UDRP/PWD/02/36/RD/105
Agreement signed
|
Project: |
UDRP-RB |
Package No.: |
116 |
Package Name: |
UDRP/PWD/02/36/RD/105 |
Sanction Cost: |
1354.32 lakhs |
District: |
Chamoli |
Block: |
Karnaprayag |
Constituency: |
Karanprayag |
Circle: |
Rudraprayag WB Circle |
DEA: |
DEA Karanprayag |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
only Supervision |
No.of Sub project : |
3 |
Subproject in this package |
1 1220 Sunali - Dasholikhal MR (15.400 KM.) (completed) | 2 1255 Mitiyala - Kirsal MR (2.000 KM.) (completed) | 3 1278 Ujjwalpur Saim Dharkot Motor Road (2.000 KM.) (completed) |
|
Procurement: |
Package No.: 116
Package Name: UDRP/PWD/02/36/RD/105
Tender Date: 11-09-2015
Current Status: Agreement signed
Achieved on Date: 05-01-2016 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/02/36/RD/105
Contractor Name: N P Buildwell Pvt. Ltd
|
Start Date: 12-01-2016
Intended Completion Date: 10-06-2019
Original End Date: 11-04-2017
|
Total Bond Cost: 103646807.66 (1036.47 lakhs)
Variation Cost: 25046778.29 (250.47 lakhs) Hence Total Bond Cost is 128693585.95 (1286.94 lakhs)
|
LD Analysis for Milestone1: calculated LD is Rs 9120848 for 176 days
LD Analysis for Milestone2: calculated LD is Rs 24615925 for 475 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Hill side Cutting & Slip clearence | 17.40 KM | 172.43 | 17.40 KM | 17.40 KM | 11.75 | 172.43 | 2. | R/Wall, B/ Wall Type Protection works | 4791.00 m | 436.70 | 4791.00 m | 4791.00 m | 34.1 | 436.70 | 3. | GSB/RBI/G-1 | 2.90 KM | 25.25 | 2.90 KM | 2.90 KM | 1.64 | 25.25 | 4. | G-2 | 13.62 KM | 71.73 | 13.62 KM | 13.62 KM | 5.06 | 71.73 | 5. | G-3 | 16.23 KM | 145.78 | 16.23 KM | 16.23 KM | 10.12 | 145.78 | 6. | PC/CC i/c Prime Coat, Tack Coat | 17.73 KM | 217.40 | 17.73 KM | 17.73 KM | 15.39 | 217.40 | 7. | Cause Way | 22.00 No | 87.29 | 22.00 No | 22.00 No | 7.1 | 87.29 | 8. | Culverts/Scupper | 32.00 No | 105.08 | 32.00 No | 32.00 No | 7.67 | 105.08 | 9. | longitudinal Drain | 19400.00 m | 41.27 | 19400.00 m | 19400.00 m | 3.63 | 41.27 | 10. | Crash Barrier | 1.00 m | 0.00 | 1.00 m | 1.00 m | 0 | 0.00 | 11. | Parapet | 890.00 No | 28.99 | 890.00 No | 890.00 No | 1.91 | 28.99 | 12. | Road Furniture | 416.00 No | 5.23 | 416.00 No | 416.00 No | 0.43 | 5.23 | 13. | Env. Man & Moni Plan | 3.00 Job | 13.37 | 3.00 Job | 3.00 Job | 1.21 | 13.37 |
Total Amount: |
1350.52 |
|
100 |
1350.52 |
|
Remarks:
No Remarks
Work Program Made On:
11-02-2016
Updation of work program on:
02-08-2019
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 02-May-2016 | 36.13 lakhs |
2. | 30-June-2016 | 22.92 lakhs |
3. | 24-August-2016 | 57.16 lakhs |
4. | 30-September-2016 | 17.00 lakhs |
5. | 26-October-2016 | 26.05 lakhs |
6. | 10-February-2017 | 129.74 lakhs |
7. | 31-March-2017 | 44.75 lakhs |
8. | 13-October-2017 | 58.81 lakhs |
9. | 25-November-2017 | 44.41 lakhs |
10. | 04-January-2018 | 48.87 lakhs |
11. | 28-February-2018 | 31.69 lakhs |
12. | 28-March-2018 | 65.40 lakhs |
13. | 21-May-2018 | 12.11 lakhs |
14. | 31-May-2018 | 100.25 lakhs |
15. | 23-August-2018 | 57.21 lakhs |
16. | 28-September-2018 | 15.31 lakhs |
17. | 16-October-2018 | 26.69 lakhs |
18. | 31-October-2018 | 46.03 lakhs |
19. | 28-November-2018 | 39.31 lakhs |
20. | 29-November-2018 | 33.97 lakhs |
