarks: No Remarks       Work Program Made On: 25-09-2015       Updation of work program on: 22-07-2016      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.06-June-2015120.43  lakhs
2.27-August-201545.61  lakhs
3.30-September-201569.00  lakhs
4.30-October-201544.19  lakhs
5.21-December-201539.17  lakhs
6.30-January-201640.21  lakhs
7.09-March-201628.77  lakhs
8.30-March-201614.97  lakhs
9.30-April-201624.13  lakhs
10.25-May-201647.99  lakhs
11.26-October-201634.00  lakhs
12.24-February-201721.74  lakhs
Total 530.21  lakhs
% Payment 97.22 %
Advance Amount:  48.86  lakhs        Recovered Amount:  48.86  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 190     No. of Test Done : 212      No. of Test Passed : 190      No. of Test Failed : 22   Test report of this package
Number of Pics Available on Web Repository: 134
Number of Notice(s) issued: 72

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.13-06-201611.425Seal coat work in progressPramod JoshiSite EngineerDSC4 R&B WB Munsyari See Pic
2.18-05-20168.325Rolling of premix carpetPramod JoshiSite EngineerDSC4 R&B WB Munsyari See Pic
3.18-05-20168.200Seal coat work in progressPramod JoshiSite EngineerDSC4 R&B WB Munsyari See Pic
4.30-04-20168.325P Q C work in progressPramod JoshiSite EngineerDSC4 R&B WB Munsyari See Pic
5.27-04-2016Chainage 0.400Laying of PCPrem PrakashAEUDRP R&B Munsyari See Pic
6.26-04-20160.400Rolling of sealcoatPramod JoshiSite EngineerDSC4 R&B WB Munsyari See Pic
7.26-04-20160.400Seal coat work in progressPramod JoshiSite EngineerDSC4 R&B WB Munsyari See Pic
8.22-04-2016LabBitumen extraction test of pcDinesh KumarREDSC4 R&B WB Munsyari See Pic
9.22-04-20168+325Causeway khranja in progressDinesh KumarREDSC4 R&B WB Munsyari See Pic
10.22-04-20160+400Seal coat work in progressDinesh KumarREDSC4 R&B WB Munsyari See Pic
11.22-04-2016LabBitumen extraction test of p cGirjesh Kumar DubeyQCDSC4 R&B WB Munsyari See Pic
12.22-04-2016LabBitumen extraction testGirjesh Kumar DubeyQCDSC4 R&B WB Munsyari See Pic
13.22-04-20160+400Rolling of sealcoatGirjesh Kumar DubeyQCDSC4 R&B WB Munsyari See Pic
14.21-04-20160.250Seal coat work in progressPramod JoshiSite EngineerDSC4 R&B WB Munsyari See Pic
15.19-04-201613.000Information boardPramod JoshiSite EngineerDSC4 R&B WB Munsyari See Pic
16.14-04-20160.000Seal coat work in progressPramod JoshiSite EngineerDSC4 R&B WB Munsyari See Pic
17.14-04-20160.125P C work in progressPramod JoshiSite EngineerDSC4 R&B WB Munsyari See Pic
18.14-04-20160.025P C work in progressPramod JoshiSite EngineerDSC4 R&B WB Munsyari See Pic
19.14-04-20160.000P C work in progressPramod JoshiSite EngineerDSC4 R&B WB Munsyari See Pic
20.14-04-20160.650Seal coat in progressPramod JoshiSite EngineerDSC4 R&B WB Munsyari See Pic