Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/PWD/07/15/RD/103 Agreement signed
Project: UDRP-RB Package No.: 114 Package Name: UDRP/PWD/07/15/RD/103 Sanction Cost: 972.41  lakhs
District: Pithoragarh Block: Gangolihat Constituency: Gangolihat Circle: Pithoragarh WB Circle
DEA: DEA Munsyari DSC: Yongma Engineering Co. Ltd. DSC Scope: only Supervision No.of Sub project : 1
Subproject in this package
1  2333   Madanpur Nani motor road (10.200 KM.) (completed)
Procurement:
Package No.: 114        Package Name: UDRP/PWD/07/15/RD/103        Tender Date: 10-04-2015        Current Status: Agreement signed        Achieved on Date: 21-07-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/07/15/RD/103        Contractor Name: GDS Infrastructure       
Start Date: 28-07-2015        Intended Completion Date: 31-05-2018        Original End Date:  27-10-2016
Total Bond Cost: 76467874.61 (764.68 lakhs)        Variation Cost: 16394378.87 (163.94 lakhs)     Hence Total Bond Cost is   92862253.48 (928.62 lakhs) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 688212 for 18 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence10.12 KM98.6410.12 KM10.12 KM10.998.64
2.R/Wall, B/ Wall Type Protection works2567.00 m269.992567.00 m2567.00 m29.84269.99
3.G-210.12 KM115.3910.12 KM10.12 KM12.75115.39
4.G-310.12 KM75.4710.12 KM10.12 KM8.3475.47
5.PC/CC i/c Prime Coat, Tack Coat10.12 KM127.7110.12 KM10.12 KM14.12127.71
6.Cause Way6.00 No20.875.00 No5.00 No2.3120.87
7.Culverts/Scupper 38.00 No105.0438.00 No38.00 No11.61105.04
8.longitudinal Drain9271.00 m35.439271.00 m9271.00 m3.9235.43
9.Crash Barrier0.00 m0.000.00 m0.00 m00.00
10.Parapet532.00 No5.74430.00 No430.00 No0.635.74
11.Road Furniture955.00 No9.12955.00 No955.00 No1.019.12
12.Other Allied Works & Finishing Work 2.00 Job41.342.00 Job2.00 Job4.5741.34
Total Amount: 904.74 100   904.74
Remarks: No Remarks       Work Program Made On: 28-09-2015       Updation of work program on: 29-11-2017      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.30-September-201546.66  lakhs
2.31-October-201537.62  lakhs
3.30-December-201588.56  lakhs
4.18-February-201650.22  lakhs
5.09-March-201640.83  lakhs
6.30-March-201627.94  lakhs
7.24-May-201670.12  lakhs
8.30-June-201634.60  lakhs
9.31-August-201613.75  lakhs
10.30-September-201645.93  lakhs
11.22-November-201622.42  lakhs
12.02-January-201719.10  lakhs
13.31-May-201730.71  lakhs
14.21-June-201736.70  lakhs
15.31-August-20176.36  lakhs
16.10-November-201710.76  lakhs
17.26-November-201748.20  lakhs
18.07-December-201731.52  lakhs
19.30-December-201734.25  lakhs
20.16-February-201814.46  lakhs
21.27-February-201846.26  lakhs
22.27-March-201851.68  lakhs
23.23-May-201838.70  lakhs
24.29-September-201881.07  lakhs
25.27-October-201815.00  lakhs
26.22-June-20194.88  lakhs
Total 948.3  lakhs
% Payment 102.12 %
Advance Amount:  0.00  lakhs        Recovered Amount:  0.00  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 500     No. of Test Done : 500      No. of Test Passed : 500      No. of Test Failed : 0   Test report of this package
Number of Pics Available on Web Repository: 235
Number of Notice(s) issued: 83

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.14-01-20188+900Sure visit with EESir and AE sirDinesh KumarREDSC4 R&B WB Munsyari See Pic
2.05-01-20186+050Parapet work in progressDinesh KumarREDSC4 R&B WB Munsyari See Pic
3.06-10-20178+600Width checking of WBM 1st layerDinesh KumarREDSC4 R&B WB Munsyari See Pic
4.06-10-20179+850Width checking during hill cuttingDinesh KumarREDSC4 R&B WB Munsyari See Pic
5.21-03-20177.450Plum work in progressPramod JoshiSite EngineerDSC4 R&B WB Munsyari See Pic
6.09-01-20176.700Hillside cuttingPramod JoshiSite EngineerDSC4 R&B WB Munsyari See Pic
7.07-01-20176.600Hillside cuttingPramod JoshiSite EngineerDSC4 R&B WB Munsyari See Pic
8.19-12-20166.425Hillside cuttingPramod JoshiSite EngineerDSC4 R&B WB Munsyari See Pic
9.19-12-20166.425Hillside cuttingPramod JoshiSite EngineerDSC4 R&B WB Munsyari See Pic
10.17-12-20161+300AIV Test for G2 aggregate result found 27 %Dinesh KumarREDSC4 R&B WB Munsyari See Pic
11.17-12-20162+125Dry R/ W work in progressDinesh KumarREDSC4 R&B WB Munsyari See Pic
12.03-12-20162+300Site visit of TL sir and EE sir at ch 2+300Dinesh KumarREDSC4 R&B WB Munsyari See Pic
13.03-12-20162+700Rolling on pc surfaceDinesh KumarREDSC4 R&B WB Munsyari See Pic
14.08-11-20162.360Thickness checking of pc found 23mmPramod JoshiSite EngineerDSC4 R&B WB Munsyari See Pic
15.08-11-20162.350PC work in progressPramod JoshiSite EngineerDSC4 R&B WB Munsyari See Pic
16.06-11-20161.350PC work in progressPramod JoshiSite EngineerDSC4 R&B WB Munsyari See Pic
17.05-11-20161.800Premix carpetPramod JoshiSite EngineerDSC4 R&B WB Munsyari See Pic
18.05-11-20161.325Ambient air quality test runningPramod JoshiSite EngineerDSC4 R&B WB Munsyari See Pic
19.03-11-2016Chainage 1.400PC work in progressPrem PrakashAEUDRP R&B Munsyari See Pic
20.02-11-2016Chainage 1.500PC work in progressPrem PrakashAEUDRP R&B Munsyari See Pic