Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/PWD/07/16/RD/101 Agreement signed
Project: UDRP-RB Package No.: 112 Package Name: UDRP/PWD/07/16/RD/101 Sanction Cost: 3429.70  lakhs
District: Pithoragarh Block: Munsiari Constituency: Dharchula Circle: Pithoragarh WB Circle
DEA: DEA Munsyari DSC: Yongma Engineering Co. Ltd. DSC Scope: only Supervision No.of Sub project : 1
Subproject in this package
1  2334   Madkot Bauna (24.500 KM.) (completed)
Procurement:
Package No.: 112        Package Name: UDRP/PWD/07/16/RD/101        Tender Date: 10-04-2015        Current Status: Agreement signed        Achieved on Date: 26-08-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/07/16/RD/101        Contractor Name: M/S.Dalip Singh Adhikari       
Start Date: 02-09-2015        Intended Completion Date: 30-04-2018        Original End Date:  01-12-2016
Total Bond Cost: 210812767.6 (2108.13 lakhs)        Variation Cost: 123739530.79 (1237.4 lakhs)     Hence Total Bond Cost is   334552298.39 (3345.52 lakhs) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence23.63 KM305.6223.63 KM23.63 KM10.13305.62
2.R/Wall, B/ Wall Type Protection works9298.00 m922.949298.00 m9298.00 m30.58922.94
3.G-223.63 KM424.2823.63 KM23.63 KM14.06424.28
4.G-323.63 KM200.4423.63 KM23.63 KM6.64200.44
5.PC/CC i/c Prime Coat, Tack Coat24.13 KM376.1724.13 KM24.13 KM12.46376.17
6.Cause Way29.00 No122.6526.00 No26.00 No4.06122.65
7.Culverts/Scupper 141.00 No438.18130.00 No130.00 No14.52438.18
8.longitudinal Drain23333.00 m59.5723333.00 m23333.00 m1.9759.57
9.Crash Barrier2910.00 m72.752910.00 m2910.00 m2.4172.75
10.Parapet1231.00 No38.222300.00 No2300.00 No1.2738.22
11.Road Furniture1786.00 No19.021786.00 No1786.00 No0.6319.02
12.Other Allied Works & Finishing Work 1.00 Job38.531.00 Job1.00 Job1.2838.53
Total Amount: 3018.37 100   3018.37
Remarks: No Remarks       Work Program Made On: 28-09-2015       Updation of work program on: 13-11-2017      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.30-September-2015154.61  lakhs
2.30-October-2015107.20  lakhs
3.26-December-2015121.48  lakhs
4.30-January-2016120.51  lakhs
5.29-February-2016405.36  lakhs
6.30-March-201673.62  lakhs
7.24-May-201655.48  lakhs
8.30-July-201671.97  lakhs
9.26-October-2016123.29  lakhs
10.23-December-2016126.46  lakhs
11.30-January-2017122.28  lakhs
12.24-February-2017110.65  lakhs
13.31-March-2017195.51  lakhs
14.30-April-201779.91  lakhs
15.31-May-2017133.32  lakhs
16.21-June-2017104.87  lakhs
17.30-June-2017135.56  lakhs
18.13-July-201722.71  lakhs
19.31-August-20177.87  lakhs
20.10-November-201792.79  lakhs
21.26-November-2017140.59  lakhs
22.26-December-201795.73  lakhs
23.14-January-201855.79  lakhs
24.16-February-201895.56  lakhs
25.27-February-201888.23  lakhs
26.27-March-2018120.86  lakhs
27.20-April-2018101.97  lakhs
28.23-May-2018106.15  lakhs
29.06-June-201822.31  lakhs
30.29-September-201870.38  lakhs
31.29-October-2018152.87  lakhs
Total 3415.89  lakhs
% Payment 102.1 %
Advance Amount:  210.00  lakhs        Recovered Amount:  210.00  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 1124     No. of Test Done : 1149      No. of Test Passed : 1124      No. of Test Failed : 25   Test report of this package
Number of Pics Available on Web Repository: 276
Number of Notice(s) issued: 90

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.02-04-201822+ 650Rolling on pc surface .Dinesh KumarREDSC4 R&B WB Munsyari See Pic
2.02-04-201822+650Rolling on PC Surface with tandem Roller .Dinesh KumarREDSC4 R&B WB Munsyari See Pic
3.02-04-201822+600PC work in progressDinesh KumarREDSC4 R&B WB Munsyari See Pic
4.01-04-201822+750Rolling work on Seal coat at madkote-bona motor roadDeepak Kumar 3JEUDRP R&B Munsyari See Pic
5.01-04-201822+890Rolling work on PC at madkote-bona motor roadDeepak Kumar 3JEUDRP R&B Munsyari See Pic
6.01-04-201824+020Rolling work on PC at madkote-bona motor roadDeepak Kumar 3JEUDRP R&B Munsyari See Pic
7.01-04-201823+100Rolling work on PC at madkote-bona motor roadDeepak Kumar 3JEUDRP R&B Munsyari See Pic
8.31-03-201822+600Laying PC at madkote-bona motor roadDeepak Kumar 3JEUDRP R&B Munsyari See Pic
9.30-03-2018Km23Pri mix carpet rolling work on progressNeeraj PathakQCDSC WB Bridge Uttarkashi See Pic
10.19-03-201816+400Air pollution testAjay RathoreSite SupervisorDSC4 R&B WB Munsyari See Pic
11.19-03-201800+010Noice testAjay RathoreSite SupervisorDSC4 R&B WB Munsyari See Pic
12.03-02-201820+750Steel reinforcement for bed bl0ck in progressDinesh KumarREDSC4 R&B WB Munsyari See Pic
13.17-01-201816+400Collie wall in progressDinesh KumarREDSC4 R&B WB Munsyari See Pic
14.17-01-201816+700Parapet work in progressDinesh KumarREDSC4 R&B WB Munsyari See Pic
15.16-01-201816+700Parapet casting in progressAjay RathoreSite SupervisorDSC4 R&B WB Munsyari See Pic
16.16-01-201816+700Parapet work in progress at madkote-Bona motor roadDeepak Kumar 3JEUDRP R&B Munsyari See Pic
17.19-12-201719+850Wire crate work in progressAjay RathoreSite SupervisorDSC4 R&B WB Munsyari See Pic
18.08-12-201724+000CE sir site visitDinesh KumarREDSC4 R&B WB Munsyari See Pic
19.08-12-201724+100CE sir site visitDinesh KumarREDSC4 R&B WB Munsyari See Pic
20.08-12-201710+500Shoulder and Drain work in progressDinesh KumarREDSC4 R&B WB Munsyari See Pic