UDRP/PWD/02/38/RD/108
Agreement signed
|
Project: |
UDRP-RB |
Package No.: |
119 |
Package Name: |
UDRP/PWD/02/38/RD/108 |
Sanction Cost: |
889.84 lakhs |
District: |
Chamoli |
Block: |
Karnaprayag |
Constituency: |
Karanprayag |
Circle: |
Rudraprayag WB Circle |
DEA: |
DEA Gopeshwar |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
Design and Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 1238 Gauchar Shail Dua MR (10.000 KM.) (completed) |
|
Procurement: |
Package No.: 119
Package Name: UDRP/PWD/02/38/RD/108
Tender Date: 27-06-2015
Current Status: Agreement signed
Achieved on Date: 02-12-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/02/38/RD/108
Contractor Name: Sharda Associates
|
Start Date: 09-12-2015
Intended Completion Date: 31-12-2017
Original End Date: 08-03-2017
|
Total Bond Cost: 67153711.16 (671.54 lakhs)
Variation Cost: 20538013.00 (205.38 lakhs) Hence Total Bond Cost is 87691724.16 (876.92 lakhs)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: calculated LD is Rs 2048197 for 61 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Hill side Cutting & Slip clearence | 10.00 KM | 62.31 | 10.00 KM | 10.00 KM | 8.43 | 62.31 | 2. | R/Wall, B/ Wall Type Protection works | 1430.00 m | 158.19 | 1480.00 m | 1480.00 m | 21.41 | 158.19 | 3. | GSB/RBI/G-1 | 10.00 KM | 82.25 | 10.00 KM | 10.00 KM | 11.14 | 82.25 | 4. | G-2 | 10.00 KM | 59.80 | 10.00 KM | 10.00 KM | 8.1 | 59.80 | 5. | G-3 | 10.00 KM | 82.44 | 10.00 KM | 10.00 KM | 11.16 | 82.44 | 6. | PC/CC i/c Prime Coat, Tack Coat | 10.00 KM | 117.65 | 10.00 KM | 10.00 KM | 15.93 | 117.65 | 7. | Cause Way | 3.00 No | 6.82 | 1.00 No | 1.00 No | 0.92 | 6.82 | 8. | Culverts/Scupper | 23.00 No | 85.82 | 22.00 No | 22.00 No | 11.62 | 85.82 | 9. | longitudinal Drain | 10000.00 m | 41.27 | 10000.00 m | 10000.00 m | 5.59 | 41.27 | 10. | Crash Barrier | 950.00 m | 25.52 | 950.00 m | 950.00 m | 3.45 | 25.52 | 11. | Parapet | 400.00 No | 12.17 | 400.00 No | 400.00 No | 1.65 | 12.17 | 12. | Road Furniture | 153.00 No | 4.48 | 153.00 No | 153.00 No | 0.61 | 4.48 |
Total Amount: |
738.72 |
|
100 |
738.72 |
|
Remarks:
No Remarks
Work Program Made On:
23-12-2015
Updation of work program on:
23-11-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 23-January-2016 | 51.69 lakhs |
2. | 29-February-2016 | 42.66 lakhs |
3. | 30-April-2016 | 67.33 lakhs |
4. | 30-June-2016 | 44.80 lakhs |
5. | 30-August-2016 | 35.78 lakhs |
6. | 30-September-2016 | 47.75 lakhs |
7. | 08-December-2016 | 45.89 lakhs |
8. | 03-February-2017 | 65.46 lakhs |
9. | 28-February-2017 | 29.03 lakhs |
10. | 22-March-2017 | 58.86 lakhs |
11. | 31-March-2017 | 29.46 lakhs |
12. | 25-May-2017 | 98.29 lakhs |
13. | 14-July-2017 | 40.35 lakhs |
14. | 13-October-2017 | 106.21 lakhs |
15. | 19-December-2017 | 78.37 lakhs |
16. | 30-May-2018 | 20.98 lakhs |
17. | 12-September-2018 | 14.03 lakhs |
Total |
876.94 lakhs |
% Payment |
100 % |
|
Advance Amount: 147.71 lakhs
Recovered Amount: 127.81 lakhs
Balance to be Recovered 19.90 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 182 |
Number of Notice(s) issued: 73 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 20-11-2017 | 0.840 | Consultation with local people Mr pulsar Lal and hagfish lal | Ashwani Kumar | RE | DSC4 R&B WB Chamoli | See Pic |
2. | 20-11-2017 | 0.870 | Checking slope of Retaining wall found 1:3 | Ashwani Kumar | RE | DSC4 R&B WB Chamoli | See Pic |
3. | 20-11-2017 | 0.470 | Work of Retaining wall in progress | Ashwani Kumar | RE | DSC4 R&B WB Chamoli | See Pic |
4. | 23-07-2017 | Ch. 7+050 | Road damage due to heavy Rain | Sohanbir Singh | JE | UDRP R&B Chamoli | See Pic |
5. | 23-07-2017 | Ch.0+880 | Consultation with local people | Sohanbir Singh | JE | UDRP R&B Chamoli | See Pic |
6. | 22-07-2017 | Ch. 6+450 | Slip clearance | Sohanbir Singh | JE | UDRP R&B Chamoli | See Pic |
7. | 22-07-2017 | Ch.0+390 | Old R/W damage due to Heavy Rain | Sohanbir Singh | JE | UDRP R&B Chamoli | See Pic |
8. | 14-04-2017 | Lab | AIV test of G3 material found 24percent | Kirti Vardhan Negi | AE | DEA WB Gopeshwar | See Pic |
9. | 14-04-2017 | Checking 8.060 | Thicknesses checking of pc by EE sir found 20mm | Kirti Vardhan Negi | AE | DEA WB Gopeshwar | See Pic |
10. | 14-04-2017 | Ch 8.040 | Laying of pc | Kirti Vardhan Negi | AE | DEA WB Gopeshwar | See Pic |
11. | 14-04-2017 | Ch 8.040 | Rolling of seal coat | Kirti Vardhan Negi | AE | DEA WB Gopeshwar | See Pic |
12. | 25-03-2017 | Ch 9.150 | Bitumen extraction test | Kirti Vardhan Negi | AE | DEA WB Gopeshwar | See Pic |
13. | 25-03-2017 | Ch9.190 | Thickness checking of pc | Kirti Vardhan Negi | AE | DEA WB Gopeshwar | See Pic |
14. | 25-03-2017 | Ch 9.190 | Seal coat laying | Kirti Vardhan Negi | AE | DEA WB Gopeshwar | See Pic |
15. | 25-03-2017 | Ch 6.950 | Plum wall for hp band protection | Kirti Vardhan Negi | AE | DEA WB Gopeshwar | See Pic |
16. | 25-03-2017 | Ch 1.650 | Top of wall in1:5 cement mortar | Kirti Vardhan Negi | AE | DEA WB Gopeshwar | See Pic |
17. | 25-03-2017 | Ch 1.650 | Checking of road width | Kirti Vardhan Negi | AE | DEA WB Gopeshwar | See Pic |
18. | 27-01-2017 | Ch 0 160 | Checking of G2 by chief sir | Kirti Vardhan Negi | AE | DEA WB Gopeshwar | See Pic |
19. | 27-01-2017 | Ch 0.440 | Checking of slope of Rwall by EE sir | Kirti Vardhan Negi | AE | DEA WB Gopeshwar | See Pic |
20. | 22-12-2016 | 1.050 | WC work in progress | Pankaj Singh Rawat | Site Supervisor | DSC1 R&B WB Chamoli | See Pic |
|
|