Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/PWD/08/05/RD/099 Agreement signed
Project: UDRP-RB Package No.: 110 Package Name: UDRP/PWD/08/05/RD/099 Sanction Cost: 1598.60  lakhs
District: Bageshwar Block: Garud Constituency: Bageshwar Circle: Pithoragarh WB Circle
DEA: DEA Bageshwar DSC: Royal Haskoning DHV DSC Scope: Design and Supervision No.of Sub project : 4
Subproject in this package
1  1136   Chaufala Mate Tilsari MR (6.000 KM.) (in prorgress)
2  1137   Dakghar Simghari MR (2.560 KM.) (in prorgress)
3  1138   Okadal Ana Loharchora Gairlaikh (6.000 KM.) (in prorgress)
4  1139   Kandhar Reetha Talla Parkoti Sirkot Patharkhani MR (6.000 KM.) (in prorgress)
Procurement:
Package No.: 110        Package Name: UDRP/PWD/08/05/RD/099        Tender Date: 27-06-2015        Current Status: Agreement signed        Achieved on Date: 24-09-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/08/05/RD/099        Contractor Name: Anil Malik Contractor       
Start Date: 01-10-2015        Intended Completion Date: 15-06-2017        Original End Date:  30-12-2016
Total Bond Cost: 152575316.91 (1525.75 lakhs)        Variation Cost: 6238867.06 (62.39 lakhs)     Hence Total Bond Cost is   158814183.97 (1588.14 lakhs) 
LD Analysis for Milestone1: calculated LD is Rs 2746368 for 36 days        LD Analysis for Milestone2: calculated LD is Rs 3661824 for 48 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence4.07 KM129.393.95 KM3.83 KM8.08125.26
2.R/Wall, B/ Wall Type Protection works3219.00 m275.553096.00 m3096.00 m17.3275.55
3.GSB/RBI/G-119.46 KM275.5819.37 KM19.37 KM17.51275.58
4.G-319.46 KM144.3319.43 KM18.78 KM8.84139.38
5.PC/CC i/c Prime Coat, Tack Coat19.46 KM266.7519.43 KM15.23 KM13.55207.74
6.Cause Way7.00 No52.716.00 No4.00 No1.9931.90
7.Culverts/Scupper 81.00 No190.8864.00 No64.00 No11.73190.88
8.longitudinal Drain18691.00 m122.2818691.00 m16586.00 m6.71103.34
9.Crash Barrier1430.00 m39.511332.00 m979.00 m1.9730.29
10.Parapet786.00 No22.29786.00 No666.00 No1.3118.87
11.Road Furniture628.00 No6.72626.00 No514.00 No0.355.32
12.Other Allied Works & Finishing Work 9.00 Job62.009.00 Job0.00 Job00.00
Total Amount: 1587.99 89.35   1404.11
Remarks: No Remarks       Work Program Made On: 21-11-2015       Updation of work program on: 14-05-2017      
Work Program Status:This Package contain more than one subproject,pleae check individua subproject for Program Expired.
Financial Progress
SNo. Date Payment
1.29-February-2016207.70  lakhs
2.29-March-201657.75  lakhs
3.30-April-2016133.03  lakhs
4.28-June-2016170.00  lakhs
5.12-August-201692.33  lakhs
6.29-September-2016126.10  lakhs
7.22-October-2016255.51  lakhs
8.08-December-20160.76  lakhs
9.21-December-20162.72  lakhs
10.13-January-201795.71  lakhs
11.02-February-20170.26  lakhs
12.27-April-201767.29  lakhs
13.21-June-2017107.52  lakhs
Total 1316.68  lakhs
% Payment 82.91 %
Advance Amount:  625.98  lakhs        Recovered Amount:  555.41  lakhs        Balance to be Recovered  70.57  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Environment & Social Compliances(Package level):No Pending Issue
Environment & Social Compliances(Sub Project level):
Chaufala Mate Tilsari MR(1136) Signs, Query
Dakghar Simghari MR(1137) Signs, debris disposal, Query
Okadal Ana Loharchora Gairlaikh(1138) Signs, debris disposal, Query
Kandhar Reetha Talla Parkoti Sirkot Patharkhani MR(1139) Signs, debris disposal, Query
Detailed report of this Package
Quality
No. of Test Required : 1479     No. of Test Done : 1389      No. of Test Passed : 1336      No. of Test Failed : 53   Test report of this package
Number of Pics Available on Web Repository: 286
Number of Notice(s) issued: 63

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.14-06-20171+700Seal coat over pc surface in progressManoj BhattREDSC5 R&B WB Bageshwar See Pic
2.14-06-20171+800Seal coat on pc surface in progressManoj BhattREDSC5 R&B WB Bageshwar See Pic
3.08-06-20173+550G3 Rolling, Work in progressMohd Irfan QureshiQCDSC5 R&B WB Bageshwar See Pic
4.13-05-20171+500G3 work in progressMohd. Ifran QureshiQCDSC5 R&B WB Bageshwar See Pic
5.12-05-2017Anil malik contractor labWBM G 3 gradation test reportJagdish Narayan MeenaAEUDRP R&B Bageshwar See Pic
6.12-05-2017Ch 0.700Sample collection for WBM G3 greadation test and AIV test .Jagdish Narayan MeenaAEUDRP R&B Bageshwar See Pic
7.06-05-2017End PointOn end point of the road parapet s and warning sign board requiredManoj BhattREDSC5 R&B WB Bageshwar See Pic
8.06-05-2017End pointEnd point of Road required safety sign and parapet wallManoj BhattREDSC5 R&B WB Bageshwar See Pic
9.05-05-2017Anil malik labWBM G3 Gradation reportMohd. Ifran QureshiQCDSC5 R&B WB Bageshwar See Pic
10.05-05-2017Anil malik labGradation of WBM G3Mohd. Ifran QureshiQCDSC5 R&B WB Bageshwar See Pic
11.05-05-20170+700Super elevation check and found 7%.Mohd. Ifran QureshiQCDSC5 R&B WB Bageshwar See Pic
12.05-05-20170+750Providing screening on G3Mohd. Ifran QureshiQCDSC5 R&B WB Bageshwar See Pic
13.05-05-20170+730G3 layingMohd. Ifran QureshiQCDSC5 R&B WB Bageshwar See Pic
14.04-05-20170+825Social Experts Discuss with workering labours working at siteManoj BhattREDSC5 R&B WB Bageshwar See Pic
15.04-05-20170+750Social Experts discussions with road users.Manoj BhattREDSC5 R&B WB Bageshwar See Pic
16.04-05-20170+750Discuss with Villagers Mr. CS Pandey (mob. No. 9967270096) social experts Dr. S ROY & Mr. CS Tyagi.Manoj BhattREDSC5 R&B WB Bageshwar See Pic
17.04-05-20170+750WBM gr-3, Spreading in ProgressManoj BhattREDSC5 R&B WB Bageshwar See Pic
18.04-05-20170+875Social Experts verifing social compliancesManoj BhattREDSC5 R&B WB Bageshwar See Pic
19.04-05-20170+000Social experts visit to verify the compliancesManoj BhattREDSC5 R&B WB Bageshwar See Pic
20.04-05-2017Piu office in bageshwar, Environment expert Dr. Sameer Ray discussions EE, RE, JEEnvironment expert discuss with EE and RE, JEMohd. Ifran QureshiQCDSC5 R&B WB Bageshwar See Pic