UDRP/PWD/07/20/RD/102
Agreement signed
|
Project: |
UDRP-RB |
Package No.: |
113 |
Package Name: |
UDRP/PWD/07/20/RD/102 |
Sanction Cost: |
883.66 lakhs |
District: |
Pithoragarh |
Block: |
Munakot |
Constituency: |
Pithoragarh |
Circle: |
Pithoragarh WB Circle |
DEA: |
DEA Askot |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
Design and Supervision |
No.of Sub project : |
2 |
Subproject in this package |
1 2375 Badari kante Bora MR (6.000 KM.) (completed) | 2 2385 Jhulaghat Talesur MR (5.000 KM.) (completed) |
|
Procurement: |
Package No.: 113
Package Name: UDRP/PWD/07/20/RD/102
Tender Date: 27-06-2015
Current Status: Agreement signed
Achieved on Date: 14-12-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/07/20/RD/102
Contractor Name: Anupam Construction Co.
|
Start Date: 21-12-2015
Intended Completion Date: 15-05-2018
Original End Date: 21-03-2017
|
Total Bond Cost: 64083507.2 (640.84 lakhs)
Variation Cost: 16723036.85 (167.23 lakhs) Hence Total Bond Cost is 80806544.05 (808.07 lakhs)
|
LD Analysis for Milestone1: calculated LD is Rs 2210898 for 69 days
LD Analysis for Milestone2: calculated LD is Rs 7786206 for 243 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Hill side Cutting & Slip clearence | 5.75 KM | 42.61 | 5.05 KM | 5.05 KM | 6.23 | 42.61 | 2. | R/Wall, B/ Wall Type Protection works | 2242.00 m | 145.71 | 2242.00 m | 2242.00 m | 21.22 | 145.71 | 3. | G-2 | 22.25 KM | 127.81 | 22.25 KM | 22.25 KM | 18.63 | 127.81 | 4. | G-3 | 11.13 KM | 110.10 | 11.13 KM | 11.13 KM | 16.05 | 110.10 | 5. | PC/CC i/c Prime Coat, Tack Coat | 11.13 KM | 140.65 | 11.13 KM | 11.13 KM | 20.51 | 140.65 | 6. | Cause Way | 4.00 No | 19.58 | 4.00 No | 4.00 No | 2.85 | 19.58 | 7. | Culverts/Scupper | 13.00 No | 50.51 | 12.00 No | 12.00 No | 7.37 | 50.51 | 8. | longitudinal Drain | 10432.00 m | 22.47 | 10432.00 m | 10432.00 m | 3.28 | 22.47 | 9. | Crash Barrier | 200.00 m | 5.40 | 200.00 m | 200.00 m | 0.79 | 5.40 | 10. | Parapet | 190.00 No | 6.87 | 190.00 No | 190.00 No | 1 | 6.87 | 11. | Road Furniture | 172.00 No | 5.40 | 172.00 No | 172.00 No | 0.79 | 5.40 | 12. | Other Allied Works & Finishing Work | 2.00 Job | 8.88 | 2.00 Job | 2.00 Job | 1.3 | 8.88 |
Total Amount: |
685.99 |
|
100 |
685.99 |
|
Remarks:
No Remarks
Work Program Made On:
20-01-2016
Updation of work program on:
28-11-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 12-February-2016 | 26.53 lakhs |
2. | 19-March-2016 | 44.51 lakhs |
3. | 30-April-2016 | 15.96 lakhs |
4. | 23-June-2016 | 19.96 lakhs |
5. | 12-August-2016 | 29.47 lakhs |
6. | 31-August-2016 | 9.76 lakhs |
7. | 26-October-2016 | 27.79 lakhs |
8. | 29-November-2016 | 11.71 lakhs |
9. | 31-December-2016 | 15.24 lakhs |
10. | 31-January-2017 | 18.67 lakhs |
11. | 28-February-2017 | 11.48 lakhs |
12. | 10-March-2017 | 11.03 lakhs |
13. | 31-March-2017 | 6.63 lakhs |
14. | 15-April-2017 | 20.07 lakhs |
15. | 31-May-2017 | 12.02 lakhs |
16. | 20-June-2017 | 26.51 lakhs |
17. | 30-June-2017 | 32.50 lakhs |
18. | 03-November-2017 | 24.91 lakhs |
19. | 22-December-2017 | 26.00 lakhs |
20. | 30-December-2017 | 26.11 lakhs |
21. | 12-January-2018 | 42.24 lakhs |
22. | 16-February-2018 | 44.02 lakhs |
23. | 26-February-2018 | 16.72 lakhs |
24. | 28-March-2018 | 15.21 lakhs |
25. | 23-April-2018 | 31.08 lakhs |
