Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UEAP/PWD/C91 Agreement signed
Project: UEAP-RB Package No.: 1095 Package Name: UEAP/PWD/C91 Sanction Cost: 396.00  lakhs
District: Tehri Block: Jaunpur Constituency: Dhanaulti Circle:
DEA: DEA UEAP Tehri DSC: TPF Getinsa Euroestudios S.L. DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  5337   Aglad Thatyur Motor Road (Chronic Slip Zone) (0.200 KM.) (in prorgress)
Procurement:
Package No.: 1095        Package Name: UEAP/PWD/C91        Tender Date: 11-09-2015        Current Status: Agreement signed        Achieved on Date: 18-04-2016

Construction Phase

Agreement Details
Bond/Agreement Name: UEAP/PWD/C91        Contractor Name: Shiv Shankar Construction Company       
Start Date: 12-05-2016        Intended Completion Date: 30-06-2017        Original End Date:  11-03-2017
Total Bond Cost: 37113251.2 (371.13 lakhs)        Variation Cost: 5538382.15 (55.38 lakhs)     Hence Total Bond Cost is   42651633.35 (426.52 lakhs) 
LD Analysis for Milestone1: calculated LD is Rs 742280 for 40 days        LD Analysis for Milestone2: calculated LD is Rs 1020635 for 55 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence0.20 KM125.440.20 KM0.15 KM22.0694.08
2.R/Wall, B/ Wall Type Protection works200.00 m170.41200.00 m200.00 m39.95170.41
3.Other Allied Works & Finishing Work 4.00 Job130.674.00 Job2.00 Job15.3265.33
Total Amount: 426.52 77.33   329.82
Remarks: No Remarks       Work Program Made On: 21-07-2017       Updation of work program on: 31-07-2017      
Work Program Status:Program Expired.
Financial Progress
SNo. Date Payment
1.05-October-201676.94  lakhs
2.01-December-201647.15  lakhs
3.28-March-2017132.83  lakhs
4.07-June-201766.28  lakhs
5.19-July-201754.27  lakhs
6.31-August-201714.82  lakhs
7.25-September-201711.63  lakhs
Total 403.92  lakhs
% Payment 94.7 %
Advance Amount:  37.00  lakhs        Recovered Amount:  37.00  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Analysis:Physical Progress Wrongly Reported.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):Staff not deputed yet
Environment & Social Compliances(Sub Project level):
Aglad Thatyur Motor Road (Chronic Slip Zone)(5337)No Pending Issue
Detailed report of this Package
Quality
Test Information not Available.
Number of Pics Available on Web Repository: 37
Number of Notice(s) issued: 48

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.07-09-2017Part aSite conditionKishan Singh RawatJEUEAP R&B Tehri See Pic
2.07-09-2017Part aPresent site conditionKishan Singh RawatJEUEAP R&B Tehri See Pic
3.07-09-2017A PartSite visit by se sir and THDC teamKishan Singh RawatJEUEAP R&B Tehri See Pic
4.07-09-2017A PartPresent site condition of siteKishan Singh RawatJEUEAP R&B Tehri See Pic
5.07-09-2017A PartSMRD silip clearancesKishan Singh RawatJEUEAP R&B Tehri See Pic
6.07-09-2017A PartBbKishan Singh RawatJEUEAP R&B Tehri See Pic
7.07-09-2017RHyKishan Singh RawatJEUEAP R&B Tehri See Pic
8.26-07-2017A PartTHDC site visit c-91Kishan Singh RawatJEUEAP R&B Tehri See Pic
9.17-07-2017A partSRMD,Site Clearance part 'A'Kishan Singh RawatJEUEAP R&B Tehri See Pic
10.17-07-2017Part ASRMD,Site clearance part 'A'Kishan Singh RawatJEUEAP R&B Tehri See Pic
11.17-07-2017Part ASRMD,Site Clearance part 'A'Kishan Singh RawatJEUEAP R&B Tehri See Pic
12.09-06-2017Part a3d netAmit Kumar 2AEUDRP AF S&B Bageshwar See Pic
13.09-06-2017Part bBreast wallAmit Kumar 2AEUDRP AF S&B Bageshwar See Pic
14.09-06-2017Part bGabion layingAmit Kumar 2AEUDRP AF S&B Bageshwar See Pic
15.17-05-2017A part3D netKishan Singh RawatJEUEAP R&B Tehri See Pic
16.17-05-2017A partGabions wallKishan Singh RawatJEUEAP R&B Tehri See Pic
17.17-05-2017A partSite visit C 91THDC TeamKishan Singh RawatJEUEAP R&B Tehri See Pic
18.17-05-2017B partsite visit C-91 THDC teamKishan Singh RawatJEUEAP R&B Tehri See Pic
19.17-05-2017A part3D netKishan Singh RawatJEUEAP R&B Tehri See Pic
20.17-05-2017B partB/wKishan Singh RawatJEUEAP R&B Tehri See Pic