UDRP/PWD/08/05/RD/099
Agreement signed
|
Project: |
UDRP-RB |
Package No.: |
110 |
Package Name: |
UDRP/PWD/08/05/RD/099 |
Sanction Cost: |
1598.60 lakhs |
District: |
Bageshwar |
Block: |
Garud |
Constituency: |
Bageshwar |
Circle: |
Pithoragarh WB Circle |
DEA: |
DEA Bageshwar |
DSC: |
Royal Haskoning DHV |
DSC Scope: |
Design and Supervision |
No.of Sub project : |
4 |
Subproject in this package |
1 1136 Chaufala Mate Tilsari MR (6.000 KM.) (completed) | 2 1137 Dakghar Simghari MR (2.560 KM.) (completed) | 3 1138 Okadal Ana Loharchora Gairlaikh (6.000 KM.) (completed) | 4 1139 Kandhar Reetha Talla Parkoti Sirkot Patharkhani MR (6.000 KM.) (completed) |
|
Procurement: |
Package No.: 110
Package Name: UDRP/PWD/08/05/RD/099
Tender Date: 27-06-2015
Current Status: Agreement signed
Achieved on Date: 24-09-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/08/05/RD/099
Contractor Name: Anil Malik Contractor
|
Start Date: 01-10-2015
Intended Completion Date: 10-10-2017
Original End Date: 30-12-2016
|
Total Bond Cost: 152575316.91 (1525.75 lakhs)
Variation Cost: 4156629.06 (41.57 lakhs) Hence Total Bond Cost is 156731945.97 (1567.32 lakhs)
|
LD Analysis for Milestone1: calculated LD is Rs 2746368 for 36 days
LD Analysis for Milestone2: calculated LD is Rs 3661824 for 48 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Hill side Cutting & Slip clearence | 4.07 KM | 137.42 | 3.83 KM | 3.83 KM | 8.83 | 137.42 | 2. | R/Wall, B/ Wall Type Protection works | 3219.00 m | 275.55 | 3096.00 m | 3096.00 m | 17.3 | 275.55 | 3. | GSB/RBI/G-1 | 19.35 KM | 275.58 | 19.37 KM | 19.37 KM | 17.51 | 275.58 | 4. | G-3 | 19.35 KM | 144.33 | 19.43 KM | 19.43 KM | 9.11 | 144.33 | 5. | PC/CC i/c Prime Coat, Tack Coat | 19.35 KM | 266.76 | 19.46 KM | 19.46 KM | 16.84 | 266.76 | 6. | Cause Way | 7.00 No | 52.71 | 6.00 No | 6.00 No | 3.15 | 52.71 | 7. | Culverts/Scupper | 81.00 No | 190.88 | 64.00 No | 64.00 No | 11.73 | 190.88 | 8. | longitudinal Drain | 18607.00 m | 121.37 | 18691.00 m | 18691.00 m | 7.71 | 121.37 | 9. | Crash Barrier | 1430.00 m | 39.52 | 1629.00 m | 1629.00 m | 2.49 | 39.52 | 10. | Parapet | 786.00 No | 22.30 | 686.00 No | 686.00 No | 1.5 | 22.30 | 11. | Road Furniture | 628.00 No | 6.72 | 709.00 No | 709.00 No | 0.42 | 6.72 | 12. | Other Allied Works & Finishing Work | 5.00 Job | 55.00 | 9.00 Job | 9.00 Job | 3.41 | 55.00 |
Total Amount: |
1588.14 |
|
100 |
1588.14 |
|
Remarks:
No Remarks
Work Program Made On:
21-11-2015
Updation of work program on:
28-11-2017
|
|
Work Program Status:This Package contain more than one subproject,pleae check individua subproject for Program Expired. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 29-February-2016 | 207.70 lakhs |
2. | 29-March-2016 | 57.75 lakhs |
3. | 30-April-2016 | 133.03 lakhs |
4. | 28-June-2016 | 170.00 lakhs |
5. | 22-October-2016 | 255.51 lakhs |
6. | 21-December-2016 | 2.72 lakhs |
7. | 13-January-2017 | 95.71 lakhs |
8. | 02-February-2017 | 0.26 lakhs |
9. | 27-April-2017 | 67.29 lakhs |
10. | 21-June-2017 | 107.52 lakhs |
11. | 21-August-2017 | 54.78 lakhs |
12. | 08-September-2017 | 0.37 lakhs |
