UDRP/PWD/02/36/RD/106
Agreement signed
|
Project: |
UDRP-RB |
Package No.: |
117 |
Package Name: |
UDRP/PWD/02/36/RD/106 |
Sanction Cost: |
1245.39 lakhs |
District: |
Chamoli |
Block: |
Gairsain |
Constituency: |
Karanprayag |
Circle: |
Rudraprayag WB Circle |
DEA: |
DEA Gopeshwar |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
only Supervision |
No.of Sub project : |
2 |
Subproject in this package |
1 1222 Aagerchatti Jingod Motor Road (7.000 KM.) (completed) | 2 1267 Sarkot Sampark Road (5.500 KM.) (completed) |
|
Procurement: |
Package No.: 117
Package Name: UDRP/PWD/02/36/RD/106
Tender Date: 23-05-2015
Current Status: Agreement signed
Achieved on Date: 06-08-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/02/36/RD/106
Contractor Name: Singla Construction Limited
|
Start Date: 13-08-2015
Intended Completion Date: 14-05-2017
Original End Date: 12-11-2016
|
Total Bond Cost: 103206509.48 (1032.07 lakhs)
Variation Cost: 13196287.93 (131.96 lakhs) Hence Total Bond Cost is 116402797.41 (1164.03 lakhs)
|
LD Analysis for Milestone1: calculated LD is Rs 2941371 for 57 days
LD Analysis for Milestone2: calculated LD is Rs 4025034 for 78 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Hill side Cutting & Slip clearence | 12.50 KM | 25.54 | 12.50 KM | 12.50 KM | 3.33 | 25.54 | 2. | R/Wall, B/ Wall Type Protection works | 4609.00 m | 311.50 | 4609.00 m | 4609.00 m | 39.94 | 311.50 | 3. | G-2 | 19.50 KM | 133.91 | 19.50 KM | 19.50 KM | 17.1 | 133.91 | 4. | G-3 | 12.50 KM | 89.31 | 12.50 KM | 12.50 KM | 11.41 | 89.31 | 5. | PC/CC i/c Prime Coat, Tack Coat | 12.50 KM | 99.08 | 12.50 KM | 12.50 KM | 12.47 | 99.08 | 6. | Cause Way | 10.00 No | 11.95 | 10.00 No | 10.00 No | 1.52 | 11.95 | 7. | Culverts/Scupper | 72.00 No | 64.68 | 72.00 No | 72.00 No | 8.23 | 64.68 | 8. | longitudinal Drain | 12000.00 m | 31.06 | 12000.00 m | 12000.00 m | 3.88 | 31.06 | 9. | Crash Barrier | 0.00 m | 0.00 | 0.00 m | 0.00 m | 0 | 0.00 | 10. | Parapet | 0.00 No | 0.00 | 0.00 No | 0.00 No | 0 | 0.00 | 11. | Road Furniture | 222.00 No | 16.29 | 222.00 No | 222.00 No | 2.12 | 16.29 |
Total Amount: |
783.32 |
|
100 |
783.32 |
|
Remarks:
No Remarks
Work Program Made On:
25-09-2015
Updation of work program on:
26-05-2018
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 19-October-2015 | 40.56 lakhs |
2. | 30-November-2015 | 30.94 lakhs |
3. | 04-March-2016 | 80.95 lakhs |
4. | 21-July-2016 | 110.37 lakhs |
5. | 31-August-2016 | 101.27 lakhs |
6. | 27-October-2016 | 83.41 lakhs |
7. | 30-December-2016 | 28.49 lakhs |
8. | 28-February-2017 | 19.28 lakhs |
9. | 24-March-2017 | 54.29 lakhs |
10. | 20-May-2017 | 177.66 lakhs |
11. | 25-November-2017 | 56.53 lakhs |
12. | 28-February-2018 | 61.66 lakhs |
13. | 28-April-2018 | 89.00 lakhs |
14. | 31-January-2016 | 43.15 lakhs |
15. | 03-May-2016 | 124.04 lakhs |
16. | 16-October-2017 | 40.12 lakhs |
17. | 29-June-2018 | 23.34 lakhs |
Total |
1165.06 lakhs |
% Payment |
100.09 % |
|
Advance Amount: 140.00 lakhs
Recovered Amount: 140.00 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 215 |
Number of Notice(s) issued: 78 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 12-04-2017 | 1.475 | Seal | Manish Rana | JE | UDRP R&B Gopeshwar | See Pic |
2. | 12-04-2017 | 1.460 | Seal coat work | Manish Rana | JE | UDRP R&B Gopeshwar | See Pic |
3. | 12-04-2017 | Chainage-3.780 | Damage R/wall reconstruction work | Manish Rana | JE | UDRP R&B Gopeshwar | See Pic |
4. | 12-01-2017 | 0.530 | Construction of toe wall in RR 1:5.
