UDRP/PWD/07/15/RD/103
Agreement signed
|
Project: |
UDRP-RB |
Package No.: |
114 |
Package Name: |
UDRP/PWD/07/15/RD/103 |
Sanction Cost: |
972.41 lakhs |
District: |
Pithoragarh |
Block: |
Gangolihat |
Constituency: |
Gangolihat |
Circle: |
Pithoragarh WB Circle |
DEA: |
DEA Munsyari |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
only Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 2333 Madanpur Nani motor road (10.200 KM.) (completed) |
|
Procurement: |
Package No.: 114
Package Name: UDRP/PWD/07/15/RD/103
Tender Date: 10-04-2015
Current Status: Agreement signed
Achieved on Date: 21-07-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/07/15/RD/103
Contractor Name: GDS Infrastructure
|
Start Date: 28-07-2015
Intended Completion Date: 31-05-2018
Original End Date: 27-10-2016
|
Total Bond Cost: 76467874.61 (764.68 lakhs)
Variation Cost: 16394378.87 (163.94 lakhs) Hence Total Bond Cost is 92862253.48 (928.62 lakhs)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: calculated LD is Rs 688212 for 18 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Hill side Cutting & Slip clearence | 10.12 KM | 98.64 | 10.12 KM | 10.12 KM | 10.9 | 98.64 | 2. | R/Wall, B/ Wall Type Protection works | 2567.00 m | 269.99 | 2567.00 m | 2567.00 m | 29.84 | 269.99 | 3. | G-2 | 10.12 KM | 115.39 | 10.12 KM | 10.12 KM | 12.75 | 115.39 | 4. | G-3 | 10.12 KM | 75.47 | 10.12 KM | 10.12 KM | 8.34 | 75.47 | 5. | PC/CC i/c Prime Coat, Tack Coat | 10.12 KM | 127.71 | 10.12 KM | 10.12 KM | 14.12 | 127.71 | 6. | Cause Way | 6.00 No | 20.87 | 5.00 No | 5.00 No | 2.31 | 20.87 | 7. | Culverts/Scupper | 38.00 No | 105.04 | 38.00 No | 38.00 No | 11.61 | 105.04 | 8. | longitudinal Drain | 9271.00 m | 35.43 | 9271.00 m | 9271.00 m | 3.92 | 35.43 | 9. | Crash Barrier | 0.00 m | 0.00 | 0.00 m | 0.00 m | 0 | 0.00 | 10. | Parapet | 532.00 No | 5.74 | 430.00 No | 430.00 No | 0.63 | 5.74 | 11. | Road Furniture | 955.00 No | 9.12 | 955.00 No | 955.00 No | 1.01 | 9.12 | 12. | Other Allied Works & Finishing Work | 2.00 Job | 41.34 | 2.00 Job | 2.00 Job | 4.57 | 41.34 |
Total Amount: |
904.74 |
|
100 |
904.74 |
|
Remarks:
No Remarks
Work Program Made On:
28-09-2015
Updation of work program on:
29-11-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 30-September-2015 | 46.66 lakhs |
2. | 31-October-2015 | 37.62 lakhs |
3. | 30-December-2015 | 88.56 lakhs |
4. | 18-February-2016 | 50.22 lakhs |
5. | 09-March-2016 | 40.83 lakhs |
6. | 30-March-2016 | 27.94 lakhs |
7. | 24-May-2016 | 70.12 lakhs |
8. | 30-June-2016 | 34.60 lakhs |
9. | 31-August-2016 | 13.75 lakhs |
10. | 30-September-2016 | 45.93 lakhs |
11. | 22-November-2016 | 22.42 lakhs |
12. | 02-January-2017 | 19.10 lakhs |
13. | 31-May-2017 | 30.71 lakhs |
14. | 21-June-2017 | 36.70 lakhs |
15. | 31-August-2017 | 6.36 lakhs |
16. | 10-November-2017 | 10.76 lakhs |
17. | 26-November-2017 | 48.20 lakhs |
