UEAP/PWD/C-83B Agreement signed
Project: UEAP-RB Package No.: 1098 Package Name: UEAP/PWD/C-83B Sanction Cost: 1787.00  lakhs
District: Nainital Block: Haldwani Constituency: Lalkuan Circle:
DEA: DEA UEAP Nainital DSC: Sheladia Associates DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  5915   Ramnagar Kaladungi Haldwani Kathgodam Chorgaliya Sitarganj Bijti MR Phase 4 (Km. 77 to 87.30) (11.300 KM.) (completed)
Procurement:
Package No.: 1098        Package Name: UEAP/PWD/C-83B        Tender Date: 30-01-2016        Current Status: Agreement signed        Achieved on Date: 02-04-2016

Construction Phase

Agreement Details
Bond/Agreement Name: UEAP/PWD/C-83B        Contractor Name: Raj Shyama Constructions Pvt. Ltd       
Start Date: 12-04-2016        Intended Completion Date: 11-12-2016       
Total Bond Cost: 114675232 (1146.75 lakhs)        Variation Cost: 32316921.45 (323.17 lakhs)     Hence Total Bond Cost is   146992153.45 (1469.92 lakhs) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.R/Wall, B/ Wall Type Protection works3360.00 m287.283360.00 m3360.00 m20.76287.28
2.PC/CC i/c Prime Coat, Tack Coat3.39 KM61.723.39 KM3.39 KM4.4661.72
3.BM i/c Prime Coat, Tack Coat11.30 KM687.6911.30 KM11.30 KM49.7687.69
4.SDBC i/c Tackcoat11.30 KM194.8511.30 KM11.30 KM14.08194.85
5.Cause Way3.00 No43.713.00 No3.00 No3.1643.71
6.Culverts/Scupper 9.00 No77.148.00 No8.00 No5.5777.14
7.Crash Barrier1310.00 m29.481310.00 m1310.00 m2.1329.48
8.Road Furniture75.00 No1.8875.00 No75.00 No0.141.88
Total Amount: 1383.75 100   1383.75
Remarks: No Remarks       Work Program Made On: 11-07-2016       Updation of work program on: 25-05-2017      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.30-April-2016216.45  lakhs
2.31-May-2016238.78  lakhs
3.02-June-2016174.85  lakhs
4.23-June-2016178.18  lakhs
5.31-August-201679.28  lakhs
6.27-October-2016106.98  lakhs
7.28-November-2016151.32  lakhs
8.28-February-2017165.21  lakhs
9.25-March-201759.57  lakhs
10.30-May-201729.76  lakhs
11.22-June-201741.62  lakhs
Total 1442  lakhs
% Payment 98.1 %
Advance Amount:  0.00  lakhs        Recovered Amount:  0.00  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 1531     No. of Test Done : 1532      No. of Test Passed : 1521      No. of Test Failed : 3   Test report of this package
Number of Pics Available on Web Repository: 41
Number of Notice(s) issued: 28

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.28-12-2016Chainage 83+700Thermoplast work on the roadRajiv GururaniEEUEAP R&B Nainital See Pic
2.28-12-2016Chainage 84+900Thermoplast work on roadRajiv GururaniEEUEAP R&B Nainital See Pic
3.28-12-2016Chainage 80+400Culvert after completionRajiv GururaniEEUEAP R&B Nainital See Pic
4.28-12-2016Chainage 80+400Culvert after completionRajiv GururaniEEUEAP R&B Nainital See Pic
5.28-12-2016Chainage 76+400Thermoplast work is onRajiv GururaniEEUEAP R&B Nainital See Pic
6.29-11-2016Chainage 80+400Checking Crust & Bituminous thickness at the affected area where road damagedRajiv GururaniEEUEAP R&B Nainital See Pic
7.29-11-2016Chainage 77+400DBM work in the approaches of culverts is in progressRajiv GururaniEEUEAP R&B Nainital See Pic
8.08-11-2016Chainage 85+450Inspection of thermoplast by SE SirRajiv GururaniEEUEAP R&B Nainital See Pic
9.08-11-2016Chainage 80+425SE sir inspection of portion that become uneven due to rains last monthRajiv GururaniEEUEAP R&B Nainital See Pic
10.02-11-2016At plantBitumen Content test for BCLalit TiwariAEDEA ADB Nainital See Pic
11.02-11-201683+700Construction of CausewayLalit TiwariAEDEA ADB Nainital See Pic
12.02-11-2016At PlantCompressive LoadLalit TiwariAEDEA ADB Nainital See Pic
13.02-11-2016At LabBitumen Content testLalit TiwariAEDEA ADB Nainital See Pic
14.02-11-2016At LabConcrete cube weight .taking before loding for Compressive TestLalit TiwariAEDEA ADB Nainital See Pic
15.02-11-2016At plantTesting of BC mixLalit TiwariAEDEA ADB Nainital See Pic
16.02-11-2016At plantBitumen content testLalit TiwariAEDEA ADB Nainital See Pic
17.02-11-201683+200SE sir Site InspectionLalit TiwariAEDEA ADB Nainital See Pic
18.28-10-201679+0506.mSpan steel work in progressAnil KumarJEUEAP R&B Nainital See Pic
19.16-10-2016Chainage 80.400Inspection of Road at Chainage 80+400 by Chief Engg Haldwani which was settled during the rainy season .C E sir suggested treatment to be optedRajiv GururaniEEUEAP R&B Nainital See Pic
20.14-10-2016Chainage 80+425Checking crustRajiv GururaniEEUEAP R&B Nainital See Pic