Without using safety measures | Alok Chandra Joshi | Site Supervisor | DSC1 R&B WB Chamoli | See Pic |
5. | 02-12-2016 | Ch 3.800km | R/wall rejected due to bad masonry work | Manish Rana | JE | UDRP R&B Gopeshwar | See Pic |
6. | 01-12-2016 | Chainage-4.225km | Thickness checking of pc G2 1st & 2nd layer & G3 by pwd ce sir | Manish Rana | JE | UDRP R&B Gopeshwar | See Pic |
7. | 01-12-2016 | Chainage-6.950km | Thickness checking by pwd chief engineer sir | Manish Rana | JE | UDRP R&B Gopeshwar | See Pic |
8. | 01-12-2016 | Ch.6.950km | Pwd chief engineer sir visit | Manish Rana | JE | UDRP R&B Gopeshwar | See Pic |
9. | 28-10-2016 | 5.190 | Taking Joint Measurement of PC Work | Alok Chandra Joshi | Site Supervisor | DSC1 R&B WB Chamoli | See Pic |
10. | 28-10-2016 | 2.700 | Jointly checking of thickness of PC Work | Alok Chandra Joshi | Site Supervisor | DSC1 R&B WB Chamoli | See Pic |
11. | 28-10-2016 | 2.950 | Gradiation test of WBM G3by RE Sir | Alok Chandra Joshi | Site Supervisor | DSC1 R&B WB Chamoli | See Pic |
12. | 28-10-2016 | 2.800 | Bitumin Extraction test in site | Alok Chandra Joshi | Site Supervisor | DSC1 R&B WB Chamoli | See Pic |
13. | 28-10-2016 | 2.625 | Thickness checking by RE Sir | Alok Chandra Joshi | Site Supervisor | DSC1 R&B WB Chamoli | See Pic |
14. | 26-10-2016 | 4.740 | PC WORK IN PROGRESS | Alok Chandra Joshi | Site Supervisor | DSC1 R&B WB Chamoli | See Pic |
15. | 17-10-2016 | 5.250 | Bitumin Extraction test in site lab | Alok Chandra Joshi | Site Supervisor | DSC1 R&B WB Chamoli | See Pic |
16. | 17-10-2016 | 5.075 | Seal Coat work in progress | Alok Chandra Joshi | Site Supervisor | DSC1 R&B WB Chamoli | See Pic |
17. | 17-10-2016 | 5.380 | Thickness checking of PC Work by RE Sir | Alok Chandra Joshi | Site Supervisor | DSC1 R&B WB Chamoli | See Pic |
18. | 17-10-2016 | 5.125 | Rolling of seal coat surface | Alok Chandra Joshi | Site Supervisor | DSC1 R&B WB Chamoli | See Pic |
19. | 15-10-2016 | 5.725 | Tack Coat & PC Work in progress | Alok Chandra Joshi | Site Supervisor | DSC1 R&B WB Chamoli | See Pic |
20. | 11-10-2016 | 5.375 | Seal Coat Work in Progress | Alok Chandra Joshi | Site Supervisor | DSC1 R&B WB Chamoli | See Pic |
|
|