Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/PWD/02/38/RD/107 Agreement signed
Project: UDRP-RB Package No.: 118 Package Name: UDRP/PWD/02/38/RD/107 Sanction Cost: 661.61  lakhs
District: Chamoli Block: Narain Bagar Constituency: Tharali Circle:
DEA: DEA Karanprayag DSC: Yongma Engineering Co. Ltd. DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  1299   Kulsari Gairwaram MR (9.000 KM.) (completed)
Procurement:
Package No.: 118        Package Name: UDRP/PWD/02/38/RD/107        Tender Date: 11-09-2015        Current Status: Agreement signed        Achieved on Date: 05-01-2016

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/02/38/RD/107        Contractor Name: Chaudhary Sandeep Contractor & Suppliers       
Start Date: 12-01-2016        Intended Completion Date: 31-01-2018        Original End Date:  11-04-2017
Total Bond Cost: 51751924.84 (517.52 lakhs)        Variation Cost: 11656779.53 (116.57 lakhs)     Hence Total Bond Cost is   63408704.37 (634.09 lakhs) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 2199460 for 85 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence8.70 KM81.308.70 KM8.70 KM12.4781.30
2.R/Wall, B/ Wall Type Protection works2375.00 m221.192375.00 m2375.00 m33.92221.19
3.GSB/RBI/G-14.20 KM29.114.20 KM4.20 KM4.4629.11
4.G-24.40 KM35.444.40 KM4.40 KM5.4435.44
5.G-35.20 KM50.905.20 KM5.20 KM7.850.90
6.PC/CC i/c Prime Coat, Tack Coat8.30 KM89.368.30 KM8.30 KM13.789.36
7.Cause Way5.00 No18.765.00 No5.00 No2.8818.76
8.Culverts/Scupper 20.00 No66.7820.00 No20.00 No10.2466.78
9.longitudinal Drain8500.00 m33.008500.00 m8500.00 m5.0633.00
10.Parapet586.00 No17.62586.00 No586.00 No2.717.62
11.Road Furniture103.00 No2.22103.00 No103.00 No0.342.22
12.Env. Man & Moni Plan1.00 Job6.491.00 Job1.00 Job16.49
Total Amount: 652.17 100   652.17
Remarks: No Remarks       Work Program Made On: 28-01-2016       Updation of work program on: 02-08-2019      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.28-March-201628.64  lakhs
2.11-May-201638.42  lakhs
3.25-May-201620.31  lakhs
4.30-June-201640.07  lakhs
5.31-August-201630.69  lakhs
6.26-October-201627.97  lakhs
7.17-December-201653.11  lakhs
8.02-February-201717.11  lakhs
9.28-February-201761.45  lakhs
10.24-March-201719.23  lakhs
11.20-May-201714.33  lakhs
12.24-June-201752.46  lakhs
13.28-July-201714.45  lakhs
14.13-October-201724.44  lakhs
15.31-October-201733.52  lakhs
16.23-November-201744.13  lakhs
17.28-February-201843.37  lakhs
18.27-March-201834.76  lakhs
19.10-August-201832.47  lakhs
20.25-September-20183.15  lakhs
21.27-February-201918.08  lakhs
Total 652.16  lakhs
% Payment 102.85 %
Advance Amount:  20.31  lakhs        Recovered Amount:  0.00  lakhs        Balance to be Recovered  20.31  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 322     No. of Test Done : 405      No. of Test Passed : 361      No. of Test Failed : 44   Test report of this package
Number of Pics Available on Web Repository: 83
Number of Notice(s) issued: 76

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.04-04-2018At KM 9Visit of CE sir and instructions given for rectification of defects and handover to civil division without any further delayRajan NautiyalJEUDRP R&B Chakrata See Pic
2.23-03-2018At ch 3+380Sampling for Third party testing of P. C. workRajan NautiyalJEUDRP R&B Chakrata See Pic
3.23-03-2018At Ch 3+250Core cutting for third party testingRajan NautiyalJEUDRP R&B Chakrata See Pic
4.23-03-2018At Ch 3+000Core cutting for Third party testingRajan NautiyalJEUDRP R&B Chakrata See Pic
5.23-03-2018At Ch 1+650Core cutting for Third party testing of CC work.Rajan NautiyalJEUDRP R&B Chakrata See Pic
6.23-01-2018At Ch 3+225Checking of CC Panel by EE sirRajan NautiyalJEUDRP R&B Chakrata See Pic
7.23-01-2018At KM 3+000Checking of CC and Plum work by EE sirRajan NautiyalJEUDRP R&B Chakrata See Pic
8.23-01-2018At Ch 1+500C C Panel M30 Checking by EE sir and instructions for finishing work has givenRajan NautiyalJEUDRP R&B Chakrata See Pic
9.23-01-2018At Ch 3/25Coolie wall workRajan NautiyalJEUDRP R&B Chakrata See Pic
10.23-01-2018At CH 3+000Dismantling of CC panel (due to poor quality)Rajan NautiyalJEUDRP R&B Chakrata See Pic
11.21-01-2018Ch 0.400-0.425Visit by PPE's expert Mr Arun Tyagi and check the ppe's of labour found okDhwajvir SinghJEUDRP R&B Karnprayag See Pic
12.11-01-2018At Ch 5/21Collie wall work found satisfactoryRajan NautiyalJEUDRP R&B Chakrata See Pic
13.11-01-2018At Ch 3+250Kharinja work rejectedRajan NautiyalJEUDRP R&B Chakrata See Pic
14.11-01-2018At Ch 3+350CC panel rejected due to excess water and not using vibratorRajan NautiyalJEUDRP R&B Chakrata See Pic
15.11-01-2018At Laboratoryconcrete Cube test is in progress of CC road M30Rajan NautiyalJEUDRP R&B Chakrata See Pic
16.12-12-2017At Ch 0+000KM stone, Direction and information board fixed completedRajan NautiyalJEUDRP R&B Chakrata See Pic
17.26-11-2017At Ch 1+640 to 1+660C C road concrete Work done Without surface roughing and neend improvement in camberRajan NautiyalJEUDRP R&B Chakrata See Pic
18.26-11-2017At Ch 1+650Parapet construction in progressRajan NautiyalJEUDRP R&B Chakrata See Pic
19.26-11-2017At Ch 2+700U Drain workRajan NautiyalJEUDRP R&B Chakrata See Pic
20.16-11-2017At Ch 4+830Bridle Way construction for villageRajan NautiyalJEUDRP R&B Chakrata See Pic