Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/PWD/02/38/RD/108 Agreement signed
Project: UDRP-RB Package No.: 119 Package Name: UDRP/PWD/02/38/RD/108 Sanction Cost: 889.84  lakhs
District: Chamoli Block: Karnaprayag Constituency: Karanprayag Circle: Rudraprayag WB Circle
DEA: DEA Gopeshwar DSC: Yongma Engineering Co. Ltd. DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  1238   Gauchar Shail Dua MR (10.000 KM.) (completed)
Procurement:
Package No.: 119        Package Name: UDRP/PWD/02/38/RD/108        Tender Date: 27-06-2015        Current Status: Agreement signed        Achieved on Date: 02-12-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/02/38/RD/108        Contractor Name: Sharda Associates       
Start Date: 09-12-2015        Intended Completion Date: 31-12-2017        Original End Date:  08-03-2017
Total Bond Cost: 67153711.16 (671.54 lakhs)        Variation Cost: 20538013.00 (205.38 lakhs)     Hence Total Bond Cost is   87691724.16 (876.92 lakhs) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 2048197 for 61 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence10.00 KM62.3110.00 KM10.00 KM8.4362.31
2.R/Wall, B/ Wall Type Protection works1430.00 m158.191480.00 m1480.00 m21.41158.19
3.GSB/RBI/G-110.00 KM82.2510.00 KM10.00 KM11.1482.25
4.G-210.00 KM59.8010.00 KM10.00 KM8.159.80
5.G-310.00 KM82.4410.00 KM10.00 KM11.1682.44
6.PC/CC i/c Prime Coat, Tack Coat10.00 KM117.6510.00 KM10.00 KM15.93117.65
7.Cause Way3.00 No6.821.00 No1.00 No0.926.82
8.Culverts/Scupper 23.00 No85.8222.00 No22.00 No11.6285.82
9.longitudinal Drain10000.00 m41.2710000.00 m10000.00 m5.5941.27
10.Crash Barrier950.00 m25.52950.00 m950.00 m3.4525.52
11.Parapet400.00 No12.17400.00 No400.00 No1.6512.17
12.Road Furniture153.00 No4.48153.00 No153.00 No0.614.48
Total Amount: 738.72 100   738.72
Remarks: No Remarks       Work Program Made On: 23-12-2015       Updation of work program on: 23-11-2017      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.23-January-201651.69  lakhs
2.29-February-201642.66  lakhs
3.30-April-201667.33  lakhs
4.30-June-201644.80  lakhs
5.30-August-201635.78  lakhs
6.30-September-201647.75  lakhs
7.08-December-201645.89  lakhs
8.03-February-201765.46  lakhs
9.28-February-201729.03  lakhs
10.22-March-201758.86  lakhs
11.31-March-201729.46  lakhs
12.25-May-201798.29  lakhs
13.14-July-201740.35  lakhs
14.13-October-2017106.21  lakhs
15.19-December-201778.37  lakhs
16.30-May-201820.98  lakhs
17.12-September-201814.03  lakhs
Total 876.94  lakhs
% Payment 100 %
Advance Amount:  147.71  lakhs        Recovered Amount:  127.81  lakhs        Balance to be Recovered  19.90  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 155     No. of Test Done : 171      No. of Test Passed : 151      No. of Test Failed : 20   Test report of this package
Number of Pics Available on Web Repository: 182
Number of Notice(s) issued: 73

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.20-11-20170.840Consultation with local people Mr pulsar Lal and hagfish lalAshwani KumarREDSC4 R&B WB Chamoli See Pic
2.20-11-20170.870Checking slope of Retaining wall found 1:3Ashwani KumarREDSC4 R&B WB Chamoli See Pic
3.20-11-20170.470Work of Retaining wall in progressAshwani KumarREDSC4 R&B WB Chamoli See Pic
4.23-07-2017Ch. 7+050Road damage due to heavy RainSohanbir SinghJEUDRP R&B Chamoli See Pic
5.23-07-2017Ch.0+880Consultation with local peopleSohanbir SinghJEUDRP R&B Chamoli See Pic
6.22-07-2017Ch. 6+450Slip clearanceSohanbir SinghJEUDRP R&B Chamoli See Pic
7.22-07-2017Ch.0+390Old R/W damage due to Heavy RainSohanbir SinghJEUDRP R&B Chamoli See Pic
8.14-04-2017LabAIV test of G3 material found 24percentKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
9.14-04-2017Checking 8.060Thicknesses checking of pc by EE sir found 20mmKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
10.14-04-2017Ch 8.040Laying of pcKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
11.14-04-2017Ch 8.040Rolling of seal coatKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
12.25-03-2017Ch 9.150Bitumen extraction testKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
13.25-03-2017Ch9.190Thickness checking of pcKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
14.25-03-2017Ch 9.190Seal coat layingKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
15.25-03-2017Ch 6.950Plum wall for hp band protectionKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
16.25-03-2017Ch 1.650Top of wall in1:5 cement mortarKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
17.25-03-2017Ch 1.650Checking of road widthKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
18.27-01-2017Ch 0 160Checking of G2 by chief sirKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
19.27-01-2017Ch 0.440Checking of slope of Rwall by EE sirKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
20.22-12-20161.050WC work in progressPankaj Singh RawatSite SupervisorDSC1 R&B WB Chamoli See Pic