Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/PWD/08/06/RD/100 Agreement signed
Project: UDRP-RB Package No.: 111 Package Name: UDRP/PWD/08/06/RD/100 Sanction Cost: 1400.73  lakhs
District: Bageshwar Block: Kapkot Constituency: Kapkote Circle: Pithoragarh WB Circle
DEA: DEA Bageshwar DSC: Royal Haskoning DHV DSC Scope: Design and Supervision No.of Sub project : 3
Subproject in this package
1  1140   Dyuni Sukanda MR (5.000 KM.) (completed)
2  1141   Aso Bedapakhar Okhaldhar MR (6.300 KM.) (completed)
3  1142   Kapkot- Tehsil-Poling MR Phase2 (5.250 KM.) (completed)
Procurement:
Package No.: 111        Package Name: UDRP/PWD/08/06/RD/100        Tender Date: 27-06-2015        Current Status: Agreement signed        Achieved on Date: 24-09-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/08/06/RD/100        Contractor Name: Woodhill Infrastructure Ltd       
Start Date: 01-10-2015        Intended Completion Date: 23-02-2018        Original End Date:  30-12-2016
Total Bond Cost: 122411658.74 (1224.12 lakhs)        Variation Cost: 12988043.64 (129.88 lakhs)     Hence Total Bond Cost is   135399702.38 (1354 lakhs) 
LD Analysis for Milestone1: calculated LD is Rs 306030 for 5 days        LD Analysis for Milestone2: calculated LD is Rs 9303312 for 152 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence3.56 KM114.663.64 KM3.64 KM8.91114.66
2.R/Wall, B/ Wall Type Protection works3474.00 m369.714540.00 m4540.00 m28.41369.71
3.GSB/RBI/G-19.91 KM106.349.83 KM9.83 KM8.35106.34
4.G-29.55 KM57.987.39 KM7.39 KM4.3657.98
5.G-313.53 KM106.3912.53 KM12.53 KM8.31106.39
6.PC/CC i/c Prime Coat, Tack Coat14.33 KM198.2714.33 KM14.33 KM15.43198.27
7.Cause Way15.00 No49.0214.00 No14.00 No3.6749.02
8.Culverts/Scupper 38.00 No111.1428.00 No28.00 No8.53111.14
9.longitudinal Drain13273.00 m76.2613273.00 m13273.00 m5.8876.26
10.Crash Barrier969.00 m30.101543.00 m1543.00 m2.3530.10
11.Parapet385.00 No20.05434.00 No434.00 No1.5220.05
12.Road Furniture799.00 No8.89857.00 No857.00 No0.728.89
13.Other Allied Works & Finishing Work 22.50 Job46.3713.50 Job13.50 Job3.5646.37
Total Amount: 1295.18 100   1295.18
Remarks: No Remarks       Work Program Made On: 31-10-2015       Updation of work program on: 25-10-2018      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.04-January-201643.73  lakhs
2.27-January-2016101.62  lakhs
3.03-March-201679.23  lakhs
4.29-March-2016114.90  lakhs
5.31-May-201684.42  lakhs
6.11-July-201694.77  lakhs
7.30-August-201616.00  lakhs
8.24-October-20163.56  lakhs
9.08-December-20160.69  lakhs
10.23-December-20162.05  lakhs
11.31-March-201780.32  lakhs
12.30-June-2017135.71  lakhs
13.16-October-2017111.64  lakhs
14.24-November-201728.86  lakhs
15.15-December-2017120.89  lakhs
16.23-March-2018100.24  lakhs
17.18-August-201858.98  lakhs
18.16-November-201815.49  lakhs
19.03-January-201780.97  lakhs
20.08-March-201796.18  lakhs
Total 1370.25  lakhs
% Payment 101.2 %
Advance Amount:  534.52  lakhs        Recovered Amount:  534.52  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 1850     No. of Test Done : 1877      No. of Test Passed : 1838      No. of Test Failed : 39   Test report of this package
Number of Pics Available on Web Repository: 250
Number of Notice(s) issued: 89

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.15-07-2017Ch 2.360SRMD, slip due to heavy rainJagdish Narayan Meenaunknownunknown See Pic
2.15-07-2017Ch 2.600SRMD, slip due to heavy rainJagdish Narayan Meenaunknownunknown See Pic
3.15-07-2017Ch 4.100SRMD, slip but road open for traffic.Jagdish Narayan Meenaunknownunknown See Pic
4.15-07-2017Ch 4.150SRMD, slip due to heavy rainJagdish Narayan Meenaunknownunknown See Pic
5.15-07-2017Ch 4.200SRMD, slip due to heavy rainJagdish Narayan Meenaunknownunknown See Pic
6.15-07-2017Ch 4.300SRMD, slip clearanceJagdish Narayan Meenaunknownunknown See Pic
7.15-07-2017Ch 4.300SRMD, slip clearance by JCBJagdish Narayan Meenaunknownunknown See Pic
8.15-07-2017Ch 4.300SRMD, slip due to heavy rainJagdish Narayan Meenaunknownunknown See Pic
9.15-07-2017Ch 5.200SRMD, sinking due to heavy rain.Jagdish Narayan Meenaunknownunknown See Pic
10.15-07-2017Ch 4.100SRMD , slide due to heavy rainJagdish Narayan Meenaunknownunknown See Pic
11.16-06-20176+280Caution tape and safety sign board during the workManoj BhattREDSC2 R&B WB Pauri See Pic
12.16-06-20173+525WBM Grading-3 in ProgressManoj BhattREDSC2 R&B WB Pauri See Pic
13.08-06-2017Ch 2.400Instructions given by world bank missionJagdish Narayan Meenaunknownunknown See Pic
14.07-06-20176+260PC stoped due to rainManoj BhattREDSC2 R&B WB Pauri See Pic
15.25-05-2017HMPPC work startedManoj BhattREDSC2 R&B WB Pauri See Pic
16.19-05-20175+100G3 rectifiedMohd. Ifran QureshiQCDSC5 R&B WB Bageshwar See Pic
17.19-05-20170+010World bank visitMohd. Ifran QureshiQCDSC5 R&B WB Bageshwar See Pic
18.18-05-2017Ch 3+450Rejected EmulsionSanjay SinghSite SupervisorDSC5 R&B WB Bageshwar See Pic
19.16-05-20175+100Rectification on defected WBM G3 surfaceManoj BhattREDSC2 R&B WB Pauri See Pic
20.16-05-20175+100Rectification on WBM Gr3Manoj BhattREDSC2 R&B WB Pauri See Pic