Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/PWD/02/36/RD/105 Agreement signed
Project: UDRP-RB Package No.: 116 Package Name: UDRP/PWD/02/36/RD/105 Sanction Cost: 1354.32  lakhs
District: Chamoli Block: Karnaprayag Constituency: Karanprayag Circle: Rudraprayag WB Circle
DEA: DEA Karanprayag DSC: Yongma Engineering Co. Ltd. DSC Scope: only Supervision No.of Sub project : 3
Subproject in this package
1  1220   Sunali - Dasholikhal MR (15.400 KM.) (completed)
2  1255   Mitiyala - Kirsal MR (2.000 KM.) (completed)
3  1278   Ujjwalpur Saim Dharkot Motor Road (2.000 KM.) (completed)
Procurement:
Package No.: 116        Package Name: UDRP/PWD/02/36/RD/105        Tender Date: 11-09-2015        Current Status: Agreement signed        Achieved on Date: 05-01-2016

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/02/36/RD/105        Contractor Name: N P Buildwell Pvt. Ltd       
Start Date: 12-01-2016        Intended Completion Date: 10-06-2019        Original End Date:  11-04-2017
Total Bond Cost: 103646807.66 (1036.47 lakhs)        Variation Cost: 25046778.29 (250.47 lakhs)     Hence Total Bond Cost is   128693585.95 (1286.94 lakhs) 
LD Analysis for Milestone1: calculated LD is Rs 9120848 for 176 days        LD Analysis for Milestone2: calculated LD is Rs 24615925 for 475 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence17.40 KM172.4317.40 KM17.40 KM11.75172.43
2.R/Wall, B/ Wall Type Protection works4791.00 m436.704791.00 m4791.00 m34.1436.70
3.GSB/RBI/G-12.90 KM25.252.90 KM2.90 KM1.6425.25
4.G-213.62 KM71.7313.62 KM13.62 KM5.0671.73
5.G-316.23 KM145.7816.23 KM16.23 KM10.12145.78
6.PC/CC i/c Prime Coat, Tack Coat17.73 KM217.4017.73 KM17.73 KM15.39217.40
7.Cause Way22.00 No87.2922.00 No22.00 No7.187.29
8.Culverts/Scupper 32.00 No105.0832.00 No32.00 No7.67105.08
9.longitudinal Drain19400.00 m41.2719400.00 m19400.00 m3.6341.27
10.Crash Barrier1.00 m0.001.00 m1.00 m00.00
11.Parapet890.00 No28.99890.00 No890.00 No1.9128.99
12.Road Furniture416.00 No5.23416.00 No416.00 No0.435.23
13.Env. Man & Moni Plan3.00 Job13.373.00 Job3.00 Job1.2113.37
Total Amount: 1350.52 100   1350.52
Remarks: No Remarks       Work Program Made On: 11-02-2016       Updation of work program on: 02-08-2019      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.02-May-201636.13  lakhs
2.30-June-201622.92  lakhs
3.24-August-201657.16  lakhs
4.30-September-201617.00  lakhs
5.26-October-201626.05  lakhs
6.10-February-2017129.74  lakhs
7.31-March-201744.75  lakhs
8.13-October-201758.81  lakhs
9.25-November-201744.41  lakhs
10.04-January-201848.87  lakhs
11.28-February-201831.69  lakhs
12.28-March-201865.40  lakhs
13.21-May-201812.11  lakhs
14.31-May-2018100.25  lakhs
15.23-August-201857.21  lakhs
16.28-September-201815.31  lakhs
17.16-October-201826.69  lakhs
18.31-October-201846.03  lakhs
19.28-November-201839.31  lakhs
20.29-November-201833.97  lakhs
21.31-December-201845.72  lakhs
22.16-February-201958.76  lakhs
23.27-February-201916.60  lakhs
24.30-March-201958.44  lakhs
25.10-April-201918.61  lakhs
26.30-April-201921.06  lakhs
27.22-May-201966.53  lakhs
28.19-June-201948.06  lakhs
29.12-July-201982.98  lakhs
30.15-July-201919.98  lakhs
Total 1350.55  lakhs
% Payment 104.94 %
Advance Amount:  0.00  lakhs        Recovered Amount:  0.00  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 1005     No. of Test Done : 1305      No. of Test Passed : 1258      No. of Test Failed : 47   Test report of this package
Number of Pics Available on Web Repository: 103
Number of Notice(s) issued: 81

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.21-01-2019Ch 11.350Excavation for causewayNaveen Kumar SharmaAEUDRP R&B Karanprayag See Pic
2.13-12-2018Ch 8.950Taking mts of P. CNaveen Kumar SharmaAEUDRP R&B Karanprayag See Pic
3.23-11-2018Ch 9.700WBM in progressNaveen Kumar SharmaAEUDRP R&B Karanprayag See Pic
4.19-11-2018Ch 0.125Taking mts of B/WNaveen Kumar SharmaAEUDRP R&B Karanprayag See Pic
5.15-10-2018Ch 3+600 to 3+650Casting of parapet satisfactorilyDhwajvir SinghJEUDRP R&B Karnprayag See Pic
6.15-10-2018Ch 3+575 to 3+600Construction of R/W under progress, small size of stone is using, it has removed and rebuild with big size of stone.Dhwajvir SinghJEUDRP R&B Karnprayag See Pic
7.15-10-2018Ch 1+975Breaking of WBM G-3 stone aggregatesDhwajvir SinghJEUDRP R&B Karnprayag See Pic
8.26-09-2018Ch. 1.275C.C. pavement in progressNaveen Kumar SharmaAEUDRP R&B Karanprayag See Pic
9.25-09-2018Ch 1+500 to 1+525Congratulations of CC road at Dharkot village areaDhwajvir SinghJEUDRP R&B Karnprayag See Pic
10.25-09-2018Ch 0+225 to 0+250Excavation for R/W dressing required. Instruction has given for dressing.Dhwajvir SinghJEUDRP R&B Karnprayag See Pic
11.21-09-2018LabChecking of silt content in coarse sandNaveen Kumar SharmaAEUDRP R&B Karanprayag See Pic
12.19-09-2018Ch 1+900 to1+950Laying of khadenja in causeway under progressDhwajvir SinghJEUDRP R&B Karnprayag See Pic
13.19-09-2018Ch 6+500 to 6+525Road is settled due heavy rain fall on dated 09-09-3018Dhwajvir SinghJEUDRP R&B Karnprayag See Pic
14.19-09-2018Ch 4+825Old R/W damaged due to heavy rainfall on Dt 09/09/2018Dhwajvir SinghJEUDRP R&B Karnprayag See Pic
15.19-09-2018Ch 3+725 to 3+750Construction of R/W is completed satisfactorily which is damaged in rainy seasonDhwajvir SinghJEUDRP R&B Karnprayag See Pic
16.06-09-2018Ch 1.950Debris disposalDhwajvir SinghJEUDRP R&B Karnprayag See Pic
17.06-09-2018Ch 6.300Debris disposalDhwajvir SinghJEUDRP R&B Karnprayag See Pic
18.20-08-2018Ch 3+725Damage of old R/W due to heavy rainfallDhwajvir SinghJEUDRP R&B Karnprayag See Pic
19.08-08-2018Ch 4.800Clearance of land slid for opening communicationDhwajvir SinghJEUDRP R&B Karnprayag See Pic
20.08-08-2018Ch 3.425Clearance of land slidDhwajvir SinghJEUDRP R&B Karnprayag See Pic