UDRP/PWD/08/06/RD/100
Agreement signed
|
Project: |
UDRP-RB |
Package No.: |
111 |
Package Name: |
UDRP/PWD/08/06/RD/100 |
Sanction Cost: |
1400.73 lakhs |
District: |
Bageshwar |
Block: |
Kapkot |
Constituency: |
Kapkote |
Circle: |
Pithoragarh WB Circle |
DEA: |
DEA Bageshwar |
DSC: |
Royal Haskoning DHV |
DSC Scope: |
Design and Supervision |
No.of Sub project : |
3 |
Subproject in this package |
1 1140 Dyuni Sukanda MR (5.000 KM.) (completed) | 2 1141 Aso Bedapakhar Okhaldhar MR (6.300 KM.) (completed) | 3 1142 Kapkot- Tehsil-Poling MR Phase2 (5.250 KM.) (completed) |
|
Procurement: |
Package No.: 111
Package Name: UDRP/PWD/08/06/RD/100
Tender Date: 27-06-2015
Current Status: Agreement signed
Achieved on Date: 24-09-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/08/06/RD/100
Contractor Name: Woodhill Infrastructure Ltd
|
Start Date: 01-10-2015
Intended Completion Date: 23-02-2018
Original End Date: 30-12-2016
|
Total Bond Cost: 122411658.74 (1224.12 lakhs)
Variation Cost: 12988043.64 (129.88 lakhs) Hence Total Bond Cost is 135399702.38 (1354 lakhs)
|
LD Analysis for Milestone1: calculated LD is Rs 306030 for 5 days
LD Analysis for Milestone2: calculated LD is Rs 9303312 for 152 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Hill side Cutting & Slip clearence | 3.56 KM | 114.66 | 3.64 KM | 3.64 KM | 8.91 | 114.66 | 2. | R/Wall, B/ Wall Type Protection works | 3474.00 m | 369.71 | 4540.00 m | 4540.00 m | 28.41 | 369.71 | 3. | GSB/RBI/G-1 | 9.91 KM | 106.34 | 9.83 KM | 9.83 KM | 8.35 | 106.34 | 4. | G-2 | 9.55 KM | 57.98 | 7.39 KM | 7.39 KM | 4.36 | 57.98 | 5. | G-3 | 13.53 KM | 106.39 | 12.53 KM | 12.53 KM | 8.31 | 106.39 | 6. | PC/CC i/c Prime Coat, Tack Coat | 14.33 KM | 198.27 | 14.33 KM | 14.33 KM | 15.43 | 198.27 | 7. | Cause Way | 15.00 No | 49.02 | 14.00 No | 14.00 No | 3.67 | 49.02 | 8. | Culverts/Scupper | 38.00 No | 111.14 | 28.00 No | 28.00 No | 8.53 | 111.14 | 9. | longitudinal Drain | 13273.00 m | 76.26 | 13273.00 m | 13273.00 m | 5.88 | 76.26 | 10. | Crash Barrier | 969.00 m | 30.10 | 1543.00 m | 1543.00 m | 2.35 | 30.10 | 11. | Parapet | 385.00 No | 20.05 | 434.00 No | 434.00 No | 1.52 | 20.05 | 12. | Road Furniture | 799.00 No | 8.89 | 857.00 No | 857.00 No | 0.72 | 8.89 | 13. | Other Allied Works & Finishing Work | 22.50 Job | 46.37 | 13.50 Job | 13.50 Job | 3.56 | 46.37 |
Total Amount: |
1295.18 |
|
100 |
1295.18 |
|
Remarks:
No Remarks
Work Program Made On:
31-10-2015
Updation of work program on:
25-10-2018
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 04-January-2016 | 43.73 lakhs |
2. | 27-January-2016 | 101.62 lakhs |
3. | 03-March-2016 | 79.23 lakhs |
4. | 29-March-2016 | 114.90 lakhs |
5. | 31-May-2016 | 84.42 lakhs |
6. | 11-July-2016 | 94.77 lakhs |
7. | 30-August-2016 | 16.00 lakhs |
8. | 24-October-2016 | 3.56 lakhs |
9. | 08-December-2016 | 0.69 lakhs |
10. | 23-December-2016 | 2.05 lakhs |
