Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/PWD/07/20/RD/102 Agreement signed
Project: UDRP-RB Package No.: 113 Package Name: UDRP/PWD/07/20/RD/102 Sanction Cost: 883.66  lakhs
District: Pithoragarh Block: Munakot Constituency: Pithoragarh Circle: Pithoragarh WB Circle
DEA: DEA Askot DSC: Yongma Engineering Co. Ltd. DSC Scope: Design and Supervision No.of Sub project : 2
Subproject in this package
1  2375   Badari kante Bora MR (6.000 KM.) (completed)
2  2385   Jhulaghat Talesur MR (5.000 KM.) (completed)
Procurement:
Package No.: 113        Package Name: UDRP/PWD/07/20/RD/102        Tender Date: 27-06-2015        Current Status: Agreement signed        Achieved on Date: 14-12-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/07/20/RD/102        Contractor Name: Anupam Construction Co.       
Start Date: 21-12-2015        Intended Completion Date: 15-05-2018        Original End Date:  21-03-2017
Total Bond Cost: 64083507.2 (640.84 lakhs)        Variation Cost: 16723036.85 (167.23 lakhs)     Hence Total Bond Cost is   80806544.05 (808.07 lakhs) 
LD Analysis for Milestone1: calculated LD is Rs 2210898 for 69 days        LD Analysis for Milestone2: calculated LD is Rs 7786206 for 243 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence5.75 KM42.615.05 KM5.05 KM6.2342.61
2.R/Wall, B/ Wall Type Protection works2242.00 m145.712242.00 m2242.00 m21.22145.71
3.G-222.25 KM127.8122.25 KM22.25 KM18.63127.81
4.G-311.13 KM110.1011.13 KM11.13 KM16.05110.10
5.PC/CC i/c Prime Coat, Tack Coat11.13 KM140.6511.13 KM11.13 KM20.51140.65
6.Cause Way4.00 No19.584.00 No4.00 No2.8519.58
7.Culverts/Scupper 13.00 No50.5112.00 No12.00 No7.3750.51
8.longitudinal Drain10432.00 m22.4710432.00 m10432.00 m3.2822.47
9.Crash Barrier200.00 m5.40200.00 m200.00 m0.795.40
10.Parapet190.00 No6.87190.00 No190.00 No16.87
11.Road Furniture172.00 No5.40172.00 No172.00 No0.795.40
12.Other Allied Works & Finishing Work 2.00 Job8.882.00 Job2.00 Job1.38.88
Total Amount: 685.99 100   685.99
Remarks: No Remarks       Work Program Made On: 20-01-2016       Updation of work program on: 28-11-2017      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.12-February-201626.53  lakhs
2.19-March-201644.51  lakhs
3.30-April-201615.96  lakhs
4.23-June-201619.96  lakhs
5.12-August-201629.47  lakhs
6.31-August-20169.76  lakhs
7.26-October-201627.79  lakhs
8.29-November-201611.71  lakhs
9.31-December-201615.24  lakhs
10.31-January-201718.67  lakhs
11.28-February-201711.48  lakhs
12.10-March-201711.03  lakhs
13.31-March-20176.63  lakhs
14.15-April-201720.07  lakhs
15.31-May-201712.02  lakhs
16.20-June-201726.51  lakhs
17.30-June-201732.50  lakhs
18.03-November-201724.91  lakhs
19.22-December-201726.00  lakhs
20.30-December-201726.11  lakhs
21.12-January-201842.24  lakhs
22.16-February-201844.02  lakhs
23.26-February-201816.72  lakhs
24.28-March-201815.21  lakhs
25.23-April-201831.08  lakhs
26.27-April-201821.34  lakhs
27.22-May-201849.85  lakhs
28.07-June-20188.47  lakhs
29.30-June-201851.17  lakhs
30.08-August-201831.14  lakhs
31.26-September-201837.79  lakhs
32.01-November-201820.00  lakhs
33.27-November-201836.24  lakhs
34.21-December-201816.81  lakhs
35.19-January-201926.04  lakhs
36.17-June-20197.04  lakhs
37.30-September-201611.63  lakhs
Total 883.65  lakhs
% Payment 109.35 %
Advance Amount:  0.00  lakhs        Recovered Amount:  0.00  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 741     No. of Test Done : 752      No. of Test Passed : 745      No. of Test Failed : 7   Test report of this package
Number of Pics Available on Web Repository: 64
Number of Notice(s) issued: 73

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.24-04-2018Ch. 4+343Rolling of PC surfaceAbid Ali SiddequeeQCDSC4 R&B WB Pithoragarh See Pic
2.02-04-2018HMPBitumen content of PC material testing. Found OKAbid Ali SiddequeeQCDSC4 R&B WB Pithoragarh See Pic
3.17-01-2018Ch.0+400Rolling of PC layerAbid Ali SiddequeeQCDSC4 R&B WB Pithoragarh See Pic
4.16-01-2018HMPBitumen content of PC material testing at HMP. Found OKAbid Ali SiddequeeQCDSC4 R&B WB Pithoragarh See Pic
5.26-12-2017HMPBitumen content of PC material testing at HMP. Found OKAbid Ali SiddequeeQCDSC4 R&B WB Pithoragarh See Pic
6.21-12-2017HMPBitumen content of PC material testing at HMP. Found OK.Abid Ali SiddequeeQCDSC4 R&B WB Pithoragarh See Pic
7.10-08-20174+050Sattelement portionManoj BhattREDSC2 R&B WB Pauri See Pic
8.05-08-2017Ch.4+750Soil sample collected for CBR Test by jointlyAbid Ali SiddequeeQCDSC4 R&B WB Pithoragarh See Pic
9.02-08-20174+600Hill side portion is being moved to downManoj BhattREDSC2 R&B WB Pauri See Pic
10.02-08-20174+600Retaining wall damaged due to hill portion sattelementManoj BhattREDSC2 R&B WB Pauri See Pic
11.02-08-20174+600Walls damaged due to hill sattelement during rain.Manoj BhattREDSC2 R&B WB Pauri See Pic
12.21-05-2017Ch.1+575Gradation of WBM G3, Laying material Testing. Result Found OKAbid Ali SiddequeeQCDSC4 R&B WB Pithoragarh See Pic
13.08-04-2017Ch.0+450Gradation of WBM G2 testing by QC Incharge at siteAbid Ali SiddequeeQCDSC4 R&B WB Pithoragarh See Pic
14.25-11-20161+150Preparation of slab castingShailendra Kumar SinghREDSC4 R&B WB Askot See Pic
15.06-10-20163+900Site visit by SE, EE, tlsirShailendra Kumar SinghREDSC4 R&B WB Askot See Pic
16.21-09-20164+270G2Rejected material being scraped from siteShailendra Kumar SinghREDSC4 R&B WB Askot See Pic
17.21-09-20162+925G2Rejected material being scraped from siteShailendra Kumar SinghREDSC4 R&B WB Askot See Pic
18.21-09-20160+975Hill side cutting is in progressShailendra Kumar SinghREDSC4 R&B WB Askot See Pic
19.18-09-20160+25Site visit by DPM,EE sir world Bank gradation of G_2Shailendra Kumar SinghREDSC4 R&B WB Askot See Pic
20.18-09-20161+300Site visit by DPM, EE sir thickness checking of G-2Shailendra Kumar SinghREDSC4 R&B WB Askot See Pic