26. | 27-April-2018 | 21.34 lakhs |
27. | 22-May-2018 | 49.85 lakhs |
28. | 07-June-2018 | 8.47 lakhs |
29. | 30-June-2018 | 51.17 lakhs |
30. | 08-August-2018 | 31.14 lakhs |
31. | 26-September-2018 | 37.79 lakhs |
32. | 01-November-2018 | 20.00 lakhs |
33. | 27-November-2018 | 36.24 lakhs |
34. | 21-December-2018 | 16.81 lakhs |
35. | 19-January-2019 | 26.04 lakhs |
36. | 17-June-2019 | 7.04 lakhs |
37. | 30-September-2016 | 11.63 lakhs |
Total |
883.65 lakhs |
% Payment |
109.35 % |
|
Advance Amount: 0.00 lakhs
Recovered Amount: 0.00 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 64 |
Number of Notice(s) issued: 73 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 24-04-2018 | Ch. 4+343 | Rolling of PC surface | Abid Ali Siddequee | QC | DSC4 R&B WB Pithoragarh | See Pic |
2. | 02-04-2018 | HMP | Bitumen content of PC material testing. Found OK | Abid Ali Siddequee | QC | DSC4 R&B WB Pithoragarh | See Pic |
3. | 17-01-2018 | Ch.0+400 | Rolling of PC layer | Abid Ali Siddequee | QC | DSC4 R&B WB Pithoragarh | See Pic |
4. | 16-01-2018 | HMP | Bitumen content of PC material testing at HMP. Found OK | Abid Ali Siddequee | QC | DSC4 R&B WB Pithoragarh | See Pic |
5. | 26-12-2017 | HMP | Bitumen content of PC material testing at HMP. Found OK | Abid Ali Siddequee | QC | DSC4 R&B WB Pithoragarh | See Pic |
6. | 21-12-2017 | HMP | Bitumen content of PC material testing at HMP. Found OK. | Abid Ali Siddequee | QC | DSC4 R&B WB Pithoragarh | See Pic |
7. | 10-08-2017 | 4+050 | Sattelement portion | Manoj Bhatt | RE | DSC2 R&B WB Pauri | See Pic |
8. | 05-08-2017 | Ch.4+750 | Soil sample collected for CBR Test by jointly | Abid Ali Siddequee | QC | DSC4 R&B WB Pithoragarh | See Pic |
9. | 02-08-2017 | 4+600 | Hill side portion is being moved to down | Manoj Bhatt | RE | DSC2 R&B WB Pauri | See Pic |
10. | 02-08-2017 | 4+600 | Retaining wall damaged due to hill portion sattelement | Manoj Bhatt | RE | DSC2 R&B WB Pauri | See Pic |
11. | 02-08-2017 | 4+600 | Walls damaged due to hill sattelement during rain. | Manoj Bhatt | RE | DSC2 R&B WB Pauri | See Pic |
12. | 21-05-2017 | Ch.1+575 | Gradation of WBM G3, Laying material Testing. Result Found OK | Abid Ali Siddequee | QC | DSC4 R&B WB Pithoragarh | See Pic |
13. | 08-04-2017 | Ch.0+450 | Gradation of WBM G2 testing by QC Incharge at site | Abid Ali Siddequee | QC | DSC4 R&B WB Pithoragarh | See Pic |
14. | 25-11-2016 | 1+150 | Preparation of slab casting | Shailendra Kumar Singh | RE | DSC4 R&B WB Askot | See Pic |
15. | 06-10-2016 | 3+900 | Site visit by SE, EE, tlsir | Shailendra Kumar Singh | RE | DSC4 R&B WB Askot | See Pic |
16. | 21-09-2016 | 4+270 | G2Rejected material being scraped from site | Shailendra Kumar Singh | RE | DSC4 R&B WB Askot | See Pic |
17. | 21-09-2016 | 2+925 | G2Rejected material being scraped from site | Shailendra Kumar Singh | RE | DSC4 R&B WB Askot | See Pic |
18. | 21-09-2016 | 0+975 | Hill side cutting is in progress | Shailendra Kumar Singh | RE | DSC4 R&B WB Askot | See Pic |
19. | 18-09-2016 | 0+25 | Site visit by DPM,EE sir world Bank gradation of G_2 | Shailendra Kumar Singh | RE | DSC4 R&B WB Askot | See Pic |
20. | 18-09-2016 | 1+300 | Site visit by DPM, EE sir thickness checking of G-2 | Shailendra Kumar Singh | RE | DSC4 R&B WB Askot | See Pic |
|
|