11. | 31-March-2017 | 80.32 lakhs |
12. | 30-June-2017 | 135.71 lakhs |
13. | 16-October-2017 | 111.64 lakhs |
14. | 24-November-2017 | 28.86 lakhs |
15. | 15-December-2017 | 120.89 lakhs |
16. | 23-March-2018 | 100.24 lakhs |
17. | 18-August-2018 | 58.98 lakhs |
18. | 16-November-2018 | 15.49 lakhs |
19. | 03-January-2017 | 80.97 lakhs |
20. | 08-March-2017 | 96.18 lakhs |
Total |
1370.25 lakhs |
% Payment |
101.2 % |
|
Advance Amount: 534.52 lakhs
Recovered Amount: 534.52 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 250 |
Number of Notice(s) issued: 89 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 15-07-2017 | Ch 2.360 | SRMD, slip due to heavy rain | Jagdish Narayan Meena | unknown | unknown | See Pic |
2. | 15-07-2017 | Ch 2.600 | SRMD, slip due to heavy rain | Jagdish Narayan Meena | unknown | unknown | See Pic |
3. | 15-07-2017 | Ch 4.100 | SRMD, slip but road open for traffic. | Jagdish Narayan Meena | unknown | unknown | See Pic |
4. | 15-07-2017 | Ch 4.150 | SRMD, slip due to heavy rain | Jagdish Narayan Meena | unknown | unknown | See Pic |
5. | 15-07-2017 | Ch 4.200 | SRMD, slip due to heavy rain | Jagdish Narayan Meena | unknown | unknown | See Pic |
6. | 15-07-2017 | Ch 4.300 | SRMD, slip clearance | Jagdish Narayan Meena | unknown | unknown | See Pic |
7. | 15-07-2017 | Ch 4.300 | SRMD, slip clearance by JCB | Jagdish Narayan Meena | unknown | unknown | See Pic |
8. | 15-07-2017 | Ch 4.300 | SRMD, slip due to heavy rain | Jagdish Narayan Meena | unknown | unknown | See Pic |
9. | 15-07-2017 | Ch 5.200 | SRMD, sinking due to heavy rain. | Jagdish Narayan Meena | unknown | unknown | See Pic |
10. | 15-07-2017 | Ch 4.100 | SRMD , slide due to heavy rain | Jagdish Narayan Meena | unknown | unknown | See Pic |
11. | 16-06-2017 | 6+280 | Caution tape and safety sign board during the work | Manoj Bhatt | RE | DSC2 R&B WB Pauri | See Pic |
12. | 16-06-2017 | 3+525 | WBM Grading-3 in Progress | Manoj Bhatt | RE | DSC2 R&B WB Pauri | See Pic |
13. | 08-06-2017 | Ch 2.400 | Instructions given by world bank mission | Jagdish Narayan Meena | unknown | unknown | See Pic |
14. | 07-06-2017 | 6+260 | PC stoped due to rain | Manoj Bhatt | RE | DSC2 R&B WB Pauri | See Pic |
15. | 25-05-2017 | HMP | PC work started | Manoj Bhatt | RE | DSC2 R&B WB Pauri | See Pic |
16. | 19-05-2017 | 5+100 | G3 rectified | Mohd. Ifran Qureshi | QC | DSC5 R&B WB Bageshwar | See Pic |
17. | 19-05-2017 | 0+010 | World bank visit | Mohd. Ifran Qureshi | QC | DSC5 R&B WB Bageshwar | See Pic |
18. | 18-05-2017 | Ch 3+450 | Rejected Emulsion | Sanjay Singh | Site Supervisor | DSC5 R&B WB Bageshwar | See Pic |
19. | 16-05-2017 | 5+100 | Rectification on defected WBM G3 surface | Manoj Bhatt | RE | DSC2 R&B WB Pauri | See Pic |
20. | 16-05-2017 | 5+100 | Rectification on WBM Gr3 | Manoj Bhatt | RE | DSC2 R&B WB Pauri | See Pic |
|
|