21. | 31-December-2018 | 45.72 lakhs |
22. | 16-February-2019 | 58.76 lakhs |
23. | 27-February-2019 | 16.60 lakhs |
24. | 30-March-2019 | 58.44 lakhs |
25. | 10-April-2019 | 18.61 lakhs |
26. | 30-April-2019 | 21.06 lakhs |
27. | 22-May-2019 | 66.53 lakhs |
28. | 19-June-2019 | 48.06 lakhs |
29. | 12-July-2019 | 82.98 lakhs |
30. | 15-July-2019 | 19.98 lakhs |
Total |
1350.55 lakhs |
% Payment |
104.94 % |
|
Advance Amount: 0.00 lakhs
Recovered Amount: 0.00 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 103 |
Number of Notice(s) issued: 81 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 21-01-2019 | Ch 11.350 | Excavation for causeway | Naveen Kumar Sharma | AE | UDRP R&B Karanprayag | See Pic |
2. | 13-12-2018 | Ch 8.950 | Taking mts of P. C | Naveen Kumar Sharma | AE | UDRP R&B Karanprayag | See Pic |
3. | 23-11-2018 | Ch 9.700 | WBM in progress | Naveen Kumar Sharma | AE | UDRP R&B Karanprayag | See Pic |
4. | 19-11-2018 | Ch 0.125 | Taking mts of B/W | Naveen Kumar Sharma | AE | UDRP R&B Karanprayag | See Pic |
5. | 15-10-2018 | Ch 3+600 to 3+650 | Casting of parapet satisfactorily | Dhwajvir Singh | JE | UDRP R&B Karnprayag | See Pic |
6. | 15-10-2018 | Ch 3+575 to 3+600 | Construction of R/W under progress, small size of stone is using, it has removed and rebuild with big size of stone. | Dhwajvir Singh | JE | UDRP R&B Karnprayag | See Pic |
7. | 15-10-2018 | Ch 1+975 | Breaking of WBM G-3 stone aggregates | Dhwajvir Singh | JE | UDRP R&B Karnprayag | See Pic |
8. | 26-09-2018 | Ch. 1.275 | C.C. pavement in progress | Naveen Kumar Sharma | AE | UDRP R&B Karanprayag | See Pic |
9. | 25-09-2018 | Ch 1+500 to 1+525 | Congratulations of CC road at Dharkot village area | Dhwajvir Singh | JE | UDRP R&B Karnprayag | See Pic |
10. | 25-09-2018 | Ch 0+225 to 0+250 | Excavation for R/W dressing required. Instruction has given for dressing. | Dhwajvir Singh | JE | UDRP R&B Karnprayag | See Pic |
11. | 21-09-2018 | Lab | Checking of silt content in coarse sand | Naveen Kumar Sharma | AE | UDRP R&B Karanprayag | See Pic |
12. | 19-09-2018 | Ch 1+900 to1+950 | Laying of khadenja in causeway under progress | Dhwajvir Singh | JE | UDRP R&B Karnprayag | See Pic |
13. | 19-09-2018 | Ch 6+500 to 6+525 | Road is settled due heavy rain fall on dated 09-09-3018 | Dhwajvir Singh | JE | UDRP R&B Karnprayag | See Pic |
14. | 19-09-2018 | Ch 4+825 | Old R/W damaged due to heavy rainfall on Dt 09/09/2018 | Dhwajvir Singh | JE | UDRP R&B Karnprayag | See Pic |
15. | 19-09-2018 | Ch 3+725 to 3+750 | Construction of R/W is completed satisfactorily which is damaged in rainy season | Dhwajvir Singh | JE | UDRP R&B Karnprayag | See Pic |
16. | 06-09-2018 | Ch 1.950 | Debris disposal | Dhwajvir Singh | JE | UDRP R&B Karnprayag | See Pic |
17. | 06-09-2018 | Ch 6.300 | Debris disposal | Dhwajvir Singh | JE | UDRP R&B Karnprayag | See Pic |
18. | 20-08-2018 | Ch 3+725 | Damage of old R/W due to heavy rainfall | Dhwajvir Singh | JE | UDRP R&B Karnprayag | See Pic |
19. | 08-08-2018 | Ch 4.800 | Clearance of land slid for opening communication | Dhwajvir Singh | JE | UDRP R&B Karnprayag | See Pic |
20. | 08-08-2018 | Ch 3.425 | Clearance of land slid | Dhwajvir Singh | JE | UDRP R&B Karnprayag | See Pic |
|
|