18. | 07-December-2017 | 31.52 lakhs |
19. | 30-December-2017 | 34.25 lakhs |
20. | 16-February-2018 | 14.46 lakhs |
21. | 27-February-2018 | 46.26 lakhs |
22. | 27-March-2018 | 51.68 lakhs |
23. | 23-May-2018 | 38.70 lakhs |
24. | 29-September-2018 | 81.07 lakhs |
25. | 27-October-2018 | 15.00 lakhs |
26. | 22-June-2019 | 4.88 lakhs |
Total |
948.3 lakhs |
% Payment |
102.12 % |
|
Advance Amount: 0.00 lakhs
Recovered Amount: 0.00 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 235 |
Number of Notice(s) issued: 83 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 14-01-2018 | 8+900 | Sure visit with EESir and AE sir | Dinesh Kumar | RE | DSC4 R&B WB Munsyari | See Pic |
2. | 05-01-2018 | 6+050 | Parapet work in progress | Dinesh Kumar | RE | DSC4 R&B WB Munsyari | See Pic |
3. | 06-10-2017 | 8+600 | Width checking of WBM 1st layer | Dinesh Kumar | RE | DSC4 R&B WB Munsyari | See Pic |
4. | 06-10-2017 | 9+850 | Width checking during hill cutting | Dinesh Kumar | RE | DSC4 R&B WB Munsyari | See Pic |
5. | 21-03-2017 | 7.450 | Plum work in progress | Pramod Joshi | Site Engineer | DSC4 R&B WB Munsyari | See Pic |
6. | 09-01-2017 | 6.700 | Hillside cutting | Pramod Joshi | Site Engineer | DSC4 R&B WB Munsyari | See Pic |
7. | 07-01-2017 | 6.600 | Hillside cutting | Pramod Joshi | Site Engineer | DSC4 R&B WB Munsyari | See Pic |
8. | 19-12-2016 | 6.425 | Hillside cutting | Pramod Joshi | Site Engineer | DSC4 R&B WB Munsyari | See Pic |
9. | 19-12-2016 | 6.425 | Hillside cutting | Pramod Joshi | Site Engineer | DSC4 R&B WB Munsyari | See Pic |
10. | 17-12-2016 | 1+300 | AIV Test for G2 aggregate result found 27 % | Dinesh Kumar | RE | DSC4 R&B WB Munsyari | See Pic |
11. | 17-12-2016 | 2+125 | Dry R/ W work in progress | Dinesh Kumar | RE | DSC4 R&B WB Munsyari | See Pic |
12. | 03-12-2016 | 2+300 | Site visit of TL sir and EE sir at ch 2+300 | Dinesh Kumar | RE | DSC4 R&B WB Munsyari | See Pic |
13. | 03-12-2016 | 2+700 | Rolling on pc surface | Dinesh Kumar | RE | DSC4 R&B WB Munsyari | See Pic |
14. | 08-11-2016 | 2.360 | Thickness checking of pc found 23mm | Pramod Joshi | Site Engineer | DSC4 R&B WB Munsyari | See Pic |
15. | 08-11-2016 | 2.350 | PC work in progress | Pramod Joshi | Site Engineer | DSC4 R&B WB Munsyari | See Pic |
16. | 06-11-2016 | 1.350 | PC work in progress | Pramod Joshi | Site Engineer | DSC4 R&B WB Munsyari | See Pic |
17. | 05-11-2016 | 1.800 | Premix carpet | Pramod Joshi | Site Engineer | DSC4 R&B WB Munsyari | See Pic |
18. | 05-11-2016 | 1.325 | Ambient air quality test running | Pramod Joshi | Site Engineer | DSC4 R&B WB Munsyari | See Pic |
19. | 03-11-2016 | Chainage 1.400 | PC work in progress | Prem Prakash | AE | UDRP R&B Munsyari | See Pic |
20. | 02-11-2016 | Chainage 1.500 | PC work in progress | Prem Prakash | AE | UDRP R&B Munsyari | See Pic |
|
|