13. | 27-September-2017 | 96.29 lakhs |
14. | 16-October-2017 | 32.20 lakhs |
15. | 24-November-2017 | 69.68 lakhs |
16. | 16-November-2018 | 10.19 lakhs |
17. | 12-August-2016 | 92.33 lakhs |
18. | 08-December-2016 | 0.76 lakhs |
19. | 29-September-2016 | 126.10 lakhs |
Total |
1580.19 lakhs |
% Payment |
100.82 % |
|
Advance Amount: 625.98 lakhs
Recovered Amount: 625.98 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 286 |
Number of Notice(s) issued: 70 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 14-06-2017 | 1+700 | Seal coat over pc surface in progress | Manoj Bhatt | RE | DSC2 R&B WB Pauri | See Pic |
2. | 14-06-2017 | 1+800 | Seal coat on pc surface in progress | Manoj Bhatt | RE | DSC2 R&B WB Pauri | See Pic |
3. | 08-06-2017 | 3+550 | G3 Rolling, Work in progress | Mohd Irfan Qureshi | QC | DSC5 R&B WB Bageshwar | See Pic |
4. | 13-05-2017 | 1+500 | G3 work in progress | Mohd. Ifran Qureshi | QC | DSC5 R&B WB Bageshwar | See Pic |
5. | 12-05-2017 | Anil malik contractor lab | WBM G 3 gradation test report | Jagdish Narayan Meena | unknown | unknown | See Pic |
6. | 12-05-2017 | Ch 0.700 | Sample collection for WBM G3 greadation test and AIV test . | Jagdish Narayan Meena | unknown | unknown | See Pic |
7. | 06-05-2017 | End Point | On end point of the road parapet s and warning sign board required | Manoj Bhatt | RE | DSC2 R&B WB Pauri | See Pic |
8. | 06-05-2017 | End point | End point of Road required safety sign and parapet wall | Manoj Bhatt | RE | DSC2 R&B WB Pauri | See Pic |
9. | 05-05-2017 | Anil malik lab | WBM G3 Gradation report | Mohd. Ifran Qureshi | QC | DSC5 R&B WB Bageshwar | See Pic |
10. | 05-05-2017 | Anil malik lab | Gradation of WBM G3 | Mohd. Ifran Qureshi | QC | DSC5 R&B WB Bageshwar | See Pic |
11. | 05-05-2017 | 0+700 | Super elevation check and found 7%. | Mohd. Ifran Qureshi | QC | DSC5 R&B WB Bageshwar | See Pic |
12. | 05-05-2017 | 0+750 | Providing screening on G3 | Mohd. Ifran Qureshi | QC | DSC5 R&B WB Bageshwar | See Pic |
13. | 05-05-2017 | 0+730 | G3 laying | Mohd. Ifran Qureshi | QC | DSC5 R&B WB Bageshwar | See Pic |
14. | 04-05-2017 | 0+825 | Social Experts Discuss with workering labours working at site | Manoj Bhatt | RE | DSC2 R&B WB Pauri | See Pic |
15. | 04-05-2017 | 0+750 | Social Experts discussions with road users. | Manoj Bhatt | RE | DSC2 R&B WB Pauri | See Pic |
16. | 04-05-2017 | 0+750 | Discuss with Villagers Mr. CS Pandey (mob. No. 9967270096) social experts Dr. S ROY & Mr. CS Tyagi. | Manoj Bhatt | RE | DSC2 R&B WB Pauri | See Pic |
17. | 04-05-2017 | 0+750 | WBM gr-3, Spreading in Progress | Manoj Bhatt | RE | DSC2 R&B WB Pauri | See Pic |
18. | 04-05-2017 | 0+875 | Social Experts verifing social compliances | Manoj Bhatt | RE | DSC2 R&B WB Pauri | See Pic |
19. | 04-05-2017 | 0+000 | Social experts visit to verify the compliances | Manoj Bhatt | RE | DSC2 R&B WB Pauri | See Pic |
20. | 04-05-2017 | Piu office in bageshwar, Environment expert Dr. Sameer Ray discussions EE, RE, JE | Environment expert discuss with EE and RE, JE | Mohd. Ifran Qureshi | QC | DSC5 R&B WB Bageshwar | See Pic |
|
|